Done / Pòtfolyo patnè yo / Gwoup BID / IDB
Pwogram enfrastrikti pwodiktif IV
Tit pibliye: Productive Infrastructure Program IV
An milyon dola ameriken sof si yo di lòt bagay. Ane fiskal ayisyen, soti oktòb rive septanm. FY2026-27 te kòmanse 1 oktòb 2026.
Objektif
the project objective is to contribute to the sustainable economic development of Northern Haiti. The specific objective is to create formal employment in the North and Northeast Departments of Haiti by providing the necessary conditions for the establishment of firms in the Parc Industriel de Caracol (PIC) and ensuring its adequate management and long term sustainability.
Jan Done pwojè BID pibliye l, nan lang orijinal li.
- Sektè
- Pwoteksyon sosyal
- Etap
- Kanpe
- Apwobasyon
- 14 desanm 2015
- Fèmen
- Pa deklare
- Enstriman
- Don, Sovereign Guaranteed
- Antre an vigè
- Pa deklare
- Dènye tranzaksyon
- 14 desanm 2015
- Idantifyan operasyon an
- HA-L1101
Sik lavi3 etap, 3 dat
Istwa etap yo
| Etap | Depi |
|---|---|
| Apwouve | 14 desanm 2015 |
| An kou | 1 fevriye 2016 |
| Kanpe | Dat pa deklare |
Dat yo
| Evènman | Dat | Sous |
|---|---|---|
| Apwobasyon | 14 desanm 2015 | Done pwojè BID |
| Premye angajman | 14 desanm 2015 | Tranzaksyon |
| Siyati | 1 fevriye 2016 | Done pwojè BID |
Finansman
Tablo 1.Finansman, milyon dola ameriken
| Sous finansman | MontanMilyon dola ameriken | Wòl | Sous |
|---|---|---|---|
| IDB | 41.0 | Enstitisyon | Done pwojè BID |
Tablo 2.Pozisyon nan dat done yo pa sous (stòk), milyon dola ameriken
| Paj sa aMilyon dola ameriken | Sous | |
|---|---|---|
| Angajman | 41.0 | Done pwojè BID |
| Dekèse | Pa deklare | |
| Pa dekèse | Pa deklare | |
| Pri total | 41.0 | Done pwojè BID |
Chak montan bay jan sous la pibliye l, konvèti an US$. Montan yo dapre sous la
Chanjman nan operasyon anpa deklare
- Dat fèmti orijinal
- Pa deklare
- Pwolongasyon dat fèmti
- Pa deklare
- Restriktirasyon
- Pa deklare
- Konpozan ijans
- Pa deklare
Nouvo angajman ak dekèsman pa ane fiskal
Tablo 3.Nouvo angajman ak dekèsman pa ane fiskal (koule), milyon dola ameriken
| FY2015-16Milyon dola ameriken | |
|---|---|
| Nouvo angajman | 41.0 |
| Dekèsman | Pa deklare |
| Dekèsman kimile | Pa deklare |
Fich ak dokiman
Tranzaksyon1 tranzaksyon, 14 desanm 2015
Tablo 4.Tranzaksyon, milyon dola ameriken
| Dat | Mezi | MontanMilyon dola ameriken | Sous | Metòd |
|---|---|---|---|---|
| 14 desanm 2015 | Angajman | 41.0 | Done pwojè BID | commitment at approval date |
Kondisyon1 sou 6 rapòte
- Kalite finansman
- 110 Don estanda
- Kalite koule
- Pa deklare
- Kalite èd
- Pa deklare
- Èd mare oswa pa mare
- Pa deklare
- Kalite kolaborasyon
- Pa deklare
- Imanitè
- Pa deklare
Idantifyan1 idantifyan
| Sistèm | Idantifyan | Sous |
|---|---|---|
| Operasyon BID | HA-L1101 | Fich operasyon an |
Dokiman patnè a
Pa gen okenn dokiman nan lis pou operasyon sa a.
Sous
- Paj pwojè a, BID: kondisyon itilizasyon piblikatè a fikse
- Tranzaksyon: kondisyon itilizasyon piblikatè a fikse
- Fich operasyon an: kondisyon itilizasyon piblikatè a fikse
Done jiska 18 oktòb 2026
| Sous | Konsilte nan dat |
|---|---|
| Done pwojè BID | 18 oktòb 2026 |
Site paj sa a
HaitiDocs. Pwogram enfrastrikti pwodiktif IV. Pòtfolyo patnè yo, done jiska 18 oktòb 2026. https://www.haitidocs.org/portfolio/projects/IDB%3AHA-L1101?lang=ht