Audit of Procurement Procedures — Ministry of Public Works, Transport and Communications (MTPTC), FY 2014-2015
- MTPTC's procurement procedures show significant non-compliance with legal and regulatory frameworks, including insufficient competition and inadequate documentation.
- The CMMP does not fully perform its regulatory and oversight role, lacking resources and failing to submit activity reports to the CNMP.
- Contractual documents often lack essential administrative and technical clauses, leading to broad interpretations, addendums, and poor quality control.
- Many contracts, especially those by direct agreement, were not justified under normal conditions and showed unrealistic execution deadlines and non-application of penalties.
- Archiving systems are non-existent or inadequate, and personnel lack training, hindering proper contract management and accountability.
This final audit report, commissioned by the Project Coordination Unit (UCP) of the Ministry of Economy and Finance and conducted by Daniel Thirion International (DTI) with local firm FARUD, scrutinizes the public procurement and contractual management procedures of the Ministry of Public Works, Transport and Communications (MTPTC) for the 2014-2015 fiscal year. The mission, part of a broader economic governance reform, aimed to verify the regularity, conformity, and adherence to principles of economy, transparency, efficiency, and equity in public contracts.
The audit covered organizational structure, procurement processes, and contractual execution, including physical inspections of works in Port-au-Prince. The findings highlight systemic weaknesses, including the MTPTC's Commission Ministérielle des Marchés Publics (CMMP) not fully performing its regulatory role, a lack of internal audit, and inadequate archiving. Many contracts, particularly those awarded by direct agreement or restricted tender, showed non-compliance with legal requirements, such as insufficient competition, unrealistic execution deadlines, and missing contractual clauses.
Issues like significant quantity variations, non-application of penalties for delays, and lack of performance bonds were prevalent, leading to cost overruns and project inefficiencies. The report concludes with recommendations to strengthen institutional capacity, improve planning, enhance documentation, and ensure stricter enforcement of procurement regulations.
How to cite
National Public Procurement Commission (CNMP), 2016, Audit of Procurement Procedures — Ministry of Public Works, Transport and Communications (MTPTC), FY 2014-2015, https://cnmp.gouv.ht/uploads/documents/1761329632_Rapport_MTPTC.pdf