Teks Konple Dokiman an
Teks ki soti nan dokiman orijinal la pou endeksasyon.
Document of
The World Bank
FOR OFFICIAL USE ONLY
Report No: ICR00005439
IMPLEMENTATION COMPLETION AND RESULTS REPORT
TF-A0226
ON A
GRANT
IN THE AMOUNT OF SDR 3.5 MILLION
(US$5 MILLION EQUIVALENT)
TO THE
REPUBLIC OF HAITI
FOR THE
HT Strengthening Hydro-Met Services Project
April 13, 2021
Urban, Resilience And Land Global Practice
Latin America And Caribbean Region
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
CURRENCY EQUIVALENTS
(Exchange Rate Effective March 15, 2021)
Currency Unit = Haitian Gourdes (HTG)
HTG78.993 = US$1
US$1.431 = SDR 1
FISCAL YEAR
October 1 - September 30
Regional Vice President: Carlos Felipe Jaramillo
Country Director: Tahseen Sayed Khan
Regional Director: Anna Wellenstein
Practice Manager: David N. Sislen
Task Team Leader(s): Claudia Ruth Soto Orozco
ICR Main Contributor: Naraya Carrasco
ABBREVIATIONS AND ACRONYMS
ACCPAC Account Package
CARICOM Caribbean Community
CCPC Municipal Civil Protection Committee (Comité Communal de Protection Civile)
CIAT Comité Interministériel d’Aménagement du Territoire (Inter-ministerial Committee
for Territorial Planning)
CIF Climate Investment Funds
CNIGS Centre National de l'Information Géo-Spatiale (National Center for Geo-Spatial
Information)
CNM Centre National de Météorologie (National Center for Meteorology)
CNSA Coordination Nationale de la Sécurité Alimentaire (National Coordination for Food
Security)
COOPI Cooperazione Internazionale (Italy’s International Cooperation)
CPF Country Partnership Framework
DCC Division Changement Climatique (Climate Change Directorate)
DDA Direction Départementale de l’Agriculture (Departmental Directorate for
Agriculture)
DG Director General
DIA Direction des Infrastructures Agricoles (Agriculture Infrastructure Directorate)
DPC Direction de la Protection Civile (Civil Protection Directorate)
DRE Direction des Ressources en Eau (Water Resource Directorate)
EIRR Economic Internal Rate of Return
EMP Environmental Management Plan
ESMF Environmental and Social Management Framework
EU European Union
EWS Early Warning System
FCV Fragile, Conflict and Violence
GDP Gross Domestic Product
GFDRR Global Facility for Disaster Reduction and Recovery
GIS Geographical Information System
GoH Government of Haiti
HT Haiti
IDB Inter-American Development Bank
INSMET Cuban National Institute for Meteorology (Instituto de Meteorología de la
República de Cuba)
ISN Interim Strategy Note
ISR Implementation Status and Results
MARNDR Ministère de l’Agriculture, Ressources Naturelles et Développement Rural
(Ministry of Agriculture, Natural Resources and Rural Development)
MCH Meteorological, Climatological and Hydrological Database Management System
MDE Ministère de l'Environnement (Ministry of the Environment)
MICT Ministère de l’Intérieur et des Collectivités Territoriales (Ministry of Interior and
Territorial Communities)
MIS Management Information System
MPCE Ministère du Plan et de la Coopération Externe (Ministry of Planning and External
Cooperation)
MTPTC Ministère des Travaux Publics, Transports et Communications (Ministry of Public
Works, Transport and Communications)
NAPA National Action Plan for Adaptation
NHP National Hydro-met Platform
NPV Net Present Value
OFNAC Office National de l’Aviation Civile (National Civil Aviation Agency)
OM Operations Manual
ONEV Observatoire National de l’Environnement et de la Vulnérabilité (National
Observatory on Environment and Vulnerability)
OP Operational Policy
PAD Project Appraisal Document
PDO Project Development Objective
PGRAC Strengthening Disaster Risk Management and Climate Resilience Project (Projet de
Gestion des Risques et de Résilience aux Aléas Climatique)
PIU Project Implementation Unit
PNAP Programme National d’Alerte Précoce (National Early Warning Project)
PPCR Pilot Program for Climate Resilience
RESEPAG II Relaunching Agriculture: Strengthening Agriculture Public Services Project (Projet
de Renforcement des Services Publics Agricoles II)
RF Results Framework
SCF Strategic Climate Fund
SDGs Sustainable Development Goals
SDR Special Drawing Rights
SEMANAH Service Maritime et de Navigation d'Haïti (Haiti National Maritime and Navigation
Service)
SNRE Service National des Ressources en Eau (National Service for Water Resources)
SOP Standard operating procedures
SORT Systematic Operations Risk-rating Tool
SPCR Strategic Program for Climate Resilience
STEP Systematic Tracking of Exchanges in Procurement
TA Technical Assistance
ToC Theory of Change
UEP Unité d’Études et de Programmation (Study and Planning Unit, MARNDR)
UHM Unité Hydrométéorologique d’Haïti (Hydrometeorological Unit of Haiti)
UIS Unité Informatique et Statistique (Statistics and IT Unit, MARNDR)
UPMP Unité de Passation de Marchés Publics (Centralized Procurement Unit, MARNDR)
USAID United States Agency for International Development
WMO World Meteorological Organization
TABLE OF CONTENTS
DATA SHEET ................................................................................................................................1
I. PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES .........................................................5
A. CONTEXT AT APPRAISAL ............................................................................................................. 5
B. SIGNIFICANT CHANGES DURING IMPLEMENTATION (IF APPLICABLE) ......................................... 8
II. OUTCOME ...........................................................................................................................9
A. RELEVANCE OF PDOs .................................................................................................................. 9
B. ACHIEVEMENT OF PDOs (EFFICACY) .......................................................................................... 10
C. EFFICIENCY ................................................................................................................................ 13
D. JUSTIFICATION OF OVERALL OUTCOME RATING....................................................................... 14
E. OTHER OUTCOMES AND IMPACTS ............................................................................................ 14
III. KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME ..................................15
A. KEY FACTORS DURING PREPARATION ....................................................................................... 15
B. KEY FACTORS DURING IMPLEMENTATION ................................................................................ 16
IV. BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME ...18
A. QUALITY OF MONITORING AND EVALUATION (M&E) .............................................................. 18
B. ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE ....................................................... 19
C. BANK PERFORMANCE ............................................................................................................... 20
D. RISK TO DEVELOPMENT OUTCOME .......................................................................................... 21
V. LESSONS AND RECOMMENDATIONS .................................................................................22
ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS ..............................................................24
ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION...........................32
ANNEX 3. PROJECT COST BY COMPONENT ............................................................................... 35
ANNEX 4. EFFICIENCY ANALYSIS ............................................................................................... 36
ANNEX 5. BORROWER, CO-FINANCIER AND OTHER PARTNER/STAKEHOLDER COMMENTS ... 37
ANNEX 6. SUPPORTING DOCUMENTS ......................................................................................42
ANNEX 7. PROJECT IMPLEMENTATION TIMELINE: EXOGENOUS FACTORS ...............................43
ANNEX 8. PROJECT RESULTS FRAMEWORK AND PPCR CORE INDICATORS...............................44
ANNEX 9. PROJECT COMPONENT ACHIEVEMENTS AND LINK TO CREWS .................................45
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 1 of 46
DATA SHEET
BASIC INFORMATION
Product Information
Project ID Project Name
P148259 HT Strengthening Hydro-Met Services
Country Financing Instrument
Haiti Investment Project Financing
Original EA Category Revised EA Category
Partial Assessment (B) Partial Assessment (B)
Organizations
Borrower Implementing Agency
Republic of Haiti
Ministry of Agriculture, Natural Resources and Rural
Development (MARNDR)
Project Development Objective (PDO)
Original PDO
The Project Development Objective (PDO) is to strengthen the Republic of Haiti's institutional capacity to
providehydro-meteorological and climate information services customized to the needs of the civil protection and
agriculture sectors,which contributes to increasing disaster and climate resilience.
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 2 of 46
FINANCING
Original Amount (US$) Revised Amount (US$) Actual Disbursed (US$)
World Bank Financing
TF-A0226
5,000,000 5,000,000 3,742,007
Total 5,000,000 5,000,000 3,742,007
Non-World Bank Financing
0 0 0
Borrower/Recipient 0 0 0
Total 0 0 0
Total Project Cost 5,000,000 5,000,000 3,742,007
KEY DATES
Approval Effectiveness MTR Review Original Closing Actual Closing
26-Jun-2015 19-Oct-2015 12-Nov-2018 30-Jun-2020 30-Oct-2020
RESTRUCTURING AND/OR ADDITIONAL FINANCING
Date(s) Amount Disbursed (US$M) Key Revisions
26-Jun-2020 3.70 Change in Loan Closing Date(s)
Change in Implementation Schedule
30-Jun-2020 3.70
KEY RATINGS
Outcome Bank Performance M&E Quality
Moderately Unsatisfactory Moderately Unsatisfactory Modest
RATINGS OF PROJECT PERFORMANCE IN ISRs
No. Date ISR Archived DO Rating IP Rating
Actual
Disbursements
(US$M)
01 24-Nov-2015 Satisfactory Satisfactory 0
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 3 of 46
02 08-Jun-2016 Satisfactory Moderately Satisfactory .50
03 27-Dec-2016 Moderately Satisfactory Moderately Satisfactory .50
04 18-May-2017 Moderately Satisfactory Moderately Unsatisfactory .51
05 05-Dec-2017 Moderately Satisfactory Moderately Unsatisfactory .52
06 18-May-2018 Moderately Satisfactory Moderately Satisfactory .52
07 31-Dec-2018 Moderately Satisfactory Moderately Satisfactory .85
08 26-Jun-2019
Moderately
Unsatisfactory
Moderately Unsatisfactory .85
09 31-Dec-2019
Moderately
Unsatisfactory
Moderately Unsatisfactory 1.29
10 30-Oct-2020
Moderately
Unsatisfactory
Moderately Unsatisfactory 3.70
SECTORS AND THEMES
Sectors
Major Sector/Sector (%)
Agriculture, Fishing and Forestry 14
Other Agriculture, Fishing and Forestry 14
Water, Sanitation and Waste Management 86
Public Administration - Water, Sanitation and Waste
Management
72
Other Water Supply, Sanitation and Waste
Management
14
Themes
Major Theme/ Theme (Level 2)/ Theme (Level 3) (%)
Finance 16
Finance for Development 16
Disaster Risk Finance 16
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 4 of 46
Public Sector Management 36
Public Administration 36
E-Government, incl. e-services 36
Urban and Rural Development 48
Disaster Risk Management 48
Disaster Response and Recovery 16
Disaster Risk Reduction 16
Disaster Preparedness 16
ADM STAFF
Role At Approval At ICR
Regional Vice President: Jorge Familiar Calderon Carlos Felipe Jaramillo
Country Director: Mary A. Barton-Dock Tahseen Sayed Khan
Director: Ede Jorge Ijjasz-Vasquez Anna Wellenstein
Practice Manager: Anna Wellenstein David N. Sislen
Task Team Leader(s): Gaetano Vivo Claudia Ruth Soto Orozco
ICR Contributing Author: Naraya Carrasco
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 5 of 46
I. PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES
A. CONTEXT AT APPRAISAL
Context
1. At appraisal in May 2015, Haiti was still confronting considerable challenges due to exogenous and endogenous
factors. Haiti continued to be severely affected by the aftermath of the catastrophic 2010 earthquake that led to a toll
of 220,000 casualties, including one in three civil servants, 1.5 million people displaced, and the equivalent of 120 percent
of gross domestic product (GDP) destroyed, while facing a growing political and socioeconomic crisis. Climate change
was projected to heighten the risk of hydrometeorological (hydromet) hazards, with an increased frequency and intensity
of extreme events such as Hurricane Sandy in 2012—about 75 deaths, 200,000 affected and US$0.5 billion in damages.
The poverty rate was 58.5 percent, with almost 6.3 million Haitians unable to meet their basic needs and one million
Haitians living slightly above the poverty level, risking falling back into poverty because of external shocks, including
climatic-induced shocks.
2. Haiti’s economic recovery and growth potential could not be sustained without improving the country’s
meteorological data to support early warning systems to enhance its resilience as a whole and informing the agricultural
sector. A World Bank global study
1
ranked Haiti fifth in exposure to the risk of two or more hazards, with more than 93
percent of its territory and 96 percent of its population at risk of two or more hazards and 56 percent of its GDP linked
to an area exposed to risk stemming from two or more hazards. High coastal population density, informal settlements,
weak infrastructure and flood-prone agricultural land render Haiti’s population and the agricultural sector particularly
vulnerable. Over the past decade, hydromet hazards have claimed lives, affected livelihoods, and have taken a heavy toll
on all sectors of the Haitian economy, especially in agriculture and food security.
Rationale for World Bank Engagement
3. Four years after the 2010 Earthquake, the Government of Haiti (GoH) had embarked on a structural reform of
the country where catastrophic events and climate change were high on national priority. In this context, a World Bank
recipient-executed trust fund grant was provided to Haiti under the Pilot Program for Climate Resilience (PPCR) under
the Strategic Climate Fund. At appraisal, the objectives of the project aligned with the World Bank Group’s Haiti Interim
Strategy Note (ISN) FY13–FY14 (Report #71885-HT) and supported two of the four objectives of the ISN: (i) reducing
vulnerability and increasing resilience, and (ii) promoting inclusive growth. It also contributed to the ISN crosscutting
theme of strengthening governance. Moreover, the World Bank had a comparative advantage in hydromet operations
and experience in several countries, in conjunction with the Global Facility for Disaster Reduction and Recovery (GFDRR)
Hydromet Program, to better predict, prepare, and respond to disastrous events, manage natural resources—water in
particular—and better understand climate change effects, as well as support transport activities in aviation and
navigation. The project aligned with the GoH 2013 National Strategic Program for Climate Resilience (SPCR), which
included “Strengthening Knowledge Management of Hydro-met, Water Resources, and Climate Data to Inform Decision
Making and Policy Dialogue”. It also contributed to the implementation of Haiti’s 2006 National Action Plan for
Adaptation (NAPA). The project design responded to challenges and opportunities highlighted in various studies, such as
1
World Bank, Natural disaster hotspots: A global risk analysis, 2005.
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 6 of 46
those of the World Meteorological Organization (WMO 2010 and 2012),
2
the Interamerican Development Bank (2014)
3
and the World Bank (2014).
4
The 2012 Haiti Strategic Program for Climate Resilience (SPCR) especially pointed to a new
institutional framework for the hydromet services with the following priorities: (i) rationalizing and streamlining the
national data collection and management system; (ii) establishing a mechanism to bring together data producers and
main end users—aviation, civil protection, water utility—and providing feedback, and increasing the socioeconomic
value of data; and (iii) ensuring a sustainable financing model based on a cost-recovery principle.
Theory of Change (Results Chain)
4. The project appraisal document (PAD) did not include a theory of change (ToC). The inferred ToC (Figure 1),
including the critical assumptions, are presented below:
Figure 1: Theory of Change
- Hydromet data accessible through a centralized platform will support decision-making processes and therefore
increase preparedness and overall resilience of the Haitian population, as well as agricultural production.
2
The re-establishment of meteorological services in Haiti in 2010 with a website (www.meteo-haiti.gouv.ht) to disseminate information
and warnings to United Nations’ agencies, nongovernmental organizations (NGOs), disaster-affected communities, and the media
occurred thanks to collaboration between WMO and other development partners. WMO also partnered with Environment and Climate
Change Canada in 2012 to develop the project “Climate Services to Reduce Vulnerability in Haiti” whose aim was to install technical
equipment such as forecaster workstations, Internet, communications, and related technology in a newly built UHM headquarters.
Website: <Climate Services to Reduce Vulnerability in Haiti | World Meteorological Organization (wmo.int)>
3
IDB website: <Background Paper: LAC Small Island Development States | Publications (iadb.org)>
4
World Bank website: <WorldBank-rapid-global-assessment.pdf (whycos.org)>
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 7 of 46
- A strong hydromet unit in Haiti (UHM) and government officials well-trained in the collection and management
of hydromet data will result in on-time preparedness activities, thus enhancing the protection of the population
and improving agricultural production and livelihoods.
Project Development Objectives (PDOs)
5. The Project Development Objective (PDO), as stated in the financial agreement approved on June 26, 2015,
which is consistent with the PDO statement in the PAD, is to strengthen Haiti’s institutional capacity to provide
hydrometeorological and climate information services customized to the needs of the civil protection and agriculture
sectors, which contribute to increasing disaster and climate resilience
Key Expected Outcomes and Outcome Indicators
6. The key outcome indicators were:
(i) Data collected from hydromet networks are accessible on a centralized online data management platform,
with standard operating procedures for validation and storage;
(ii) Number of subnetworks feeding into the centralized platform; and
(iii) End users’ satisfaction rate toward improved hydromet information services, percentage and gender-
disaggregated.
Components
7. The project included three components:
- Component 1, Institutional strengthening of the hydrometeorological services and development of data
management tools (Special Drawing Rights {SDR} 2.1 million / US$3 million):
1.1. Institutional strengthening, capacity building, and partnership development. Provision of support, among
others, for:
1. Carrying out technical assistance (TA) to develop a long-term strategy based on sustainable financing and
staffing model for the national entity that will be responsible for the development, operation, and maintenance
of all hydrometeorological services.
2. Carrying out training and knowledge exchange programs to develop data management capacity of the
producers and users of hydrometeorological data.
3. Developing applications and applied research programs aimed at supporting students or young professionals
or both groups selected in accordance with the criteria set forth in the project operations manual in carrying
out field work to improve hydromet and climate data collection and management.
1.2. Strengthening interinstitutional data sharing and coordination. Provision of support, among others, for:
1. Designing a central data platform for hydrometeorological data integration based on an open data approach
through: (i) the implementation of a countrywide, georeferenced baseline assessment of hydrometeorological
equipment; (ii) the proposal for an optimal network, which would meet priority national needs while taking into
account the maintenance and operational budget; (iii) the development of the architecture and technical
specifications of a data platform capable to gather data from all existing hydrometeorological sensors and feed
in real time several user-specific interfaces; and (iv) the development of standard procedures for equipment and
data management.
2. Developing specialized interfaces based on a geographical information system (GIS) for select end users to
allow them access to hydrometeorological information.
3. Carrying out training for hydrometeorological data producers and users on the use and maintenance of
equipment and management of the online data management platform, including the specialized interfaces.
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 8 of 46
4. Repairing, replacing, or upgrading existing hydrometeorological equipment throughout the recipient's
territory based on the assessment carried out in Part 1.2.1.
- Component 2, Identifying hydrometeorological and climate services' requirements for select end users and
developing information services to support decision making (SDR 1.0 million / US$1.4 million). Provision of support
for:
1. Scoping hydrometeorological information requirements of end users, pursuant to methodology and selection
criteria set forth in the project operational manual.
2. Updating operating procedures for the optimal use of hydrometeorological services for agriculture and food
security through initiating a pilot information service for farmers and other food security stakeholders, designed
to factor requirements from end users of the food security and agricultural communities.
3. Updating operating procedures for the optimal use of hydrometeorological services for civil protection through
the launch of an information service for civil protection and through the provision of expert assistance for early
warning and emergency response in pilot zones.
4. Updating the estimated return period of selected weather hazards, including floods, windstorms, and storm
surges, to facilitate the design of infrastructure and planning of development processes.
- Component 3, Project implementation, evaluation and monitoring and pilot program for climate resilience (PPCR)
knowledge management (SDR 0.4 million / US$0.6 million):
Provision of support to the Ministry of Agriculture, Natural Resources and Rural Development (MARNDR) for
project implementation, management, procurement, and monitoring and evaluation. The project relied on a
multi-project centralized procurement unit (UPMP), also in charge of contract management that was established
by the World Bank in 2014 under MARNDR. The creation of the UPMP aimed to strengthen MARNDR’s capacity
to manage projects. The project coordinator was selected by MARNDR among the ministry’s staff
B. SIGNIFICANT CHANGES DURING IMPLEMENTATION (IF APPLICABLE)
Revised PDOs and Outcome Targets
8. The PDO indicators and outcome targets were not changed during the lifetime of the project.
Revised PDO Indicators
9. The PDO indicators were not changed during the lifetime of the project.
Revised Components
10. Under Component 3, the project had initially planned to rely on MARNDR's own staff and the UPMP for
procurement and project management to avoid the need for a full project implementation unit (PIU). However, given
MARNDR’s capacity constraints and the resignation of the Project Coordinator, the project ended up mobilizing a full PIU
after the project midterm review (MTR).
Other Changes
11. Further to the creation of the PIU after the MTR, the project was restructured in June 2020 to extend the grant
closing date by four months from June 30, 2020 to October 30, 2020 (because of delays resulting from the COVID-19
pandemic) so that the project could take delivery of the 62 hydromet stations. The residual grant funds of US$1.3 million
were canceled and the stations are installed under the World Bank’s “Relaunching Agriculture: Strengthening Agriculture
Public Services II Project” (RESEPAG II - P126744). Further TA and safeguards compliance monitoring to accompany the
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 9 of 46
installation process and support the hydromet sector will continue under the GFDRR TA, which is available under the
World Bank’s “Strengthening Disaster Risk Management and Climate Resilience Project” (PGRAC - P165870).
Rationale for Changes and Their Implication on the Original Theory of Change
12. The extension of the closing date intended to allow the project to complete shipment, delivery and installation
of hydromet equipment. The limited project extension (four months) affected the accomplishment of the short-term
outcomes shown in the Theory of Change.
II. OUTCOME
A. RELEVANCE OF PDOs
Rating: High
Assessment of Relevance of PDOs and Rating
13. The project objective remains highly relevant at closing. The PDO remains consistent with the country
partnership framework (CPF) FY2016–19 (98132-HT)—which is the ongoing CPF
5
—as it contributes to two of the three
areas of CPF’s focus: (i) the resilience area, supported by enhanced understanding of hydrometeorological and climate
risks to assess social and economic impacts, and to develop adequate policy responses to support sustained
development; and (ii) the inclusive growth area, by improving agricultural productivity and resilience. The performance
and learning review (PLR) updated the CPF FY2018 (144812-HT) and sought to further strengthen the CPF’s robust
approach to resilience in 2018 by: (i) increasing funding; (ii) improving targeting to high-risk areas; (iii) sharpening the
focus on local capacity to prepare for and respond to disasters; and (iv) mainstreaming DRM in other sectors. The PDO
also remains consistent with the Pilot Program for Climate Resilience’s (PPCR’s) targeted program of the Strategic Climate
Fund (SCF), as the project indicators contribute to the PPCR core indicators. Moreover, the PDO is in line with the risk-
based, people-centered and multi-hazard early warning systems that are being implemented by the GFDRR, the WMO,
and the United Nations Office for Disaster Risk Reduction under the multi-donor Climate Risk Early Warning Systems
(CREWS) initiative in the 15 Caribbean community (CARICOM) member countries.
6
14. The PDO remains a priority for the GoH. The frequency and severity of hydromet hazards in Haiti, which was
affected by 18 meteorological mild and severe events over the lifetime of the project (Annex 7), are anticipated to
increase because of climate change, with the population and notably the agricultural sector remaining vulnerable to their
impacts. The PDO contributes to Haiti’s hydromet services under the 2020 Second National Disaster Risk Management
Plan 2019–2030.
7, 8
The plan is divided into four strategic axes that are aligned with international and regional
commitments, such as the Sustainable Development Goals (SDGs) and climate change,
9
and the Caribbean Disaster
Management Strategy
10
respectively. The streamlining of the institutional set up and operationalization of the hydromet
system will improve the prevention and preparedness capacity element of the PDO that feeds into the GoH’s 2020 DRM
5
After the Performance and Learning Review of the CPF was completed in 2018, CPF milestones were extended until 2021 pending the
preparation of a new CPF.
6
GFDRR website: <CREWS Caribbean | GFDRR>
7
NDRNP 2020: <www.haitilibre.com/docs/PNGRD_BAT_2020_SMALL.pdf>
8
Decree 103 on the National DRM Plan in Le Moniteur, 15 juin, 2020.
9
UN 2015 SDG 1 (Target 1.5.3: adopt and implement national disaster risk reduction strategies in line with the Sendai Framework for
Disaster Risk Reduction 2015-2030) <https://sdgs.un.org/goals>
10
CDMS 2014: <CDwww.cdema.org/CDMStrategy2014-2024.pdf>
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 10 of 46
Legal and Institutional Framework
11
(the national DRM System) and the national hydromet unit’s (UHM’s) National
Strategic Plan 2020–2024 that was prepared under this project.
B. ACHIEVEMENT OF PDOs (EFFICACY)
Rating: Modest
Assessment of Achievement of Each Objective/Outcome
15. Achievement of the PDO is assessed against the targets set in the 2015 PAD and is unpacked along the lines
of the two complementary elements of the PDO that contribute to increasing disaster and climate resilience through:
(i) strengthening Haiti’s institutional capacity to provide hydromet and climate information services; and (ii)
strengthening Haiti’s institutional capacity to customize hydromet and climate information to the needs of the civil
protection and agriculture sectors (Annex 1).
PDO#1: Strengthening Haiti’s institutional capacity to provide hydromet and climate information services
16. PDO indicator 1: Data collected from hydromet networks are accessible on a centralized online hydromet data
management platform, with its own operating procedures for validation and storage – Target Partially Achieved. The
project established the National Hydromet Platform (NHP) for data management that is operated under the newly
created UHM under MARNDR’s tutelage that merged the National Meteorological Center (CNM) and the National
Service for Water Resources (SNRE) within the same ministry. UHM is housed in a new building constructed under
WMO’s Climate Services to Reduce Vulnerability in Haiti since 2017.
12
However, the online open access of the hydromet
platform has been delayed and was not achieved, although data is provided upon request (Annex 9). The intermediate
result indicator (IRI) 1 on training users and instructors, considered as an essential element of institutional capacity
building, was also not achieved (11 percent of its target). Other activities that resulted in tangible achievements are
discussed below but did not have indicators assigned and are not shown in Table 1.
• The project allowed all stakeholders to recognize UHM as Haiti’s hydromet focal point and service provider,
as UHM was instrumental in providing hydromet information before, during and after Hurricane Laura in
August 2020. The project helped formulate the UHM National Strategic Plan 2020–2024 of Haiti which was
developed by WMO and reviewed by the World Bank by the end of the project. The strategy has five priorities
to strengthen the operationalization of UHM through: (i) consolidating the UHM institutional anchor in the
existing or planned governmentwide institutional set up; (ii) ensuring sustainability of the resources and skills
necessary for the proper functioning and development UHM in conjunction with the GoH’s strategies and
priorities; (iii) increasing UHM capacity to provide quality services to all users in weather, hydrological and
climate-sensitive areas; (iv) positioning meteorology, hydrology, climatology and related disciplines as a priority
area for research and development to tap development funding better; and (v) optimizing Haiti's effective
integration into regional or global hydromet programs. The project has already contributed toward the first and
third priorities. The institutional set up and financial sustainability are an important element of the project,
however they need to be duly considered by the other ongoing hydromet projects for funding such as the
ongoing multi-donor CREWS project (Annex 9).
13
11
Decree 103 on the creation and organization of the National DRM System in Le Moniteur, 15 juin, 2020.
12
WMO website: <Climate Services to Reduce Vulnerability in Haiti | World Meteorological Organization (wmo.int)>
13
The CREWS project has three components: (i) regional strategy and identification of priority investments; (ii) institutional
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 11 of 46
• The project installed the NHP software with open-source capabilities for hydromet data management under
UHM. The NHP, which was developed by WMO, is referred as the meteorological, climatological, and
hydrological (MCH) database management system, and was installed instead of the high-tech and costly platform
suggested by the consortium hired to develop the hydromet design under Phase I. In close collaboration with
WMO’s ongoing project in Haiti, the hydromet project provided the necessary software and hardware technical
support, as well as training and capacity building. The latter is expected to be continued under the CREWS (Annex
9) financed project and by WMO with the support of Météo-France, the Caribbean Institute for Hydrology and
Meteorology, the Cuban National Institute for Meteorology (INSMET), and the Regional Specialized
Meteorological Centre in Miami. The MCH standard operating procedures have been developed for operating
and maintaining all hydromet data and data collection processes. The training program to develop data
management capacity of the producers and users of hydromet data was initiated through remote support and
activities. However, the target for training UHM staff members to develop data management capacity of
hydromet data producers and users with WMO support was not met, because of the COVID-19 pandemic as well
as UHM’s institutional weaknesses, and lack of appropriate human resources on the producers’ side. Academics
and university students were ultimately hired by the project to support UMH in data collection, validation, and
treatment.
Table 1: Extent of Achievement of Intermediate Results Indicator (IRI) Targets of PDO Indicator 1
Identify hydromet and climate services’ requirements for
select end users and development of information services
to support decision making
Baseline /
Unit
Target Number
Achieved
%
Achieved
IRI 1. Number of users and instructors trained on the use of
the centralized data platform
#0 80 9 11%
Note: Percentage achieved is color coded: yellow – not achieved set target; and light green – achieved set target.
17. PDO indicator 2: Number of subnetworks feeding into the centralized platform – Target Achieved. The project
consolidated and centralized the existing inter-institutional hydromet networks’ data that feed into the MCH’s NHP.
The platform’s permanent server hosts the UHM network, comprising 34 stations from five sub-networks: the National
Center for Geo-Spatial Information (CNIGS) of the Ministry of Planning and External Cooperation (MPCE); Italy’s
Cooperazione Internazionale (COOPI); and NGO partners’ networks, Fondation Nouvelle, Grand-Anse and CESAL.
Hydromet historical data since 1926 from 230 stations were also added to the platform. These 34 stations will remain
under the aegis of the five networks for future operation and maintenance (Annex 9). The NHP will gradually receive
additional information and data from government agencies, including MARNDR’s departmental agricultural directions
(DDAs), while several agencies and NGOs will keep updating the MCH. Only one of two IRIs targets was achieved, as
discussed below and shown in Table 2.
• The output target for the indicator IRI 2 was achieved by hosting 34 stations in the UHM network from five
independent sub-networks.
• The target of having at least 50 hydromet stations operating was not reached. The institutional diagnostic of the
hydromet sector carried out by the project recommended the optimization of the hydromet equipment and
strengthening of data management. The programed training for the UHM staff members to develop equipment
management capacity was completed. As recommended by the consortium to optimize the hydromet system,
strengthening and capacity building of hydromet services and early warning systems; and (iii) implementation of national-level pilot
projects to comprehensively strengthen early warning systems.
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 12 of 46
the number of stations was increased to 62 stations that were successfully procured and delivered. However,
travel restrictions on account of the COVID-19 pandemic significantly delayed the delivery and hampered the
installation of the equipment. Only two stations were installed and were not connected to MCH by closing date.
The installation of the stations will be completed under RESEPAG II, with technical support from the PGRAC.
Table 2: Extent of Achievement of Intermediate Results Indicator (IRI) Targets of PDO Indicator 2
Identify hydromet and climate services’ requirements for select
end users and development of information services to support
decision making
Baseline /
Unit
Target Number
Achieved
%
Achieved
IRI 2. Hydrological and meteorological stations reporting data to the
platform in line with agreed standard operation procedures.
#0 34 34 100%
IRI 3. Operational stations #0 50 2 4%
Note: The target for operational stations was not changed although 62 were procured. Percentage achieved is color coded:
yellow – not achieved set target; and light green – achieved set target.
PDO#2: Strengthening Haiti’s institutional capacity to customize hydromet and climate information to the needs of
the civil protection and agriculture sectors
18. PDO indicator 3: End users' satisfaction rate — of whom 50 percent was female — toward improved hydromet
information services – Target not Achieved. The end user satisfaction target of 100 percent was not met because the
platform was not online. While the platform is operational and managed by UHM, data from the platform are not
directly accessible to end users through an online portal but are only provided upon request which explains the 52
percent satisfaction rate. The WMO TA is supporting UHM to set up the online portal for direct data sharing. The three
IRI targets were not achieved as discussed below and shown in Table 3:
• The project had planned to analyze the data collected by the hydromet networks and consolidated in the
national data platform to develop software interfaces customized to meet the needs of the Directorate of
Civil Protection and the agriculture sector. The project did not have the time to customize the full application
from MCH to be used by the municipal civil protection committees (CCPCs) and the Departmental Agricultural
Directions (DDAs). However, it was able to advance in the following areas: scoping the hydromet information
requirements of end users and the development of initial customized hydromet products to be used by the
agriculture sector. Moreover, the quality of the existing UHM hydromet products was improved. The project
also provided equipment, such as servers to save and better process the data and carried out maintenance of
hydromet stations to ensure the quality and regularity of information. A designated training session for 85 end
users, including 13 women, from CCPCs and DDAs in the interpretation and the use of UHM’s hydromet
products were carried out and was not captured by an indicator.
Table 3: Extent of Achievement of Intermediate Results Indicator (IRI) Targets of PDO Indicator 3
Strengthen the institution for hydromet services and development of data
management tools
Baseline /
Unit
Target Number
Achieved
%
Achieved
IRI 4. Number of civil protection committees (CCPCs) using the customized
application from the centralized data platform
#0 40 0 0%
IRI 5. Number of departmental agricultural directions (DDAs) using the
customized application from the centralized data platform
#0 10 0 0%
IRI 6. Direct project beneficiaries #0 1,000,000 0 0%
Note: Percentage achieved is color coded: yellow – not achieved set target; and light green – achieved set target.
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 13 of 46
Justification of Overall Efficacy Rating
Rating: Modest
19. The project achieved the end target of only one of the three PDO indicators; it also did not meet the end targets
of most IRIs.
C. EFFICIENCY
Rating: Modest
Assessment of Efficiency and Rating
20. Economic efficiency. The project’s ex-ante economic analysis was based on a World Bank report on the use of
international benchmarks to derive potential benefits associated with well-functioning, modern early warning systems
that could reduce disaster-related asset losses and improve agricultural productivity.
14
The project had an ex-ante
positive return on investment, with a present value benefit to cost ratio ranging between 1.6 and 33 over a 15-year
timeframe to account for high uncertainties. At closing, the hydromet system was not fully operational, and the present
value of benefit over cost ratio of less than zero. Despite the additional cost to project management because of COVID-
19 and contract renegotiation owing to force majeure, the ex-ante benefits could well accrue when the hydromet
system is fully operational.
21. Design efficiency. The project suffered from design flaws, inadequate institutional arrangements for project
implementation, and a poor Results Framework (RF) that affected the Monitoring and Evaluation arrangements. The
design, built on the World Bank’s global hydromet experience, was considered appropriate for a poor, fragile, conflict
and violence (FCV) affected country. Components 1 and 2 were straightforward, consisting mainly of consulting services,
institutional and interinstitutional capacity building, and the procurement and installation of equipment. However,
project management was anchored in the new UHM under MARNDR, with all procurement and contract management
delegated to the UPMP; both institutions had low capacity. The project opted to contract two consortiums instead of
one as initially foreseen in the procurement plan, which proved to be ineffective. The World Bank team had to spend
considerable time and effort to reconcile the views of both consortiums and provide close TA to the UHM and the new
PIU created after the MTR. The initial absence of a PIU, the low capacity of UHM, the UPMP and the new PIU as well as
the stalled reform process of MARNDR (see Section IIIB) hampered activities, resulted in serious delays and in the
cancelation of US$1.3 million grant (26 percent, see Annex 3). The design did not properly account for the low capacity
of the institutions.
22. Implementation efficiency. The project faced several endogenous and exogenous factors (see Sections III and IV)
that led to early delays in contracting and in disbursement processing. MARNDR, which was subjected to an overall
reform to streamline processes and improve effectiveness in 2014, displayed weaknesses in managing and coordinating
the project. After a first mis-procurement (Section IV), MARNDR selected a new consortium to execute the design,
monitor, and develop the project elements of the first phase. The consortium did not provide the deliverables on time,
which affected the project implementation timetable. Based on the MTR recommendations, the World Bank set up a
PIU that enabled the speeding up of implementation and disbursements, but the weakness of the PIU did not allow it
to complete the project activities. The COVID-19 pandemic also had some bearing on the final achievements, as most
deliverables due between mid-2019 and mid-2020 were delayed, canceled, or transferred to other ongoing projects.
Only 75 percent of the grant was disbursed, and the remaining amount was canceled. Yet, the design proved to be
14
A Cost-Effective Solution to Reduce Disaster Losses in Developing Countries: Hydro-Meteorological Services, Early Warning, and
Evacuation (World Bank Policy Research, Working Paper #6058, 2012)
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 14 of 46
flexible as the MTR recommended the setting up of a PIU while the soft activities and equipment procurement and
installation had to be calibrated to respond to time constraints.
23. Administrative efficiency. Given the country and project context, the project showed excessive administrative
spending and required extensive World Bank implementation support for: (i) project preparation, where the World Bank
cost reached about US$300,000 (8 percent of the disbursed grant, see Annex 2); (ii) project supervision, where the World
Bank cost reached about US$450,000 (12 percent of the disbursed grant, see Annex 2), and project coordination to
procurement and contract management needed careful and continuous support; and (iii) project management from
grant funds reached about US$800,000 (16 percent of the disbursed grant, see Annex 3), although the envelope was
not increased despite the introduction of a PIU after the MTR. Despite this considerable expenditure and support, the
project did not have a successful outcome.
24. The discussion above confirms that even after making allowances for the FCV context of Haiti, the grant could
have been implemented more efficiently. The efficiency of the project is therefore rated “modest”.
D. JUSTIFICATION OF OVERALL OUTCOME RATING
Rating: Moderately Unsatisfactory
25. The ratings for the relevance of the PDO, efficacy, and efficiency were respectively rated “high”, “modest”,
and “modest”. The overall outcome of the project is rated “Moderately Unsatisfactory”.
E. OTHER OUTCOMES AND IMPACTS
26. Gender. The project set a number of targets for benefiting women; however, none of the targets were reached.
These included targets on women’s satisfaction on improved hydromet information services, training of female users
and instructors on the centralized data platform, and the target number of female project beneficiaries.
27. Institutional Strengthening. The project started building UHM capacity and carrying out institutional and
interinstitutional capacity building and data sharing, whose benefits will be reaped once the activities are completed
under RESEPAG II. It will also provide a better understanding of hydromet and climate risks and impacts on the economy
and on the social fabric, as well as help develop adequate policy responses to support resilient and sustained
development.
28. Mobilizing Private Sector Financing. This was not specifically relevant for this project.
29. Poverty Reduction and Shared Prosperity. When fully operational, the hydromet system is expected to positively
affect almost one million beneficiaries who will be covered by the early warning system and meteorological forecasts;
these would increase their wellbeing through the prevention of premature deaths, morbidity and injuries. Moreover,
farmers will be able to rely on hydromet information and forecasts and take the necessary measures before and after
climate events to improve their livestock and agricultural productivity and by extension livelihoods, especially in remote
areas where the poor and vulnerable live.
30. Other Unintended Outcomes and Impacts. The World Bank technical and financial assistance under the project
supported the creation of the UHM in 2016. The MARNDR merged the hydrological and meteorological services in a
single more efficient unit for the strengthening of hydromet services in Haiti. This institutional achievement was also
supported by the Climate Services to Reduce Vulnerability in Haiti project carried out by WMO and Environment and
Climate Change Canada. While the creation of the UHM was not included as a target of the Hydromet project, its creation
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 15 of 46
represents a substantial achievement for the country to increase resilience against weather related disasters and climate
change.
III. KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME
A. KEY FACTORS DURING PREPARATION
31. Project preparation was challenging, as it had to: (i) set up realistic objectives; (ii) ensure a simple design; (iii)
select appropriate stakeholders using hydromet services; and (iv) establish adequate risk mitigation measures. During
project preparation, the political and socioeconomic context was conducive for reform, as development partners and
GoH turned the catastrophic 2010 earthquake into an opportunity where, notably, preparedness and hydromet services
were high on the GoH agenda. The institutional reform stance included a complete reform of MARNDR and associated
public services. In this context, ambitious institutional reform plans were drafted and a series of projects - supported by
various development partners, such as the Interamerican Development Bank, the International Fund for Agricultural
Development, the Food and Agriculture Organization, and the World Bank - were designed to support this global effort
to reform essential institutions, including the strengthening of public services related to hydromet, DRM, and agriculture.
It is in this context that the new UHM was set up. However, project preparation did not appreciate from the outset the
extent of capacity building and time needed to reform government institutions such as MARNDR and the newly created
UHM. Moreover, the grant envelope was too small to maintain GoH’s buy-in during implementation, especially since the
positive context during preparation was reversed during implementation. Therefore, the PPCR grant could have been
considered as an additional financing under the ongoing RESEPAG II or another ongoing project as an alternative.
32. Realism of Objectives. The PDOs were focused but were not realistic, as they were too broad and were ambitious
in the context of the grant amount, even though they were in line with Haiti’s SPCR as well as with the PPCR core
indicators.
33. Design Challenges. The project benefited from lessons learned worldwide from hydromet projects, and more
specifically form Caribbean projects. However, despite collaboration and resource sharing between the World Bank and
WMO during project preparation and implementation, the technological capabilities of the consolidated hydromet
platform should have been calibrated at the outset within parameters that fit Haiti’s institutional capacity. Conversely,
the institutional and inter-institutional capacity building activities proved to be challenging in an FCV context, including
exposure to exogenous factors (Section III B) five years after the 2010 earthquake. In addition, the UHM was newly set
up and did not get MARNDR’s required political and budgetary commitment throughout the project. As a result, the initial
hydromet system that was suggested by the consortium in charge of the project design during the first phase was
overambitious. Moreover, the RF lacked coherence, where some IRIs and PDO indicators should have been selected more
carefully, while there were no indicators to measure some important achievements, e.g., UHM National Strategic Plan
2020–2024 of Haiti.
34. Selection of Implementing Agencies. Given the GoH’s ongoing reform stance in 2014, MARNDR, which housed
the UHM, was the natural recipient of the grant, and its functions were retained in lieu of a full-fledged PIU. However,
MARNDR’s capabilities were weak, and they significantly delayed project implementation. For interinstitutional capacity
building, the project targeted the newly created inter-ministerial coordination of the hydromet platform: MARNDR, inter-
ministerial Committee for Territorial Planning (CIAT), Ministry of Environment (MDE), CNIGS, and end users, that required
more strengthening and cohesion.
35. Risk Identification and Mitigation Measures. At appraisal, the project was rightly categorized as “substantial
risk”, and the overall risk rating was increased to “high” in 2017 as the government’s internal stakeholders lacked
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 16 of 46
commitment to the PDO and were holding up on the UHM consolidation and the process for platform integration. Risk
mitigation measures were considered, including re-engaging the dialogue with MARNDR’s new minister and new director
general and setting up a new PIU, which partially helped achieve the PDO.
36. Reputational risks. The project incorporated several measures to ensure transparency in implementation but did
not require a redress mechanism for potential grievances from stakeholders. Moreover, not installing the remaining
stations after project closing could affect the hydromet services in a country prone to extreme meteorological events
and climate change effects.
37. Implementation capacity and sustainability. As project activities were considered simple in relation to
procurement and FM, the World Bank decided to rely on MARNDR and its UPMP to manage the project, where fiduciary
responsibility was under RESEPAG II while the Ministry’s FM unit was being created and made operational. This
arrangement proved ineffective, and the World Bank decided to set up a full PIU after the MTR. The PIU required constant
World Bank support and capacity building.
38. Procurement and FM. Assessments during project preparation had pointed to substantial procurement and FM
risks. At appraisal, the World Bank included two indicators in the Results Framework on procurement and FM reporting
to monitor MARNDR functions (Table 5). The initial arrangements were replaced by a new PIU that required constant
World Bank support to implement the project.
39. Community participation. The project design incorporated the identification of beneficiaries and the inclusion
of women, although the targets were not reached. The targets for training of public servants and NGOs were not reached.
Academia and young students were mobilized to carry out data entry at the UHM as well as field work to improve
hydromet and climate data collection and aggregation.
B. KEY FACTORS DURING IMPLEMENTATION
Factors subject to either or both government and implementing entities control
40. Commitment to hydromet process. After a slow start, MARNDR in conjunction with the MPCE, the Italian
Cooperation, and two targeted NGOs demonstrated a strong commitment to improve UHM’s role by improving and
consolidating the MCH after the MTR. Despite low capacity, MARNDR remained committed to pursuing the PDO by
establishing and consolidating the platform to accommodate five subnetworks to increase Haiti’s disaster and climate
resilience, although it still needs to introduce the hydromet budgetary line to sustain the platform services in the future.
41. Fund flow, staffing, and procurement. Implementation had a slow start, mainly because of the lack of adequate
management, staffing, and delays in procurement of the two main contracts in the initial procurement plan, on account
of MARNDR’s managerial weaknesses to implement the project. The initial project coordinator resigned, and the delays
in bringing a new project coordinator on board after establishing a PIU also affected project implementation. The project
was put on a fast-track disbursement mode after setting up the PIU; however, only 75 percent of the grant was disbursed.
Initially, the project was meant to be implemented through two phases, with one large contract in each phase. After an
initial mis-procurement (as the selected firm misrepresented its capabilities to perform the first phase activities), the
tender was relaunched and the first phase relied on an initial single contract to design, monitor, and develop the project:
the consortium design proved technologically ambitious, while the quality of deliverables was below expectation and
deliverables were not produced on time. After the MTR, the PIU considered three (instead of one) contracts for the
second phase to increase the chances of achieving the targets: (i) hydromet equipment in 62 stations, which were
delivered but only two were installed; (ii) flood modeling for three river basins in lieu of the estimated return period of
selected weather hazards activity, which was not included in the initial scope of work of the project but was awarded to
the same international consulting firm leading the first phase’s consortium, and was canceled as the firm was not able to
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 17 of 46
deliver the flood modeling before closing; and (iii) centralized platform that was initially mis-procured, as none of the
proposals was acceptable and an alternative plan was adopted to select the WMO MCH that proved effective given the
country’s situation. Of the 62 stations, only one company of the 14 (which had downloaded the request for proposal)
submitted a proposal for the delivery and installation of the hydromet equipment. The contract was awarded on an
exceptional basis, even though the financial proposal of US$2.8 million exceeded the World Bank ceiling of US$1.4 million.
After some delays to sort out the newly awarded contract and payment procedures, the equipment delivery and
installation as well as the training were supposed to be completed by July 2020, which turned out to be unrealistic
because of COVID-19 pandemic related delays. In the end, the training was carried out and the equipment was delivered,
but only two stations were installed.
42. Restructuring. An initial restructuring after the MTR, which could have helped revised the scope, results
framework, and deliverables of the project, was not considered. The June 2020 restructuring was carried out after the
COVID-19 pandemic lockdowns and disruptions had delayed the delivery of the hydromet equipment for 62 stations.
However, an extension of only four months was provided based on a corporate decision to extend projects in the Haiti
portfolio only by a minimal extent and instead transfer remaining activities to other on-going projects.
43. Collaborative and participatory approach. Implementation of the project required collaborative work within and
across sectors to set up the MCH, while integrating the five hydromet networks that were initially used independently of
each other. The project sought an effective collaboration with WMO to set up the MCH and to ensure the successful
implementation of the project. This required: capacity building at all levels; data acquisition; development of a strategic
plan; and reaching out to all stakeholders using or needing hydromet services, notably DDAs and CCPCs under the DPC
(that was elevated to a directorate general under the 2020 National DRM system). Such collaboration after the MTR led
to a more effective implementation of most activities than would have been the case otherwise.
Factors subject to the World Bank Control
44. Adequacy of supervision. Ten implementation support missions provided MARNDR with extensive support from
the World Bank, especially after the setting up a new PIU. These missions attempted to put the project deliverables back
on track. The World Bank’s supervision missions helped identify and overcome some of the key implementation
challenges and bottlenecks. Mitigation measures included the setting up of a PIU after the MTR, the capacity building of
the hydromet specialists, and the transfer of the installation of the remaining stations at the end of the project. The last
supervision mission was carried out online due to the COVID-19 pandemic.
45. Regular, strategic, outcome-focused support. The World Bank worked with GoH to institutionalize the MCH
within the newly created UHM and to provide the necessary visibility to UHM to be recognized at the national hydromet
focal point, as well as helped produce the UHM Strategic Plan 2020–2024 to improve and sustain hydromet services in
the future. Despite the turnover of Task Team Leaders, of whom one was based in Haiti from early 2016 to end 2019, the
World Bank team and consultants provided expert guidance during regular missions and interim technical missions on
procurement, financial management, monitoring, and evaluation, as well as the strengthening of hydromet capacity by
hiring two international hydromet consultants. The implementation status and results reports (ISRs) candidly detailed
the project’s setbacks and challenges and recorded the agreed measures to overcome them. Despite all these efforts,
the implementation progress rating remained moderately unsatisfactory during the last three ISRs, as activities were
delayed and canceled.
Factors outside the control of either or both the government and the implementing agency
46. Between project effectiveness in October 2015 and project closing in October 2020, Haiti was hit by 18
meteorological events - floods, hurricanes including the disruptive Hurricane Matthew, and droughts - political and
social unrest, and the COVID-19 pandemic from February 2020 onward. These factors disrupted project implementation
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 18 of 46
and the procurement and installation of the hydromet equipment (see Annex 7). Political gridlock and social unrest,
interspersed with spikes in violence, lasted throughout the project implementation period. Violence and unrest
culminated to new heights during the final two years, especially between October 2019 and January 2020. The
depreciation of the Haitian gourde by 117 percent against the US dollar affected the implementation of some national
contracts. Six new cabinets during project implementation meant multiple re-appropriations for the project by new
ministers at MARNDR, while the lack of MARNDR capacity and UHM appropriation early on also affected project
implementation.
IV. BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME
A. QUALITY OF MONITORING AND EVALUATION (M&E)
M&E Design
47. The PDO indicators and all IRIs except one were linked to PPCR core indicators (Annex 8). The monitoring
arrangements described in the PAD were not always in accordance with generally accepted practices. The project
would use various M&E tools to assess the implementation of the project and its impact on stakeholders and
beneficiaries, including the establishment and operation of: (i) a baseline survey; (ii) semiannual technical and financial
audits; (iii) specific indicators in the results framework to monitor FM and procurement reporting; (iv) an MTR; (v) a final
project evaluation; and (vi) regular M&E reports. Except for the end user’s satisfaction baseline that was carried out at
project end, most baselines were appropriately set during appraisal and remained unchanged during project
implementation, although they should have been adjusted together with the project scope after the MTR through a
restructuring. Some indicators and targets turned out to be too ambitious, as both the country’s FCV conditions and the
COVID-19 added to the uncertainties under which the project was implemented. One PDO indicator was inadequate to
measure the progress of the project towards achieving its objectives: PDO indicator 2 was achieved, however one of the
two IRIs associated with this PDO was not, which is counterintuitive. Instead, “number of new stations and existing
stations feeding into the centralized platform” should have been the PDO indicator 2. The M&E system did not also
capture the formulation of the UHM Strategic Plan 2020–2024, the training of CCPC and DDA staff, measure the
institutional progress of the UHM and its financial sustainability. The targets for the training of hydromet specialists and
gender training were set too high in the Haiti context and were not achieved.
M&E Implementation
48. The M&E system was not implemented until 2019, as activities picked up only then. Even thereafter, the
progress reports did not provide updates on all the agreed indicators. M&E data on most activities under Component 1
were collected, measured, recorded, analyzed, verified and stored (including data disaggregated by gender) based on
the RF. However, M&E data on the remaining Component 2 activities were not collected, as these activities were not
implemented. Regarding the PDO indicator 3, the user’s satisfaction baseline (35 percent satisfaction) sample was much
larger than the user satisfaction (52 percent satisfaction) target sample and both the baseline and the target results of
PDO indicator 3 are questionable although it had achieved an improvement by a 1.5 factor by the end of the project as
reported in the RF PAD. However, a new end target of user’s satisfaction of 100 percent was introduced in the RF in the
ISR 4 of May 2017 without any explanation. This target was considered to rate the achievement of the PDO indicator 3.
M&E Utilization
49. Reports and information submitted by MARNDR provided key inputs to prepare the MTR and the ISRs,
although some delays were reported. Data were collected and analyzed on outcomes and outputs for PDO#1 and PDO#2
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 19 of 46
and their IRIs when the project relied on both MARNDR functions and post-MTR PIU, resulting in a “moderately
satisfactory” rating for M&E by project end.
Justification of Overall Rating of Quality of M&E
50. Overall M&E quality is rated as modest. The M&E design was inadequate, and its implementation was not timely
to assess the achievement of the PDO and measure project implementation progress.
B. ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE
51. Compliance with overall social and environmental safeguards is rated satisfactory. The project was assessed to
be an environmental risk category B investment under the World Bank’s Operational Policy on Environmental Assessment
(OP/BP 4.01) and was rated as an extremely low environmental risk. PGRAC will be responsible for ensuring safeguard
compliance for the installation of the remaining stations under RESEPAG II, as full coordination between the two projects
is required to achieve the deferred targets of the project.
52. The project implemented the environmental safeguard policies effectively. It maintained and replaced two
hydromet equipment and provided services and capacity building for these two stations. Awareness-raising and
communication activities were carried out at both sites to ensure the engagement and support of the two local
communities. During project implementation, compliance with safeguards remained “satisfactory” as: (i) the
environmental and social management framework (ESMF) was prepared and updated after the setup of PIU to include
social issues such as the right of way, and the safeguard instruments were implemented smoothly; (ii) the safety of workers
involved in the repair or removal of equipment was maintained; and (iii) possible exposure to minor electromagnetic fields
was avoided. The project identified and screened the locations for most, if not all, of the 50 stations for environmental
and social impacts, and the due diligence screening performed by the firm retained to procure and install the stations was
satisfactory to the World Bank. This screening will be used to install the remaining stations.
53. Social safeguard policies were also effectively implemented by the project through the two installed stations.
The project is composed of a series of TA activities and instrument installation on government-owned sites involving
minimal safeguard implications. It did not trigger either OP 4.10 or OP 4.12 and did not affect people. Sites affecting
populations that might trigger OP 4.12 were not considered. The project did not implement a grievance redress
mechanism (GRM), as a GRM was not required. Site visits allowed the client to monitor measures to prevent or mitigate
social impacts. The ISRs rated compliance with social safeguards as “satisfactory” throughout the project.
54. Financial Management. Compliance with the project’s FM was satisfactory throughout project implementation.
After the MTR, the project accounting was transferred to the Accounting Package (ACCPAC) system that was finally up and
running by the end of the project, although it was supposed be active by the end of 2018. Interim financial reports (IFRs)
and financial audits were provided on time and were accepted by the World Bank. The World Bank team provided
guidance as required to project FM staff, who were proactive and responsive.
55. Procurement. Compliance with the project’s procurement regulations was satisfactory until 2017 but was
downgraded to moderately satisfactory from 2018 to 2019 and was further downgraded to moderately unsatisfactory at
closing. The capacity to produce, launch, and evaluate the challenging tenders was the issue that delayed project
implementation during the project’s first and second phases. Procurement remained rated as satisfactory until 2017 due
to the timely issuance of a few fairly straightforward bid documents, evaluation of bids, and proposals. However, there
were significant delays in major procurements for the second phase’s implementation of the UHM development plan.
Moreover, the consortium executing the first phase of the project (design, monitor, and develop the project elements)
not only delayed the deliverables as set in the timetable but also delayed the issuance of payment receipts. The creation
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 20 of 46
of a PIU after the MTR improved the procurement process, including the introduction of the Systematic Tracking of
Exchanges in Procurement (STEP, which had been requested by the World Bank since 2016). Contract management was
also a challenge and resulted in delays and poor implementation of contracts, while the cancellation of some contracts
before closing was warranted due to the accumulated delays. Under Component 3, as the project had initially planned to
rely on MARNDR’s own staff for project management, two project management indicators, which usually do not belong
in the RF, were added (Table 4)
56. Fiduciary Indicators. The Results Framework included procurement and FM indicators and both indicators met
their targets by closing.
Table 4: Extent of Achievement of IRI Project Management Reporting Targets
Intermediate Results Indicators: Support to project implementation,
monitoring and evaluation, and PPCR knowledge management
Baseline/
Unit
Target Number
Achieved
%
Achieved
Timely submission of project procurement reports No Yes Yes 100%
Timely submission of financial management reports No Yes Yes 100%
Note: Percentage achieved is color coded: yellow – not achieved set target; and light green – achieved set target.
C. BANK PERFORMANCE
Quality at Entry
57. The World Bank built on the WMO’s stance in preparing the project using a phased approach to ensure
effectiveness. The development of project activities was based on the WMO’s Climate Services to Reduce Vulnerability
in Haiti that notably led to the creation of UHM under MARNDR, a World Bank assessment (Institutional Expertise of
Haiti's Hydromet Service, 2014 carried out by WMO consultants), and the 2012 Haiti SPCR and PPCR practices. The
housing of UHM under MARNDR should have been more carefully assessed by the World Bank, and housed, like CIAT,
under an overarching institution, such as the premiership, although CIAT is still facing weaknesses. However, activities
were selected and implemented after close consultations with GoH and with the stakeholders who would benefit from
hydromet services: (i) MARNDR housing UHM, DDAs and National Coordination of Food Security; (ii) CIAT under the
tutelage of the premiership; (iii) MPCE housing CNIGS; (iv) MDE housing the climate change division; (v) Ministry of
Interior and Territorial Communities (MICT) housing the DPC and the Department of Territorial Communities; and (vi)
Ministry of Public Works, Transport and Communications housing the Haiti Maritime and Navigation Service, the Urban
Planning Service, and the National Civil Aviation Office that eventually transferred some of its staff to work within UHM
premises after 2017. Project activities provided tailormade TA to pursue hydromet system strengthening and to build
capacity within: (i) UHM and across institutions, such as the CNIGS and the DPC, for communications and early warning
systems; and (ii) the CNIGS for Earth observation data and agencies within ministries, such as the DDAs. Although
drawing from the World Bank’s global experience across several hydromet projects, the project team did not fully
benefit from the lessons from investments in Haiti, e.g., the 2009–2015 Emergency Bridge Reconstruction and
Vulnerability Reduction Project (PROReV) that oversaw the production by CIAT of the National Multihazard Atlas, as
well as the 2012–2020 “Disaster Risk Management and Reconstruction Project” (PRGRD) that installed early warning
communication systems and capitalized on the ongoing dialogue with the GoH regarding disaster risk management and
climate change.
58. The project basics were not sound and the project components not well targeted; the delivery mechanisms
were assumed to be effective, in particular the fiduciary aspects, despite the FCV context. The World Bank should
have paid more attention during project preparation to meet its strategic, technical, economic, financial, safeguard,
fiduciary, and institutional requirements. The project was overambitious, and the targets should have been selected
more realistically. A better institutional assessment was needed on the adequacy of anchoring hydromet services
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 21 of 46
within MARNDR. Some of the fiduciary and institutional aspects proved to have been inadequately assessed, as
observed during project implementation. The risk assessment was comprehensive, and appropriate risk management
measures were included in the project design and in the implementation support plan. However, the RF did not
capture the breadth of the project, as the six IRIs did not accurately measure the activities that would contribute to
the achievement of the three PDO indicators. Moreover, the latter did not consider UHM’s sustainability as a corner
stone of the country’s entire hydromet and early warning systems, and as one of the ISN’s priorities in reducing
vulnerability and increasing resilience. Triggered by the COVID-19 pandemic, the restructuring came too late, but was
nevertheless essential at the end of the project to extend the project closing by four months to ensure that the
hydromet equipment was delivered by the closing date.
Quality of Supervision
59. The World Bank provided timely and adequate support and guidance to the project through biannual
supervision missions and frequent informal contacts and technical discussions. Nevertheless, implementation of
the project stalled until MTR’s mitigation measures to set up a PIU and reconsider the deliverables and the
timetable. Constant dialogue with multi-stakeholders and development partners were integral to the supervision
missions. Yet, it took more than two years for the World Bank to react effectively to the reality that the project was
not moving. Hence, although the achievement of the PDO was the team’s high priority, and the Bank’s efforts and
constant technical support to the PIU helped bring the project back on track, the pace of implementation was too
slow to achieve the targets set. The World Bank team reported on project status candidly in periodic aide-mémoires
and ISRs and highlighted the shortcomings, challenges, and actions required to get the project back on track after the
MTR, including a project extension to realize planned outputs and outcomes. Such actions included direct and
consultant support through training and assistance, especially for procurement after the setting up of the PIU. The
World Bank team maintained an exceptionally good working relationship with WMO during the MCH set up, which
helped put the project back on track.
Justification of Overall Rating of Bank Performance
Rating: Moderately Unsatisfactory
60. Based on the above discussion, the World Bank’s performance is rated “Moderately Unsatisfactory”.
D. RISK TO DEVELOPMENT OUTCOME
61. The 2012 SPCR allowed the setting up of interministerial coordination of the hydromet platform, create the
platform under one entity (UHM), and consolidate the platform (MCH) to increase disaster and climate resilience
across sectors and themes, for example, energy, transport, environment, agriculture, gender, and poverty
reduction. The UHM Strategic Plan 2020–2024 prepared under the project sets clear priorities to improve and
maintain the platform. The project faces moderate risk to sustainability in the short term, as the installation of the
stations will be carried out under RESEPAG II with TA from the PGRAC and will benefit from parallel ongoing projects
implemented by development partners (such as the ongoing multi-donor CREWS project and WMO capacity
strengthening). However, the moderate risk to sustainability could increase in the medium term, should the UHM’s
institutional and financial sustainability not be realized as articulated in the UHM Strategic Plan 2020-2024. When the
hydromet platform is fully operational and UHM is provided a dedicated budget and charges a fee for services, it will
have the capacity to perform simulations and projections that will inform the formulation of strategies and policies,
improve decision making as well as the design of programs and projects to manage future climate and disaster risks
better.
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 22 of 46
62. Political instability, the difficult economic outlook, the COVID-19 pandemic, and civil unrest continue to remain
an important characteristic of Haiti’s landscape. While the UHM has been created and a strategy has been
formulated, the open access and increased number of end users should be accompanied by political commitment,
dissemination to NGOs, and buy-in from beneficiaries to maintain the momentum of mainstreaming, consolidating,
and disseminating hydromet services.
V. LESSONS AND RECOMMENDATIONS
63. The lessons learned are articulated along six themes in an FCV country: new project versus additional financing
for an ongoing project, design, management, procedures, contractual arrangements, and institutional and financial
sustainability of hydromet.
64. Given the small size of the grant, there is a need to better gauge the pros and cons of preparing a standalone
project against adding the grant to an ongoing project, as small projects do not attract political commitment and
support from governments. For the various reasons discussed earlier, the project was not effective as the hydromet
stations were not installed, the UHM institutional strengthening under MARNDR was incomplete, and the
sustainability of the UHM was not considered. Low institutional capacity was also one of the reasons for the project
to have several setbacks, despite the initial positive context during project preparation. Development agencies,
including the World Bank, need to carefully gauge the trade-offs between having a standalone project versus attaching
relatively small grants to ongoing projects with already established and functioning implementation arrangements.
This would also optimize administration costs, as the running costs of a PIU can be high, especially in FCV countries.
Adding the grant to the ongoing RESEPAG II under MARNDR should have been judiciously considered by the Bank.
65. There is a need to consider very simple project designs and strike the right balance between the technology
considered and the technical capacity of the various institutional stakeholders, where service provision should be
decoupled from system expansion. Capitalizing on and strengthening the existing system should be the priority of
decision makers before embarking on a system expansion. Albeit unfinished, the strengthening of services brought
the UHM to the fore, especially during Hurricane Laura in 2020, where UHM’s critical information was used before,
during, and after the event. The project design favored not only a system expansion, but also a hi-tech platform where
technology should be relative to its absorptive capacity. The selection of a hi-tech platform resulted in limited supplier
participation in procurement processes, as only a limited number of international firms had the technical and financial
capacity to execute the activities while small local firms (that had the knowledge to customize hydromet systems to
the needs and capacity of the country) were sidelined. It is imperative to consider existing services, the reality of the
market and the institutional capacity of the recipient when designing activities, so that they are properly calibrated to
an FCV country to allow for the gradual strengthening of the system first and then moving to system expansion by
relying on a wider range of firms (including local firms) to respond to procurement processes. The very sophisticated
and costly hydromet system recommended by the international consortium proved to be unrealistic and ineffective
and was therefore replaced by a more user-friendly and robust platform.
66. In FCV contexts, implementation arrangements relying on the recipient’s own structures should not be
considered, while the political and socioeconomic context should be closely monitored to trigger restructuring in
time for course corrections. In an FCV country with low capacity, relying on the recipient’s own newly created
structures proved to be ineffective and costly. The World Bank had to set up a PIU after the MTR in December 2018
as project implementation and disbursement faced substantial delays. Moreover, close monitoring and strong World
Bank technical support to the PIU were needed to compensate for the low technical and project management
capacity, including contract management capacity. Accurately assessing recipient capabilities and financing of the
essential human resources for key project management functions including procurement (for contract size, scope, and
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 23 of 46
number) as well as FM is essential to avoid having to rely on other World Bank project PIUs or structures outside the
PIU.
67. Splitting the project into two large contracts - one for the diagnosis, design, and supervision, and the other for
implementation - awarded to two different firms could present various implementation challenges in the context
of the recipient’s limited institutional and technical capacities. The split between the soft and the hard contracts
caused multiple slowdowns by increasing the number of stakeholders and diluting responsibilities. As a result, the
coordination and the establishment of effective and transparent communication between the actors - firms, PIU, and
UHM - proved to be challenging.
68. As already evidenced in other recent projects in Haiti (PROReV and PRGRD), relying on contractual
arrangements with clearly defined scope, timelines, and judicious technical choices proved to be a good practice.
The close coordination - with actions supported by WMO from the project design stage and throughout project
implementation, and during the installation of the WMO-based MCH - was effective and allowed synergies,
complementarities, and optimization of resources leading to positive results. The approach adopted by the World
Bank and WMO after the MTR was adopted for the development of the multi-donor CREWS in the CARICOM member
countries.
69. The institutional and financial sustainability of a hydromet entity such as UHM in a country prone to extreme
meteorological events and increased vulnerability caused by climate change requires the utmost attention of
development partners and long-term commitment, as such development outcomes take time to be achieved. The
institutional anchoring of the hydromet system should not be taken for granted and requires careful consideration as
the setting up of the system at the UHM under MARNDR lacked the necessary GoH buy-in while the UHM requires
long-term strengthening and support. Conversely, the financial sustainability of a hydromet system should be carefully
considered by supplementing budgetary appropriation with grants from development partners, as well as the
introduction of fee-based hydromet services. The hydromet system is the end goal of a value chain of information that
would provide the country’s stakeholders with critical information for strategies, policies, preparedness, and
response. Setting up an efficient hydromet system is time consuming, but it is an essential building block of a disaster
risk management strategy. For instance, the feeding of information into peripheral early warning systems will be
provided from the hydromet system. Conversely, a poorly performing system will hamper the effective performance
of these early warning systems that are imperative to reducing vulnerability and increasing resilience in an FCV
country.
.
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 24 of 46
ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS
A. RESULTS INDICATORS
A.1 PDO Indicators
Objective/Outcome: Hydro-meteorological and climate information services are provided to increase disaster resilience
Indicator Name Unit of Measure Baseline Original Target
Formally Revised
Target
Actual Achieved at
Completion
Data collected from hydro-
met networks are accessible
on a centralized online hydro-
meteorological data
management platform, with i
ts own operating procedures
for validation and storage
Yes/No N Y N
30-Jun-2015 30-Jun-2015 29-Oct-2020
Comments (achievements against targets):
Data collected from hydromet networks are centralized in an hydromet data management platform, accessible to end users upon request and not online.
Therefore, the PDO was not achieved. WMO technical assistance worked with UHM on setting up the online portal for direct data sharing and WMO is
continuing the process under their own ongoing project.
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 25 of 46
Indicator Name Unit of Measure Baseline Original Target
Formally Revised
Target
Actual Achieved at
Completion
Number of sub-networks
feeding into the centralized
platform
Number 0.00 5.00 5.00
06-Jun-2015 30-Jun-2015 29-Oct-2020
Comments (achievements against targets):
The sub-networks feeding into the UHM centralized platform were set up by the end of June 2020.
Indicator Name Unit of Measure Baseline Original Target
Formally Revised
Target
Actual Achieved at
Completion
End users' satisfaction rate
towards improved hydromet
information services
Percentage 35.00 53.00 52.00
30-Jun-2015 30-Jun-2015 29-Oct-2020
End users' satisfaction rate
towards improved
hydromet information
services (gender
disaggregated)
Percentage 21.00 42.00 21.00
30-Jun-2015 30-Jun-2015 29-Oct-2020
Comments (achievements against targets):
In the PAD the end target for this indicator is “baseline * 1.5”, leading to end target of 53%. However, in ISRs starting on May 2017, the end target was set
to 100%, but was not formally revised. This value that was considered for the evaluation. The achieved target was only 52 percent of the end-
users satisfaction with the MCH as the online portal was still not fully operational by project end. The gender target was doubled to reach 42% against 50%
targeted. To derive the values of this indicator, a second satisfaction survey was conducted with a sample of 83 entities: Community organization such as
Citoyenneté et Inclusion (Citizenship and Inclusion); Service Maritime et de Navigation d'Haïti (Haiti Maritime and Navigation Service) ; Bureau Agricole
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 26 of 46
Communale (Communal Agricultural Office); CCPCs; Coordination Départementale de Gestion Des Risques de Désastres (Departmental Coordination of
Disaster Risk Management); and DDAs. However, this represents half of the sample that was considered in the first survey and includes, apart from NGOs
and some self-governing institutions, the same categories of users. The 52 percent of the end-users satisfaction is not as representative as the first survey
that was carried out to draw the baseline of 35 percent.
A.2 Intermediate Results Indicators
Component: Identification of hydro-meteorological and climate services’ requirements for select end users and development of information services to
support decision making
Indicator Name Unit of Measure Baseline Original Target
Formally Revised
Target
Actual Achieved at
Completion
Number of users and
instructors trained on the
use of the centralized data
platform
Number 0.00 80.00 9.00
30-Jun-2015 30-Jun-2015 29-Oct-2020
Number of users and
instructors trained on the
use of the centralized data
platform (% of women)
Number 0.00 20.00 3.75
30-Jun-2015 30-Jun-2015 29-Oct-2020
Comments (achievements against targets):
Nine of 80 targeted staff members were fully trained to develop data management capacity of the producers and users of hydromet data. Four female staff
members were trained, which is also below target.
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 27 of 46
Indicator Name Unit of Measure Baseline Original Target
Formally Revised
Target
Actual Achieved at
Completion
Hydrological and
meteorological stations
reporting data to the
platform in line with agreed
SOPs
Number 0.00 34.00 34.00
30-Jun-2015 30-Jun-2015 29-Oct-2020
Comments (achievements against targets):
The national Hydromet platform that was installed and relies on the MCH open-source software developed by WMO and is hosted in a permanent server.
However, the platform hosts data from 34 stations from the five networks is not being constantly updated to remain in sync with the software upgrades
carried out by the stations from the 5 networks. Since February 2020, the World Bank and WMO have installed the MCH. Four manuals were prepared for
the standard operating procedures and used for online training to: (i) provide the procedure by which MCH users can enter the information from
observations to the system through the MCH client; (ii) provide the procedure by which MCH users can enter the information from observations to the
system through the MCH website; (iii) provide a procedure for loading data from Davis automatic weather stations of the ProVantage and ProVantage2
models; and (iv) help users develop Excel sheets that can extract data directly from the MCH database.
Indicator Name Unit of Measure Baseline Original Target
Formally Revised
Target
Actual Achieved at
Completion
Operational stations
(physical structure)
Number 0.00 50.00 2.00
30-Jun-2015 30-Jun-2015 29-Oct-2020
Comments (achievements against targets):
A contract for the supply and delivery of key Hydro-met equipment was signed in February 2020 between MARNDR and the firm BFOR and the delivery and
installation of 62 stations were planned to be completed before the end of June 30, 2020, the grant’s closing date. However, due to travel restrictions
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 28 of 46
linked to COVID-19 (the suppliers are based in Germany and Spain, which were very affected by the pandemic between March and June 2020) the delivery
was postponed to the end of July and the installation was planned be completed before the end of October 2020. However, only two stations have been
installed by the closing date and were not connected to the MCH.
Component: Support to project implementation, monitoring and evaluation, and PPCR knowledge management
Indicator Name Unit of Measure Baseline Original Target
Formally Revised
Target
Actual Achieved at
Completion
Timely submission of project
procurement reports
Yes/No Y Y Y
30-Jun-2015 30-Jun-2015 29-Oct-2020
Comments (achievements against targets):
Procurement reporting was regularly submitted before and after the setting up of the PIU after the MTR.
Indicator Name Unit of Measure Baseline Original Target
Formally Revised
Target
Actual Achieved at
Completion
Timely submission of
financial management
reports
Yes/No Y Y Y
30-Jun-2015 30-Jun-2015 29-Oct-2020
Comments (achievements against targets):
Financial management reporting was regularly submitted before and after the setting up of the PIU after the MTR.
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 29 of 46
Component: Institutional strengthening of hydro-meteorological services and development of data management tools
Indicator Name Unit of Measure Baseline Original Target
Formally Revised
Target
Actual Achieved at
Completion
Number of Civil Protection
Committees using the
customized application from
the centralized data platform
Number 0.00 40.00 0.00
30-Jun-2015 30-Jun-2015 29-Oct-2020
Comments (achievements against targets):
CCPCs were trained on initial products but the customized application was not finalized. Therefore, this indicator did not achieve its set targets.
Indicator Name Unit of Measure Baseline Original Target
Formally Revised
Target
Actual Achieved at
Completion
Number of Departmental
Agricultural Directions (DDA)
using the customized
application from the
centralized data platform
Number 0.00 10.00 0.00
30-Jun-2015 30-Jun-2015 29-Oct-2020
Comments (achievements against targets):
DDAs were trained on initial products but the customized application was not finalized. Therefore, this indicator did not achieve its set targets.
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 30 of 46
Indicator Name Unit of Measure Baseline Original Target
Formally Revised
Target
Actual Achieved at
Completion
Direct project beneficiaries Number 0.00 1,000,000.00 0.00
30-Jun-2015 30-Jun-2015 29-Oct-2020
Female beneficiaries Percentage 0.00 0.00 0.00
Comments (achievements against targets):
As the MCH is not fully operational as targeted by the project objective, therefore the beneficiaries, of whom women, will not benefit from the project.
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 31 of 46
B. KEY OUTPUTS BY COMPONENT
Objective/Outcome 1: Strengthening Haiti’s institutional capacity to provide hydromet and climate information services
Component 1: Outcome Indicators
1.1 Data collected from hydromet networks are accessible on a centralized online
hydro-meteorological data management platform, with its own operating
procedures for validation and storage - Partially achieved.
1.2 Number of subnetworks feeding into the centralized platform - Achieved.
Intermediate Results Indicators
1.2.1 Number of users and instructors trained on the use of the centralized data
platform of whom women – Not achieved.
1.2.2 Hydrological and meteorological stations reporting data to the platform in line
with agreed standard operation procedures – Achieved.
1.2.3 Operational stations – Not achieved.
Objective/Outcome 2: Strengthening Haiti’s institutional capacity to customize hydromet and climate information to the needs of the civil
protection and agriculture sectors
Component 2: Outcome Indicators
2.1 End users' satisfaction rate toward improved hydro-met information services, of
whom women – Not achieved.
Intermediate Results Indicators
2.1.1 Number of Civil Protection Committees (CCPCs) using the customized
application from the centralized data platform – Not achieved.
2.1.2 Number of Departmental Agricultural Directions (DDAs) using the customized
application from the centralized data platform – Not achieved.
2.1.3 Direct project beneficiaries of whom women – Not achieved.
Component 3: Project Management: Procurement and Fiduciary Reporting
Key Outputs
3.1 Timely submission of project procurement reports – Achieved.
3.2 Timely submission of financial management reports – Achieved.
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 32 of 46
ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION
A. TASK TEAM MEMBERS
Name Role
Preparation
Gaetano Vivo Task Team Leader(s)
Prosper Nindorera Procurement Specialist(s)
Fabienne Mroczka Financial Management Specialist
Claudia Ruth Soto Orozco Team Member
Rose Caline Desruisseaux-Cadet Team Member
Josue Akre Team Member
Jean Baptiste Migraine Team Member
Ramiro Ignacio Jauregui-Zabalaga Counsel
Peter F. B. A. Lafere Social Specialist
Michel Matera Team Member
Nancy Chaarani Meza Team Member
Nyaneba E. Nkrumah Social Specialist
Carolina J. Cuba Hammond Team Member
Victor Manuel Ordonez Conde Team Member
Aboubacar Magassouba Team Member
Supervision/ICR
Claudia Ruth Soto Orozco Task Team Leader(s)
Mamata Tiendrebeogo, Aboubacar Magassouba Procurement Specialist(s)
Lucas Carrer Financial Management Specialist
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 33 of 46
Alfred Jean-Marie Borgonovo Financial Management Specialist
Eduardo Porras Calderon Team Member
Noris Viviana Sandoval Sierra Procurement Team
Maria Laettitia Antoine Procurement Team
Marie Eleonor Jean Baptiste Procurement Team
Jean Noel Degrace Team Member
Marcela Nandllely Gonzalez Team Member
Naraya Carrasco Team Member
Djeanane Monfort Procurement Team
Kevin McCall Environmental Specialist
Khaled Mohamed Ben Brahim Team Member
Ramiro Ignacio Jauregui-Zabalaga Counsel
Ingrid Sandra Milord Procurement Team
Hadji Huseynov Team Member
Peter F. B. A. Lafere Social Specialist
Felipe Jacome Social Specialist
Pepita Hortense C. Olympio Procurement Team
Asli Gurkan Social Specialist
Andrianirina Michel Eric Ranjeva Team Member
Ali Alwahti Procurement Team
Carl Christian Gyde Jacobsen Team Member
Isabella Micali Drossos Team Member
Brad Kelly Lassiter Procurement Team
Manju Ghumman Team Member
Carolina J. Cuba Hammond Team Member
Serge A. Pieyns Team Member
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 34 of 46
B. STAFF TIME AND COST
Stage of Project Cycle
Staff Time and Cost
No. of staff weeks US$ (including travel and consultant costs)
Preparation
FY14 8.775 94,977.95
FY15 18.791 118,721.71
FY16 16.992 77,499.30
Total 44.56 291,198.96
Supervision/ICR
FY16 1.900 13,978.00
FY17 19.218 158,421.23
FY18 12.975 111,824.04
FY19 1.032 75,989.59
FY20 9.574 88,226.63
Total 44.70 448,439.49
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 35 of 46
ANNEX 3. PROJECT COST BY COMPONENT
Components
Amount
at
Approval
Amounts
reallocated
between
disbursement
categories
during FY20
Actual
at
Project
Closing
(US$M)
Percentage
of
Approval
(US$M) (US$M) (US$M) (%)
Institutional strengthening of hydro-
meteorological services and development of
data management tools
3.00 1.75 0.54 18%
Identification of hydro-meteorological and
climate services’ requirements for select end
users and development of information
services to support decision making
1.40 2.36 1.90 136%
Support to project implementation,
monitoring and evaluation, and PPCR
knowledge management
0.60 0.90 0.80 133%
Cash in Government’s account at the end of
the project
0.53
Total 5.00 5.00 3.77 75%
Note: Grant amount of US$ 5 million was not allocated by component as reported in the Grant Agreement where
eligible costs included: Goods, non-consulting services, consultants' services, Training and Operating Costs.
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 36 of 46
ANNEX 4. EFFICIENCY ANALYSIS
Ex-Ante Economic Analysis
1. Since 2010, Haiti’s weather forecasts and severe weather warnings are based on models and analysis run abroad
(mainly by US NOAA and Méteo France). Moreover, there were no seasonal forecasts or timely planting and harvesting
advisories adapted to the local conditions/data that could enhance the productivity of farming, particularly as climate
change undermines the predictive value of historical climate knowledge and associated traditional practices. This left an
opening for producing more adapted forecasts and warnings, thus diminishing the loss of lives and assets while
increasing agricultural production in this highly climate-vulnerable country.
2. An ex-ante economic analysis of the project investments confirmed a positive return on investment, with a very
wide benefit/cost ratio between 1.6 and 33 over a 15-year timeframe. These results were based on international
benchmarks
15
reported in percentage of GDP. In the case of Haiti, this was supposed to translate into gains of
approximately 0.03% and 0.3% of GDP.
Ex-Post Economic Analysis
3. As the Hydro-met project missed its objective of setting up and operationalizing the MCH, the benefits of the
project will accrue in the future under RESEPAG II. By the end of the project, the MCH integrated 34 stations from five
subnetworks and improved the efficiency of hydromet services. However, while end-user access will improve, CCPC and
DDA staff, although trained, are not yet using the data to perform the needed forecasts for meteorological events and
for meteorological-based agricultural management. Table 4.1 summarizes the results of the ex-post economic analysis.
Table 4.1: Ex-Post Benefit-Cost Analysis of the Hydro-met Project
Indicators Discount Rates over 20 years Criteria
4% 6% 8%
NPV (US$ Million) Negative Negative Negative >0
ERR (±%) Negative Negative Negative ≥ discount rate considered
PVBCR <0 <0 <0 >1
15
A Cost-Effective Solution to Reduce Disaster Losses in Developing Countries: Hydro-Meteorological Services, Early Warning, and
Evacuation (World Bank Policy Research, Working Paper #6058, 2012)
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 37 of 46
ANNEX 5. BORROWER, CO-FINANCIER AND OTHER PARTNER/STAKEHOLDER COMMENTS
MINISTRY OF AGRICULTURE, NATURAL RESOURCES AND RURAL DEVELOPMENT (MARNDR)
HYDROMETEOROLOGICAL UNIT (UHM)
COMMENTS ON THE FINAL EVALUATION OF THE
HT Strengthening Hydro-Met Services Project (HYDROMET)
TF-0A0226 GRANT AGREEMENT
FUNDING: Strategic Climate Fund-Pilot Program for Climate Resilience
Prepared by:
Coordination of the UHM
April 2021
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 38 of 46
Background and Institutional Anchor
The Hydromet project, although with limited resources, has been of great strategic importance to the Haitian
state as it aimed of improving access to good quality data and information for rational multi-sector decision-
making. It is in this sense that the Haitian State, through the MARNDR, was committed to this project from the
onset using its various operational bodies and which continue to be strengthened, i.e., the administrative and
technical structures.
Administrative Structure
From an administrative point of view, the HYDROMET project benefited from the experience of the RESEPAG II
project financial management and the MARNDR Public Procurement Unit (UPMP). The latter are entities with full
decision-making autonomy in strict compliance with Haitian laws’ procedures and World Bank directives. Apart
from the long delay in starting the project, these two entities were able to fulfill their mission with
professionalism despite a difficult socio-political context since 2018. However, it is important to draw attention
to UPMP staff that operated with a reduced number of UPMP executives. All staff, consultant or service contracts
go through the UPMP for all projects’ foreign funds provided to MARNDR. The available staff are constantly
overwhelmed by a flood of files. So inevitably, there are inevitable delays in processing of these files. The
Hydromet project suffered like any other project. It would have been wise for the projects to support the
recruitment of additional UPMP staff and the strengthening of capacity of the new recruits through ongoing
training.
Technical Structure
The Hydrometeorological Unit (UHM) was the technical anchor of the project and was to be the main beneficiary
of the strengthening planned by HYDROMET. However, at the time of launching the Hydromet project in 2015,
the UHM was not operational as CNM and the SNRE with each a department head were not yet merged under
UHM. It was not until the May 2017 inauguration of UHM new premises and subsequent move of the staff,
furniture and equipment in December 2018 and the nomination of a new coordinator (UHM) on January 30, 2018
that UHM became operational. The absence of an active UHM Coordinator during the first 3 years of project
implementation and a lack of ownership did not help the project to start under the best technical conditions. The
difference was noticeable from 2018 onward with greater involvement of the UHM through its new coordinator.
The Project Coordination Unit
The project was administered by a coordination unit comprising a coordinator, a mid-level executive as well as a
monitoring and evaluation (M&E) specialist. The first major challenge of the project was the resignation of its
first coordinator in the 19
th
month of implementation. It took nine months to formally replace him. The
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 39 of 46
recruitment of the M&E specialist was delayed and occurred in mid-2018.
Difficulties
External Difficulties
Haiti's socio-political environment from 2018 until project closing in October 2021 did not really play in the
project's favor. The year 2019 that should have been the year of the implementation of the second phase of the
project and was marked by a total shutdown over several months. This situation has disrupted the tendering
schedule and led to the forced cancellation of most of the tenders when the situation worsened in early 2020
globally due to the COVID-19 pandemic. The latter has imposed a near-global blockade that prevented the
execution of the major contract consisting of the acquisition and installation of hydrometeorological stations and
forced the cancellation of the modelling tender as well as the development of the platform tailored to the users’
needs. To compensate for this, the World Bank has granted an extension of four months to compensate for the
delays, but the extension was largely insufficient to complete the latest activities of the project, in particular
those of the second phase.
Recommendations of the November 2018 Mid-Term Review Report
During the mid-term review, the coordination of the project drew the attention of the World Bank to the fact
that the initial objectives do not have a high probability of being achieved without an extension of at least
eighteen months, thus until 31 December 2021. The report even proposed scenarios to address these issues, i.e.,
for the activities that would not be completed by 30 June 2020. Moreover, at that time the coordination could
not even foresee the 2019 shutdown and the 2020 pandemic. The finding of the project initial delays should have
encouraged the World Bank to accept an obvious and longer extension of the project. We believe that this unique
decision would have made a very big difference in the outcome as well as a better evolution of the indicators.
We continue to regret this decision, which took little account of the difficult history of the project, especially at
the start-up.
Gains and Perspectives
Despite the many difficulties that have compromised some of the important results expected of the project, it is
important to note that the project leaves several achievements that will need to be consolidated. The project
has contributed to confer a certain national notoriety to the UHM in the sector. The project enabled the
furnishing of the workspace and the acquisition of specialized office computer equipment for the MCH platform
acquired under the project. The UHM now has a platform to collect, process and interpret data produced in the
field in real time. Through this project, UHM executives have benefited from several online and in-person training
courses on various branches related to the field of hydrometeorology. The UHM, in turn, organizes training
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 40 of 46
sessions for key users (DDA, BAC, CDPC, CCPC) on the efficient use of its various products. These trainings,
coupled with open houses for children and adults, have finally ensured that the UHM has a high profile in the
country.
One of the significant achievements of the Hydromet project is the development of key documents as part of the
first major design contract. These are the first documents that certify UHM as a full-fledged entity with clear
responsibilities and competences. These documents complete the circular creating UHM. These include the
diagnosis of the Haitian hydrometeorological sector and inter-institutional coordination, followed and especially
the development plan of the UHM with a business plan and an evolutionary budget preparation mechanism over
the next ten years. This document served as the basis for the development of the National Strategic Plan (2020-
2024). Add to this the design of the UHM's optimum network, which takes into account its capabilities as well as
its technical and budgetary limitations.
Another important achievement is the acquisition of Hydromet stations, which will be distributed across various
priority regions of the country. All the equipment was acquired and stored at the UHM premises. As of October
30, 2020, two stations have been installed in Léogâne (Momance River) and Damien. Constant follow-up is
provided with the selected company to continue the installation of stations during the year 2021. The UHM hopes
to have nearly 40 new stations installed and operational by the end of August 2021.
All these achievements have enabled UHM to position itself as the true leader in the field of hydrometeorology
in Haiti.
Thus, the project has provided the UHM with tools to move towards its autonomy.
General Considerations and Recommendations
The evaluation strategy of the project affected the evolution of the indicators after the execution of the first
major design contract and from the execution of the second major contract. Any delay or inconvenience in the
original contract would logically have had a negative impact on the start of Phase 2. Thus, this first tender, which
was initially declared unsuccessful, greatly delayed the key activities of the second phase to which all indicators
are linked. The evaluation strategy of the project did not take into account at the outset the significant
achievements of the first major contract through mainly the development plan of the UHM. The latter could have
been one of the indicators of the project.
Furthermore, we believe that on the basis of the mid-term review carried out by the project team in November
2018, the stakeholders could logically have restructured the project or extended the project substantially:
• All project partners believe that the project has closed almost at the time of its actual start, so they
would like to see a HYDROMET 2 project to consolidate the achievements of the HYDROMET 1 project.
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 41 of 46
The UHM still needs sustained support to be able to fulfill its mission.
• It is recommended that the implementation of the different phases of the projects be made more
flexible. A long delay in Phase 1 can jeopardize its related activities in Phase 2 and so on.
• It is also desirable for projects to support long-term higher education to better support institutional
strengthening, as well-trained staff offer better guarantees of consolidation of investment gains.
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 42 of 46
ANNEX 6. SUPPORTING DOCUMENTS
HT Strengthening Hydro-Met Services PAD 2015
Grant Agreement 2015
Restructuring Paper 2020
ISRs (10)
Mid-Term Review 2018
Aide-Mémoires of Implementation Support and Technical Missions
Government ICR (in French)
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 43 of 46
ANNEX 7. PROJECT IMPLEMENTATION TIMELINE: EXOGENOUS FACTORS
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 44 of 46
ANNEX 8. PROJECT RESULTS FRAMEWORK AND PPCR CORE INDICATORS
Table A8.1: Link Between Hydromet PDO Indicators and Pilot Program for Climate Resilience Core Indicators
Hydromet Indicators PPCR Core Indicators
PPCR Core Indicators #2
(“Evidence of strengthened
government capacity and
coordination mechanism to
mainstream climate resilience”)
PPCR Core Indicators #3
(“Quality and extent to which
climate responsive
instruments/investment models
are developed and tested”)
Core Indicators #4
(“Extent to which vulnerable
households, communities, businesses
and public sector services use improved
PPCR supported tools, instruments,
strategies and activities to respond to
climate variability or climate change”)
PDO indicators
Data collected from hydromet networks are accessible on
a centralized online hydrometeorological data
management platform, with its own operating procedures
for validation and storage
Number of sub-networks feeding into the centralized
platform
End users' satisfaction rate towards improved hydromet
information services of whom percentage women
IRIs
Number of users and instructors trained on the use of the
centralized data platform of whom % women
Hydrological and meteorological stations reporting data
to the platform in line with agreed SOPs
Number of Civil Protection Committees using the
customized application from the centralized data platform
Operational stations
Number of Departmental Agricultural Directions (DDA)
using the customized application from the centralized
data platform
Direct project beneficiaries of whom women
No Link No Link No Link
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 45 of 46
ANNEX 9. PROJECT COMPONENT ACHIEVEMENTS AND LINK TO CREWS
Component 1: Institutional strengthening of hydro-meteorological services and development of data
management tools.
National Hydromet platform: The MARNDR opted to install a simpler software managed by WMO called
Meteorological, Climatological and Hydrological Database Management System (MCH) as the national
hydromet platform (NHP). MCH is a database management system based on open-source database and
software, supported by WMO programs and strategy especially for least developed countries which can
guarantee a certain level of sustainability and low-cost updates.
MCH allows to connect automatic stations and gather real time data offering solutions to digitize, store, process
large amount of data and generate reports and products on large amount of meteorological, climatological and
hydrological data.
The national platform is hosted in a permanent server at the UHM. Standard operating procedures (SOP) have
been developed for operating and maintaining all hydrometeorological data and data collection processes. The
national hydromet platform hosts data from 34 stations from five subnetworks, including the UMH’s network,
the National Center for Geo-Spatial Information (CNIGS) of the Ministry of Planning, Cooperazione
Internazionale (COOPI), and NGO partners’ networks (e.g., Fondation Nouvelle Grand-Anse and CESAL). The
national platform also hosts historical hydrometeorological data (from 1926) from 230 stations of the MARNDR
Water Resources Services’ (SNRE) hydrological network. The national platform will gradually include other
networks managed by different government entities, including the MARNDR, through the Departmental
Agricultural Directions (DDAs). As well, the new equipment acquired by the Hydromet Project will be connected
to the national platform once the new automatic hydromet stations will be installed.
Training on MCH platform has been specifically designed for Haiti based on human competences and observing
networks capacities. Hence, 11 people (IT staff as administrator, climatologists, hydrologists and UHM
coordinator) were trained on the management of the MCH system, capture, consultation, management and
process of meteorological and climatological data and production of specific information for the end-users.
Strengthening of the hydromet network: Based on the results of the Institutional Diagnostic of the Hydromet
Sector, the needs for optimization of hydromet equipment and strengthening of data management tools were
identified. Hydrological monitoring equipment and stations were procured to the UHM. Equipment will be
installed by the end of 2021 with the support of two ongoing Bank-financed projects (RESEPAG II and PGRAC).
Component 2: Identification of hydro-meteorological and climate services’ requirements for select end
users and development of information services to support decision making.
The Institutional Diagnostic of the Hydromet Sector conducted in the first part of the project allowed to assess
and analyze strengths, weaknesses, opportunities, and constraints of the UHM to meet the requirements of
hydromet services of the end users. The UHM identified strategies to strengthen the institution and fulfill its
mandate and meet the requirements of hydromet information of end-users. This diagnostic also contributed
to the development of the UHM National Strategic Plan 2020-2024 achieved under Component 1.
The World Bank
HT Strengthening Hydro-Met Services (P148259)
Page 46 of 46
Additionally, under this component the project planned to analyze the data collected by the hydromet
networks consolidated in the national data platform, in order to develop software interfaces customized to
meet the needs of the Directorate of Civil Protection and the agriculture sector. The project did not fully
complete its objectives but was able to advance in the following areas: scoping the hydromet information
requirements of end-users and development of initial customized hydromet products to be used by the
agriculture sector.
Also, a designated training session was carried out for 85 end users (including 13 women) from the Civil
Protection (CCPCs) and Agricultural Departmental Offices (DDAs) in the interpretation and use of the UHM’s
hydrometeorological products (bulletins).
With the support of the Hydromet project the quality of the existing UHM hydromet products has been
improved. The project has provided equipment such as servers to save and better process the data and carried
out the maintenance of hydromet stations to ensure the quality and regularity of the information.
How CREWS project will capitalize on the hydromet achievements
One of the main activities of the CREWS project is to develop a comprehensive multi-hazards and multi-scales
early warning services (EWS) focused on hydromet risks, meeting the needs of Civil Protection and food security
(and other stakeholders) with regards to the four pillars defined for an efficient EWS: (i) risk assessment and
monitoring; (ii) forecasting and warning services; (iii) dissemination and communication; and (iv) planning and
response capacity.
The hydromet and climate observation networks and the MCH database implemented by the Hydromet
project, accompanied by ad-hoc training, will give the country (through UHM and partners) the basic capacities
to contribute to at least three of the four pillars of CREWs. Indeed, it will help to determine and fine tune risk
information, it will also strengthen capacities for real time monitoring and forecasting and will concur to
develop EWS planning and SOPs while, for example, defining thresholds for warning and associated
procedures.
Thus, the outputs of the Hydromet project will facilitate the operationalization of CREWS activities and will
contribute to achieve the expected results.