USAID Sector Reform and Utility Commercialization
(SRUC): Haiti CPU Transaction Project
Deliverable 11: Guidelines & Recommendations for Conducting a
Competitive Procurement, Reflecting Haitian Law & International Leading
Practice
January 2017
PROCUREMENT METHODS BASED on
INTERNATIONAL LEADING PRACTICE
2
Caracol Power Utility (CPU) Procurement Objective
Engage a technically and financially well-qualified private partner that will manage
the CPU in the longer term, including:
•Investment in additional generation and distribution capacity and replacement
o
f depreciated assets.
•Funding of any negative operating cash f
lows.
•Acceptance of
all financial risks, ideally without subsidies from Government of
Haiti (GoH).
Therefore:
The goal should be to maximize competition with a transparent international
tender
3
Following are fundamental principles recommended in the Guidebook and based
on international leading practice:
Transparency:
−Information shar
ing & evaluation criteria
Neutrality:
−Tender rules that “do not provide scope for discretion”
−S
ufficient time fo
r potential private partners to assess the opportunity
and prepare bids.
Non-discrimination:
−“Equal treatment…foreign & domestic”
4
United Nations PPP Guidebook
Reference: Guidebook on Promoting Good Governance in Public-Private Partnerships, 2008
–Over 80 PPPs awarded since 1991
–R
esponsibility fo
r the Concessions with the
Coordination Department at the Ministry
of Public Works
–Categories: Highways,
airports, reservoirs,
ports, urban transport, hospitals
–Electricity sector 100%
privatized (not
PPP) and unbundled, beginning in 1986:
* Generation – 26 private companies
* Transmission – 5 private companies
* Distribution – 25 private companies
5
Chile: Positive PPP & Privatization Examples
Can we add a
picture or a
map?
Reference: “Chilean Experience in Public Private Partnership,” José Miguel Hidalgo, August 2014
Public & Private participation in Chile’s Electricity Sector
The following tenets were central to the procurement process for Chilean PPPs:
−Competitive and o pen to domestic and foreign bidders
−Post-tender negotiation a
voided
−Transparent:
•Widely advertised
•R
esults made public
PPP Contracts
−Renegotiations during contract term restricted since 2010, giving more
con
fidence to investors.
6
Chile: PPP Procurement Process Fundamental to Success
Reference: “The Promise and Peril of Public- Private Partnerships: Lessons from the Chilean Experience,” International Growth Center, London, June 2011
A standard infrastructure procurement has three key steps
based on international leading practice and historically
successful PPPs
1
2
3
Request for Expressions of Interest (EOI)
Request for Proposals (RFP)
Selection of Winning Bidder and Contracting
7
Pre-qualification process:
−Advertise EOI domestically and internationally
−Direct solicitations: Permissible, but must be unbiased & transparent
−Project information: not necessarily the full Information Memorandum but
suf
ficient to provide key details on the asset
−Period to submit EOI: About six weeks is sufficient based on leading
prac
tice
8
Step 1: Request for Expressions of Interest (REI)
−Not unreasonably confining – w ould undermine competition
−Reasonable technical & financial qualification criteria (Private entities may
partne
r with other entities)
−Pre-qualifications criteria made a
vailable to parties expressing interest
−Pre-qualified bi
dders published on Internet
Pre-qualification Criteria
9
Pre-qualified bidders may request tender documents to inform their decision bid:
−Information memorandum
−Obligations of private partner (cahier des charges)
−Tender rules
oProposal requirements & submission deadline
oBid evaluation criteria
−Draft contract
Fur
thermore, the pre-qualified bidders would typically have rights to:
−Site visits
−Data Room access
10
Step 2: Request for Proposals (RFP)
Selection criteria should be objective, transparent, and simple; in order to
maximize transparency, avoid subjective weighting when feasible
Private partner’s investment & other obligations should be clearly stated in tender
conditions.
Leading Practice Utilizes the Following Criteria:
−Winning bid: Ideally, single selection criterion, e.g. highest annual lease
payment to government or lowest affermage fee to private partner
−Technical and financial qualifications of bidder: Should be
principally addressed in prequalification phase
11
Selection Criteria for Winning Bidder
Selection committee is responsible for upholding transparency
HAITIAN LAW RELEVANT FOR THE CPU
TRANSACTION
12
−Collaboration between the two Ministries throughout the CPU PPP
pr
ocess.
−Ministry of Public Works (Tr
avaux Publics), through its Energy Cell, is the
“relevant ministry” and therefore takes the leading policy role in
preparation of Information Memorandum and Cahier des Charges.
−Ministry of Economy & Finance (MEF) takes the leading role in preparing
the
Request for Expressions of Interest, the Request for Proposals, and
Contracting with the winning bidder.
−The foregoing Tender Documentation must be approved by the
Co
mmission Nationale des Marchés Publics, with final approval by the
Cour des Comptes.
13
Roles of the Ministries of Finance and Public Works
−PPP Unit pre pares tender documentation in consultation with relevant
ministry (Travaux Publics in for Caracol Utility)
−Commission Nat
ionale des Marchés Publics (CNMP) must review
documentation
−Cour Superieur de
s Comptes must give final approval to government
contracts, including tender documents
−Settlement of
disputes (Article 95): Superseded by Haiti’s approval of
the International Centre for Settlement of Investment Disputes (ICSID)
Convention approved by Haiti in 2009
−International arbitrator sh
ould be selected if winning bidder is a
foreign entity, which is permitted under the law.
14
GoH Public Procurement & Concession Act of 2009
−The CMEP law would apply if CPU w ere deemed to be a “public
enterprise”.
−In that case, a concession of a public enterprise requires parliamentary
appr
oval.
−Based upon discussions with GoH officials, their view is
:
•Referencing the
17 May 2005 decree on the “Organization de
l’Administration Centrale de l’Etat,” CPU is not established by law
or constitution and therefore is not a public enterprise.
•Therefore the
CMEP Law would not apply, and Parliamentary
approval of the CPU concession is not required.
15
Modernization of Public Enterprises Law (CMEP Law)
−Constitution: Muni cipal Councils have authority over the state private
domain real estate.
−Decentralization Decree of 2006:
Responsibilities of local
authorities/municipalities include the energy sector.
−Identify author
izations granted to EdH, Ministry of Travaux Publics, or
Ministry of Finance for land occupied by distribution lines and for
provision of electricity services in relevant service area.
−Verify if author
izations are transferable to private partners.
16
Authority of the Haitian Municipalities
−Tariffs as- year tax holiday for private partner, as for other
occupants of Caracol Industrial Park.
−If no tax holiday, commercially viable tariffs would need to be highe
r.
−Formal GoH approval of tax holiday is needed.
17
Potential Tax Holiday
2016 PRESIDENTIAL ENERGY SECTOR DECREES and
FUTURE IMPLICATIONS FOR ATTRACTING PRIVATE
PARTNERS
18
−Promote competition and private sector participation in generation,
trans
mission, distribution, and commercialization.
−Licenses and
management contracts to be subject to public service
procedures of procurement and concessions.
−Tariffs and licensing would be under authority of proposed new
re
gulatory agency.
19
GoH Decrees Governing the Electrical Energy Sector have
the following characteristics relevant to the CPU:
Government of Haiti is preparing amendments to the three energy sector decrees of February
2016
−ANARSE, the elect ricity sector regulator is not yet established.
−The amendments to the February 2016 Regulatory Decree are
in the
process of being drafted by a committee in the Office of the Prime
Minister, and will subsequently need Parliamentary approval.
−ANARSE would have authority to reform tariffs and license private
ope
rators, in line with leading practice for regulatory authorities
−According to the Letters of Implementation signed by GoH and US
AID in
August 2016: Prior to the establishment of ANARSE the Ministries of
Travaux Public, Finance, and Planning have authority to revise tariffs in
communes served by Caracol Power Utility.
20
Regulatory Authority (ANARSE) Decree (February 2016)
Government of Haiti is currently preparing amendments to the three energy sector
decrees of February 2016
According to the subject decree, EDH should “maintain energy tariffs at a level
enabling it to defray at least” the following:
–All operating expenses
–Debt interest and principal payments
–Amortization of fixed assets
–Profit corresponding to a rate of return on investment as specified by the
re
gulatory authority.
21
Electricité d’Haiti Decree (February 2016)
Government of Haiti is currently preparing amendments to the three energy sector
decrees of February 2016
POTENTIAL CPU CONCESSION STRUCTURE
EXAMPLES DISCUSSED WITH THE GOVERNMENT OF
HAITI, BASED ON INTERNATIONAL LEADING PRACTICE
22
Based on international examples and on sessions with the MEF, Ministry of Public
Works, and NRECA (the current CPU operator), the GoH is considering the
following criteria for potential inclusion in the CPU REI:
Financial:
−Sufficient financial capacity to finance US$7 million or more i
n capital
investment, Years 1 to 3 (Ref: Session 2 slide)
−Audited financial statements of the c
andidate
Technical:
−Successful manage
ment of an electric utility
−Experience in o
perating generation, transmission, or distribution.
23
Example: Potential Prequalification Criteria for CPU
Based on international examples and on sessions with the MEF, Ministry of Public
Works, and NRECA (the current CPU operator), the GoH is considering the
following as integral components of a CPU concession:
Full financial responsibility:
−Finance operations & i
nvestments (with no subsidies from GOH)
−Annual lease payments to government for existing assets
−M
ake ~$300,000 annual co
ntribution for 16 years to independent reserve
escrow fund toward 2032 replacement investments (Private partner will
be responsible for shortfall)
Full management responsibility:
−Generation, distribution, and collection for a period of 30 yea
rs
24
Example: Private Partner Concession Obligations (1)
Based on international examples and on sessions with the MEF, Ministry of Public
Works, and NRECA (the current CPU operator), the GoH is considering the
following as integral components of a CPU concession:
Service area:
−Complete expansion in current communes & Fort Li
berté
Electricity supply:
−24 hour supply, subject to reasonable availability (e.g. 98%)
Empl
oyment:
−Engage current Haitian PPSELD employees for their experience and
as
sistance with expansion
25
Example: Private Partner Concession Obligations (2)
Based on international examples and on sessions with the MEF, Ministry of Public
Works, and NRECA (the current CPU operator), the GoH is considering
commitment to the following to attract a private partner:
−Accept 30-y
replacements.
−Grant rights to private partner to use of new assets for term of
co
ncession.
−Abide by tariff schedule and quarterly adjustment formula specified in
t
ender documentation throughout term of concession.
−Set and monitor safety s
tandards.
−Set and monitor environmental s
tandards.
26
Example: Potential Government Obligations
Based on international examples and on sessions with the MEF, Ministry of Public
Works, and NRECA (the current CPU operator), the GoH is considering the
following criteria for potential inclusion in the CPU RFP:
Deadline for submitting bids
−At least three months after pr
equalification period and launch of Request
for Proposals.
Expansion options for private partner, three- year decision period:
−Ouanaminthe & Ferrier
−Quartier Morin
−Cap Haïtien
27
Example: Potential Tender Conditions (1)
Based on international examples and on sessions with the MEF, Ministry of Public
Works, and NRECA (the current CPU operator), the GoH is considering the
following criteria for potential inclusion in the CPU RFP:
Bid Criterion:
−Highest annual lease payments for term of lease, or
−L
owest tariffs proposed
−Single criterion is ideal for transparency, as prequalification addresses
othe
r requirements. Consistent with UN neutrality principle and World
Bank Group preference.
Potential second criterion:
−Minimum investment commitment for expansion options
−W
ould require weighting of cr
iteria
28
Example: Potential Tender Conditions (2)
GOH identified the next steps to launch a CPU PPP tender,
based on leading practice
1
2
3
4
5
Determine Appropriate Tariff Level & Adjustment Formula
Tariff levels are fundamental to design of the PPP
PPP Type Selection
Approval of PPP type by GoH and USAID/Haiti
Engage Government Entities
Sequencing of engagement of government entities
Draft Tender Documentation
Including Pre-qualification, Information Memorandum, Tender Rules
Launch REI, Determine Pre- qualified Bidders, then Launch RFP
Develop time frame to launch REI and RFPs
29
END
30
Deloitte refers to one or more of Deloitte Touche Tohmatsu Limited, a UK private company limited by guarantee (“DTTL”), its network of member firms, and their related entities. DTTL and each of its
member firms are legally separate and independent entities. DTTL (also referred to as “Deloitte Global”) does not provide services to clients. Please see www.deloitte.com/about to learn more about our
global network of member firms. Deloitte provides audit, consulting, financial advisory, risk management, tax and related services to public and private clients spanning multiple industries. Deloitte serves four
out of five Fortune Global 500® companies through a globally connected network of member firms in more than 150 countries and territories bringing world-class capabilities, insights, and high-quality
service to address clients’ most complex business challenges. This communication contains general information only, and none of Deloitte Touche Tohmatsu Limited, its member firms, or their related
entities (collectively, the “Deloitte network”) is, by means of this communication, rendering professional advice or services. Before making any decision or taking any action that may affect your finances or
your business, you should consult a qualified professional adviser. No entity in the Deloitte network shall be responsible for any loss whatsoever sustained by any person who relies on this communication.
© 2016 Deloitte Consulting LLP
31