Teks Konple Dokiman an
Teks ki soti nan dokiman orijinal la pou endeksasyon.
Document of
The World Bank
Report No: ICR00002483
IMPLEMENTATION COMPLETION AND RESULTS REPORT
(IDA-H4320)
ON A
GRANT
IN THE AMOUNT OF SDR 12.8 MILLION
(US$20.0 MILLION EQUIVALENT)
TO THE
REPUBLIC OF HAITI
FOR A
EMERGENCY BRIDGE RECONSTRUCTION AND VULNERABILITY
REDUCTION PROJECT
November 30, 2015
Transport & ICT
Haiti Country Unit
LATIN AMERICA AND CARIBBEAN
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
CURRENCY EQUIVALENTS
(Exchange Rate Effective November 30, 2015)
Currency Unit = Haitian Gourde
HTG 1.00 = US$0.01808
US$1.00 = HTG 55.3044
FISCAL YEAR
October 1 – September 30
ABBREVIATIONS AND ACRONYMS
AFD French Development Agency (Agence Francaise de Développement)
BMPAD Bureau of Monetization of Development Aid Programs (Bureau de Monétisations et
Programmes d’Aide au Développement)
CARDP Center and Artibonite Regional Development Project (P133352)
CIAT Inter-Ministerial Committee for Territorial Development (Comité Interministériel
d’Aménagement du Territoire)
CRV Vulnerability Reduction Unit (Cellule de Réduction de la Vulnérabilité)
DCRU Disaster Recovery and Coordination Unit
DPC Directorate of Civil Protection (Direction de la Protection Civile)
DRM Disaster Risk Management (Gestion des Risques de Désastres)
DRMRP Disaster Risk Management and Reconstruction Project (P126346)
ERDMP Emergency Recovery and Disaster Management Project (P090159)
FER Road Maintenance Fund (Fond d’Entretien Routier)
FGHI Tropical Storms Fay, Gustav, Hannah, and Hurricane Ike
GoH Government of Haiti
IaDB Inter-American Development Bank
IDA International Development Association
IP Implementation Progress
ISR Implementation Status and Results Report
M&E Monitoring and Evaluation
MICT Ministry of the Interior and Collective Territories (Ministère de L’Intérieur et des
Collectivités Territoriales)
MIS Management Information System
MPCE Ministry of Planning and External Cooperation (Ministère de Planification et Cooperation
Externe)
MTPTC Ministry of Public Works, Transportation, and Communication (Ministère de Travaux
Publics, Transport, Énergie et Communications)
MTR Mid-term Review
NDRMS National Disaster Risk Management System (Système National de Gestion des Risques et
des Désastres)
NGO Non-Governmental Organization
PCU Project Coordination Unit (Unité de Coordination de Projet)
PIU Project Implementation Unit
PDNA Post-Disaster Needs Assessment
PDO Project Development Objective
PPR Risk Management Plans (Plans de Prévention des Risques)
ii
PROReV Emergency Bridge Reconstruction and Vulnerability Reduction Project (Projet de
Reconstruction D’Urgence Des Ouvrages D’Art et de Réduction de la Vulnérabilité)
PRUII Infrastructure and Institutions Emergency Recovery Project (P120895)
PTDT Transport and Territorial Development Project (P095523)
RAI Rural Access Index
SPGRD Permanent Secretariat of Disaster Risk Management (Secretariat permanent de Gestion
des Risques et des Desastres
UCE Central Execution Unit (Unité Central d’Exécution) (PCU of MTPTC)
UCP Project Coordination Unit (Unité Coordination de Projet) (PCU of MEF at BMPAD)
UTSI Statistics and Data Processing Technical Unit (Unite Technique de Statistiques et
d’Informatique)
Regional Vice President: Jorge Familiar Calderon
Special Envoy: Mary Barton-Dock
Practice Manager: Aurelio Menendez
Project Team Leader: Pierre Xavier Bonneau
Co-Project Team Leader Michel Matera
ICR Team Leader: Pierre Xavier Bonneau
ICR Primary Author : Malaika Becoulet
iii
HAITI
Emergency Bridge Reconstruction and Vulnerability Reduction Project
CONTENTS
Data Sheet
A. Basic Information
B. Key Dates
C. Ratings Summary
D. Sector and Theme Codes
E. Bank Staff
F. Results Framework Analysis
G. Ratings of Project Performance in ISRs
H. Restructuring
I. Disbursement Graph
1. Project Context, Development Objectives and Design ............................................... 1
2. Key Factors Affecting Implementation and Outcomes ............................................ 11
3. Assessment of Outcomes .......................................................................................... 18
4. Assessment of Risk to Development Outcome ......................................................... 22
5. Assessment of Bank and Borrower Performance ..................................................... 24
6. Lessons Learned ....................................................................................................... 26
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners .......... 28
Annex 1. Project Costs and Financing .......................................................................... 29
Annex 2. Outputs by Component ................................................................................. 31
Annex 3. Economic and Financial Analysis ................................................................. 38
Annex 4. Bank Lending and Implementation Support/Supervision Processes ............ 39
Annex 5. Summary of Borrower's ICR and/or Comments on Draft ICR ..................... 40
Annex 6. Comments of Cofinanciers and Other Partners/Stakeholders ....................... 44
Annex 7. List of Supporting Documents ...................................................................... 45
iv
ADDITIONAL FINANCING DATA SHEET
Haiti
Emergency Bridge Reconstruction and Vulnerability Reduction Project ( P114292 )
LATIN AMERICA AND CARIBBEAN
GTIDR
A. Basic Information
Country: Haiti Project Name:
HT Emergency Bridge
Reconst & Vulnerab
Reduction Project
Project ID: P114292 L/C/TF Number(s): IDA-H4320
ICR Date: 11/30/2015 ICR Type: Core ICR
Lending Instrument: ERL Borrower:
MINISTRY OF
ECONOMY AND
FINANCE
Original Total
Commitment:
XDR 12.80M Disbursed Amount: XDR 12.77M
Revised Amount: XDR 12.80M
Environmental Category: B
Implementing Agencies:
Unite Centrale d'Execution
BMPAD
UCE
Unite Centrale d'Execution
CIAT
Cofinanciers and Other External Partners:
B. Key Dates
Process Date Process Original Date
Revised / Actual
Date(s)
Concept Review: 10/14/2008 Effectiveness: 03/31/2009 03/31/2009
Appraisal: Restructuring(s):
03/21/2011
05/30/2013
10/10/2014
Approval: 11/18/2008 Mid-term Review:
Closing: 06/30/2013 05/31/2015
C. Ratings Summary
C.1 Performance Rating by ICR
Outcomes: Moderately Satisfactory
v
Risk to Development Outcome: Substantial
Bank Performance: Satisfactory
Borrower Performance: Moderately Satisfactory
C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)
Bank Ratings Borrower Ratings
Quality at Entry: Satisfactory Government: Satisfactory
Quality of Supervision: Satisfactory
Implementing
Agency/Agencies:
Moderately Satisfactory
Overall Bank
Performance:
Satisfactory
Overall Borrower
Performance:
Moderately Satisfactory
C.3 Quality at Entry and Implementation Performance Indicators
Implementation
Performance
Indicators
QAG Assessments
(if any)
Rating
Potential Problem
Project at any time
(Yes/No):
Yes
Quality at Entry
(QEA):
None
Problem Project at any
time (Yes/No):
Yes
Quality of
Supervision (QSA):
None
DO rating before
Closing/Inactive status:
Moderately
Satisfactory
D. Sector and Theme Codes
Original Actual
Sector Code (as % of total Bank financing)
Public administration- Transportation 13 13
Public administration- Water, sanitation and flood
protection
25 25
Rural and Inter-Urban Roads and Highways 62 62
Theme Code (as % of total Bank financing)
Administrative and civil service reform 31 31
Natural disaster management 50 50
Participation and civic engagement 1 1
Rural services and infrastructure 18 18
E. Bank Staff
Positions At ICR At Approval
Vice President: Jorge Familiar Calderon Pamela Cox
vi
Country Director: Mary A. Barton-Dock Yvonne M. Tsikata
Practice
Manager/Manager:
Aurelio Menendez Jose Luis Irigoyen
Project Team Leader: Pierre Xavier Bonneau Nicolas Peltier-Thiberge
ICR Team Leader: Pierre Xavier Bonneau
ICR Primary Author: Malaika Becoulet
F. Results Framework Analysis
Project Development Objectives (from Project Appraisal Document)
The project's development objective in the Financing Agreement is to (i) assist the Recipient in
restoring access on selected critical points of its transport system following the FGHI Emergency,
and (ii) reduce vulnerability to national disasters by strengthening its NDRMS.
The PDO in the PAD is to (i) restore access on selected critical points of the Haitian transportation
system and (ii) support vulnerability reduction by strengthening the Haitian National Disaster Risk
Management System.
The PDO used for this ICR evaluation is that in the Financing Agreement. The differences are
editorial.
Note: The dates of the original and revised target values represent the date when they were approved
(as part of the PAD or the restructuring paper). In all cases, the targets were expected to be met by
the final closing date.
Revised Project Development Objectives (as approved by original approving authority)
(a) PDO Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised
Target
Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 1 :
Disaster Risk Management Units within key ministries are operational and
sustainable, with adequate instruments/tools and staffing before the end of the
project.
Value
quantitative or
Qualitative)
No. Yes. 2 2
Date achieved 11/18/2008 11/19/2008 05/30/2013 05/31/2015
Comments
(incl. %
achievement)
Revised 2013 Restructuring. Achieved. CIAT (an inter-ministerial committee of
6 ministries & MTPTC each established a DRM CRV unit, staffed and equipped
with resources and tools. Both are presently operational & sustainable.
Indicator 2 :
MTPTC bridge management unit is operational and sustainable, with adequate
resources and staffing.
Value
quantitative or
Qualitative)
No. Yes Yes.
vii
Date achieved 11/18/2008 11/19/2008 05/31/2015
Comments
(incl. %
achievement)
Achieved. Bridge Management Unit is operational: 12 engineers trained and 2
unit staffed based at MTPTC. From April 2011 to present, the Unit has cataloged
3455 hydraulic crossings, including 174 bridges which have been evaluated for
further maintenance.
Indicator 3 : MPCE vulnerability reduction unit is operational and sustainable.
Value
quantitative or
Qualitative)
No. Yes. Dropped. See Indicator #1
Date achieved 11/18/2008 11/19/2008 05/30/2013 05/31/2015
Comments
(incl. %
achievement)
Dropped Restructuring 2013: CRV in MPCE discontinued in Nov. 2011 due to
changes in national institutional framework. CRV staff & responsibilities for
integration of DRM in sectoral policies transferred to CIAT and is operational
(see Ind. #3 & Table 1).
Indicator 4 :
National Disaster Risk Management System (NDRMS) Policy and framework
assessed and strengthened before the end of 2013.
Value
quantitative or
Qualitative)
No. Yes. Dropped See below.
Date achieved 11/18/2008 11/19/2008 05/30/2013 05/31/2015
Comments
(incl. %
achievement)
The original indicator "SPGRD unit reinforced, operational and sustainable"
expanded to above (2011); then dropped (2013). NDRMS & SPGRD were
reinforced & improved, but the 2010 earthquake emergency was not a conducive
environment for policy reform.
Indicator 5 : Roads rehabilitated (km), non-rural roads
Value
quantitative or
Qualitative)
No. 200 200
Date achieved 05/30/2013 05/31/2013 05/31/2015
Comments
(incl. %
achievement)
New Restructuring 2013. 100% achieved. This result was achieved by
contracting local SMEs, thereby promoting the growth and development of small
and medium civil work enterprises.
(b) Intermediate Outcome Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised
Target Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 1 :
Number of emergency fords and overpasses built in the two months following
the emergency.
Value
(quantitative
or Qualitative)
1 4 3 3
Date achieved 11/18/2008 11/19/2008 05/30/2013 05/31/2015
Comments
(incl. %
achievement)
100% achieved. Target reduced due to financing from other sources for bridge 4.
By Dec 2008 three overpasses were operational on two major roads connecting
the northern and southern parts of the country.
viii
Indicator 2 : Number of bridges rebuilt with satisfactory technical standards.
Value
(quantitative
or Qualitative)
0 2 1 1
Date achieved 11/18/2008 11/19/2008 05/30/2013 05/31/2015
Comments
(incl. %
achievement)
100% achieved. Cost overruns led to reduction in target from 2 to 1. But,
engineering studies financed by PROReV were used by USAID and GOH to
build the remaining bridge (Chalon) with Bank Financing under another project
(DRMRP - P126346).
Indicator 3 : 10 emergency bridges purchased
Value
(quantitative
or Qualitative)
No. Yes. Yes.
Date achieved 05/30/2013 05/31/2013 05/31/2015
Comments
(incl. %
achievement)
100% Achieved. Staff of MTPTC were trained on the installation of emergency
bridges. 7 of the 10 emergency bridges purchased were used during the project
life to restore access on roads made inaccessible following adverse natural
events incl TS Sandy
Indicator 4 :
Number of bridges and road sections that have been repaired or consolidated
with satisfactory technical standards
Value
(quantitative
or Qualitative)
0 20 11 20
Date achieved 11/18/2008 11/19/2008 10/08/2014 05/31/2015
Comments
(incl. %
achievement)
154% Achieved. Initial target of 20 revised in 2011 Restructuring to 8(2013)
then 11(2014) in light of the necessary cost reallocation at the time. Unexpected
cost savings during project execution allowed for the increase in the # of spot
interventions.
Indicator 5 :
Number of community-based initiatives performing routine maintenance with
satisfactory technical standards
Value
(quantitative
or Qualitative)
0 20 Dropped.
20 (financed by
GoH)
Date achieved 11/18/2008 11/19/2008 05/30/2013 05/31/2015
Comments
(incl. %
achievement)
Dropped Restructuring 2013. Sub-component linked to this indicator was
dropped. Activity financed by GoH through FER.
Indicator 6 : Bridge inventory completed and up to date
Value
(quantitative
or Qualitative)
No. Yes. Yes.
Date achieved 11/18/2008 11/19/2008 05/31/2015
Comments
(incl. %
achievement)
100% Achieved. Inventory of existing bridges complete and is up to date. From
April 2011 to date, Bridge Management Unit at MTPTC conducted a first time
inventory and cataloged 3455 hydraulic crossings incl. 174 bridges which have
since been evaluated
Indicator 7 :
Constitution of an effective crisis management and vulnerability reduction unit
in MTPTC
ix
Value
(quantitative
or Qualitative)
No. Yes. Yes.
Date achieved 11/18/2008 11/19/2008 05/31/2015
Comments
(incl. %
achievement)
100% Achieved. Crisis Management and Vulnerability Reduction Unit (DRM
unit) was established, staffed and equipped with trained engineers (see PDO
Indicator #1). Operational manual (included M&E tools) was also developed.
Unit was integrated into NDRMS.
Indicator 8 : Constitution of a bridge management unit in MTPTC
Value
(quantitative
or Qualitative)
No. Yes. Yes.
Date achieved 11/18/2008 11/19/2008 05/31/2015
Comments
(incl. %
achievement)
100% Achieved. Bridge Management Unit was established, and the Road
Maintenance Division was staffed with training engineers. Unit has completed
the country's first comprehensive national bridge inventory.
Indicator 9 :
Vulnerability Reduction Unit established within MPCE and a National
Framework for Vulnerability Reduction created, in place before the end of 2012
and integrated into sectoral policies and programs before the end of 2013.
Value
(quantitative
or Qualitative)
No. Yes. Dropped.
See PDO indicator
#1
Date achieved 11/18/2008 11/19/2008 05/30/2013 05/31/2015
Comments
(incl. %
achievement)
Original indicator "est. of CRV Unit" revised to above (2011), dropped in 2013.
Unit & staff transferred from MPCE to CIAT. NDRMS Reform abandoned by
GoH due to other priorities post-earthquake. Policy dialogue recommenced in
2012, financed by DRMRP.
Indicator 10 :
Timely presentation of Disaster Recovery and Reconstruction Program(s) are
submitted and coordinated every semester and yearly by all stakeholders from
second semester of 2011.
Value
(quantitative
or Qualitative)
No. Yes. Dropped.
Achieved until
practice
discontinued 2013.
Date achieved 11/18/2008 11/19/2008 05/30/2013 05/31/2015
Comments
(incl. %
achievement)
Dropped Restructuring 2014. Dedicated PM's office installed after 2010
Earthquake was discontinued and presentations no longer held.
Indicator 11 :
A Multi-sectoral Vulnerability Reduction Unit (EM-VRU) created and
operational within CIAT before the end of the project.
Value
(quantitative
or Qualitative)
0 4 Yes/No Yes
Date achieved 11/18/2008 11/19/2008 10/10/2014 05/31/2015
Comments
(incl. %
achievement)
Revised Restructuring 2014. 100% Achieved: CRV (French for EM-VRU) was
created and is presently operational within CIAT. This CRV was transferred
from MPCE.
x
Indicator 12 :
Transversal development strategies developed by CIAT (i.e.: watershed
management, urban planning, territorial development and land tenure, Risk
Prevention Plans) established and in place before end of project.
Value
(quantitative
or Qualitative)
0 Yes. 6 6
Date achieved 11/18/2008 11/19/2008 10/10/2014 05/31/2015
Comments
(incl. %
achievement)
Revised Restructuring 2014 (mentions only CIAT because includes the CRV).
100% Achieved. Transversal development strategies & instruments were
developed by CIAT incl. key strategic documents regarding risk, watershed
management & urban plans.
Indicator 13 :
Disaster risk management principles integrated and assessed into these
transversal strategies
Value
(quantitative
or Qualitative)
No. Yes. Dropped. See Indicator #12
Date achieved 11/18/2008 11/19/2008 05/30/2013 05/31/2015
Comments
(incl. %
achievement)
Revised (2011) by including "assessed", and then dropped (2013). However the
target was achieved. Instruments to integrate DRM in territorial planning were
developed under Indicator #12.
G. Ratings of Project Performance in ISRs
No.
Date ISR
Archived
DO IP
Actual
Disbursements
(USD millions)
1 12/01/2008 Satisfactory Satisfactory 0.00
2 04/07/2009 Satisfactory Satisfactory 0.00
3 07/29/2009 Satisfactory Satisfactory 2.00
4 09/02/2009 Satisfactory Satisfactory 2.00
5 05/12/2010 Satisfactory Satisfactory 3.40
6 02/22/2011 Moderately Satisfactory Moderately Satisfactory 6.84
7 11/02/2011 Moderately Satisfactory Moderately Satisfactory 8.55
8 06/27/2012 Moderately Satisfactory Moderately Satisfactory 10.65
9 02/24/2013 Moderately Satisfactory Moderately Satisfactory 11.78
10 12/01/2013 Moderately Satisfactory
Moderately
Unsatisfactory
12.66
11 02/24/2014 Moderately Satisfactory
Moderately
Unsatisfactory
14.27
12 09/01/2014 Moderately Satisfactory Moderately Satisfactory 15.92
13 03/12/2015 Moderately Satisfactory Moderately Satisfactory 18.73
14 06/01/2015 Moderately Satisfactory Moderately Satisfactory 19.11
H. Restructuring (if any)
xi
Restructuring
Date(s)
Board
Approved
PDO Change
ISR Ratings at
Restructuring
Amount
Disbursed at
Restructuring
in USD
millions
Reason for Restructuring &
Key Changes Made
DO IP
03/21/2011 N MS MS 7.05
The first Restructuring (2011
Restructuring) occurred
following the January 12, 2010
Earthquake, when the GoH
requested a restructuring to: (i)
reallocate unallocated funds
from Category 6 to Category 2
to cover cost overruns in
Component 2; and (ii) change
outputs associated with
Component 4, specifically
renaming and expanding the
role of the Vulnerability
Reduction Unit, and introducing
changes to the Technical
Assistance activities. The
Restructuring was approved by
the Special Envoy on March 21,
2011.
05/30/2013 N MS MS 11.78
The second Restructuring (2013
Restructuring), approved on
May 30, 2013, was at the
request of the GoH to: (i)
extend the closing date by 21
months, from June 30, 2013 to
March 31, 2015, to allow for
completion of the construction
of the bridge Le Theme in
Mirebalais under Component 1;
(ii) account for changes to
outputs associated with
Component 1 and Component
2, as a result of compounded
urgent and emergency response
activities following adverse
natural events; (iii) reallocate
funds from Category 2 and
Category 3 to Category 1; (iv)
facilitate changes to the
Technical Assistance (TA)
activities under Component 4 to
reflect the changes in the
institutional framework for
vulnerability reduction in Haiti;
and (v) slight modifications to
xii
Restructuring
Date(s)
Board
Approved
PDO Change
ISR Ratings at
Restructuring
Amount
Disbursed at
Restructuring
in USD
millions
Reason for Restructuring &
Key Changes Made
DO IP
the intermediate indicators to
monitor the results expected
from the modified activities.
10/10/2014 N MS MS 16.11
The third Restructuring (2014
Restructuring), approved on
October 10, 2014, involved
several changes, including: (i)
extension of the closing date by
2 months, from March 31, 2015
to May 31, 2015 to allow for
completion of the Rural Access
Index (RAI) study under
Component 3, and the risk
assessment studies and
associated Risk Management
Plans (PPRs) for the cities of
Cap-Haitien and Les Cayes
under Component 4; (ii)
reallocation of funds from
Category 4 to Categories 1, 2
and 3 to accommodate cost
overruns; and (iii) changes to
the Project Results Framework
and Monitoring, which include
minor revisions to target values
for related intermediated
indicators to monitor the results
expected from the modified
activities.
xiii
I. Disbursement Profile
xiv
1. Project Context, Development Objectives and Design
1.1 Context at Appraisal
(a) Country and Sector Background
1. Country Context. At the time of project approval, in November 2008, Haiti had
struggled for several decades to emerge from a cycle of political instability and internal
conflicts that devastated its economy and weakened state institutions, worsened by poor
governance practices which maintained or deepened poverty. In 2004, Haiti was
devastated by Hurricane Jeanne, which caused some US$169.5 million in damages, and
took more than 4,000 lives. Tropical Storm No el, which struck Haiti in October 2007,
caused flash floods and mudslides in the Western part of the country, resulting in 66 deaths
and almost 15,000 lost homes. In March 2008, rising world prices for food and oil triggered
violent protests, leading the Senate to vote then Prime Minister Jacques-Edouard Alexis
out of office on April 12, 2008. Finally, after a period of political instability during which
the country did not have a confirmed Government, the 2008 hurricane season was
particularly severe, with the passage of three major tropical storms and one hurricane (Fay,
Gustav, Hanna and Ike - FGHI) over a four-week period. The combined toll of these storms
was some 793 killed, and 301 injured, with 1 million people affected. The result was a
collapse of the already weak national transport system—several main roads and bridges
were heavily damaged, stifling the passage of goods and services and cutting off entire
regions from others—and major crop destruction, crippling food production. All of this
was exacerbated by the 2010 earthquake which occurred two years into project
implementation and which caused unprecedented damage, by far the worst natural disaster
to strike Haiti in recent history.
2. DRM Sector. The FGHI emergency revealed important shortfalls in Haiti's
infrastructure policies and National Disaster Risk Management System (NDRMS).
Critical issues identified included: (i) a lack of an integrated approach to disaster prevention
(including poor urban planning, inefficient water management and significant erosion
caused by environmental deterioration) ; (ii) inadequate technical standards for
infrastructure construction; (iii) lack of infrastructure maintenance; and (iv) lack of
technical capacity and institutional structures to properly address crisis management and
reconstruction. The crisis particularly highlighted the importance of road and bridge
maintenance and resilient designs, since those roads and bridges that had been properly
maintained were less affected.
3. Transport Sector. The transport sector represented a major bottleneck to Haiti’s
social and economic development. With about 90 percent of the country’s overall traffic
by land, Haiti has a limited road network of about 3,400 km, including 700 km of national
roads, 1,500 km of departmental roads, and 1,200 km of tertiary roads. This road network
suffered heavily from lack of maintenance, and from the impacts of climate change and
variability, and entire regions remained isolated during the rainy season. At Project
appraisal, damage to the transport sector was particularly severe, with several regions in
the country completely isolated, and the economy in province’s departments almost
1
completely paralyzed. The Artibonite region faced catastrophic circumstances with major
flooding in Gonaives, and access from both the north and south compromised due to the
collapse of four major bridges (Montrouis, Ennery , Chalon and Mirebalais). Numerous
smaller bridges and road sections were also either destroyed or damaged.
(b) Rationale for Bank involvement.
4. The Bank and the Government of Haiti (GoH) have established an effective
partnership since the reengagement of the international community in Haiti in 2004, with
the Bank playing a prominent role in financing Disaster Risk Management and Transport
programs. The Bank had a longstanding experience in supporting the transport sector
nationwide, first engaging in 1955, and followed by seven investments and t echnical
assistance operations, with a particular focus since 2004 on strengthening the road
maintenance country system to improve resilience and protection of assets with the
Transport and Territorial Development Project – P095523) and the Disaster Risk
Management (DRM) sector with the E mergency Response Disaster Management Project
(P090150) approved in 2005, both of which were still under implementation at this
Project’s appraisal.
5. A World Bank technical assistance team was also deployed in the immediate
aftermath of Tropical Storm Gustav (second storm) to: (i) assist MTPTC in dealing with
the emergency operations; (ii) provide technical guidance on immediate repair and designs
to restore minimal connectivity; and (iii) identify medium and long term needs.
6. The GoH officially requested financial and technical assistance from the Bank to
support its P ost-Disaster Needs Assessment (PDNA) and the recovery and reconstruction
program to be created in the aftermath of FGHI. The Bank-hosted Global Facility for
Disaster Reduction and Recovery co-led a PDNA and evaluated the total damage of FGHI
at $897 million, or the equivalent of 14.6% of the GDP within weeks of the passing of
Hurricane. In terms of economic impact, prior to the 2010 earthquake, FGHI was the
largest disaster in Haiti’s recent history.
7. Interim Strategy Note (ISN). PROReV was fully aligned and consistent with
the Interim Strategy Note. Economic recovery was a central axis of the 2006 Haiti ISN,
which included the transport sector and the management of natural disasters and risks as
key components. The GoH further recognized the strategic importance of an improved
transport sector and disaster risk by featuring both as key elements of their Poverty
Reduction Strategy Paper in November 2007.
1.2 Original Project Development Objectives (PDO) and Key Indicators
8. The original Project Development Objective as described in the Financing
Agreement was to: (i) assist the Recipient in restoring access on selected critical points of
2
its transport system following the FGHI Emergency; and (ii) reduce vulnerability to
national disasters by strengthening its NDRMS.
1
9. The key original project performance indicators retained, as per the PAD Results
Framework, were:
• Disaster risk management units within key ministries are operational and
sustainable, with adequate resources and staffing;
• Ministry of Public Works, Transportation and Communication (MTPTC) bridge
management unit is operational and sustainable, with adequate resources and
staffing;
• Ministry of Planning and External Cooperation (MPCE) recovery and
reconstruction planning unit is operational and sustainable with adequate
resources and staffing (as MPCE was responsible for vulnerability reduction
activities)
• Permanent Secretariat of Disaster Risk Management (SPGRD) unit is reinforced,
operation and sustainable.(as part of the NDRMS)
1.3 Revised PDO (as approved by original approving authority) and Key Indicators,
and reasons/justification
10. The PDO definition remained unchanged during p roject implementation.
11. These changes occurred in response to the 2010 earthquake and its aftermath, the
most severe disaster that Haiti has experienced in recent years. The 2010 earthquake killed
an estimated 220,000 people, displaced over 1.5 million people, and destroyed or damaged,
150,000 buildings. The buildings of several key-line ministries collapsed outright,
including Ministry of Economy and Finance (MEF), MTPTC, and MPCE. These revisions
were necessary to adapt the project to the emergency context and changing government
priorities in the wake of the crisis, but continued to fulfill the development objective of the
project, and ultimate outcomes.
1
The PDO in the PAD is to (i) restore access on selected critical points of the Haitian transportation system
and (ii) support vulnerability reduction by strengthening the Haitian National Disaster Risk Management
System. The PDO used for this ICR evaluation is that in the Financing Agreement. The differences with the
Financing Agreement formulation are editorial.
3
Table 1: Revisions to PDO Level Indicators
PDO Level Indicators
Original Indicators Revised Indicators Comments
2011 Restructuring 2013 Restructuring 2014
Restructuring
Indicator 1. Disaster Risk
Management Units within key
ministries are operational and
sustainable, with adequate
resources and staffing.
Revised. Disaster Risk Management
Units within key ministries are
operational and sustainable, with
adequate instruments/tools and staffing
before the end of 2013.
(Change Process: Country Director
Approval – 2011 Level 2 Restructuring)
Revised. Disaster Risk Management
Units within key ministries are
operational and sustainable, with
adequate instruments/tools and
staffing before the end of the project.
(Change Process: Country Director
Approval – 2013 Level 2 Restructuring)
No change. Target and scope of
indicator did not
change. The changes
merely align the end
date of the t arget of the
indicator with the
extended closing date.
Indicator 2. MTPTC bridge
management unit is operational
and sustainable, with adequate
resources and staffing.
No change. No change. No change.
Indicator 3. MPCE
vulnerability reduction unit is operational and sustainable.
No change. Dropped. This unit was transferred to
the Inter-Ministerial Committee for
Territorial Development ( CIAT)
attached to the Prime Minister’s office
serving as the coordinating body of
the 6 key- line ministries (including the
MPCE and MTPTC) on territorial
planning and development and
vulnerability reduction, among other
things.
(Change Process: Country Director
Approval – 2013 Level 2 Restructuring)
N/A This indicator was
dropped since this unit
was transferred to
CIAT. The objective
was to be achieved
through CIAT, the
central coordinating
body, rather than
through a single
Ministry, MPCE.
Indicator 4. Permanent
Secretariat of Disaster Risk
Management (SPGRD) unit is
reinforced, operational and
sustainable.
Revised. National Disaster Risk
Management System (NDRMS) Policy
and framework assessed and
strengthened before the end of 2013.
SPGRD is one piece of the broader NDRMS. The indicator was revised
following the 2010 Earthquake to
Dropped. This indicator was dropped
when it became apparent during the
transition from the emergency
response phase to the recovery and
reconstruction phase post-earthquake
that the assessment and proposed
reforms would not be possible during
the lifetime of the project, mostly due
N/A
4
reflect the modification of activities to
strengthen weaknesses in the broader
system, not simply reinforce the
Permanent Secretariat.
(Change Process: Country Director
Approval – 2011 Level 2 Restructuring)
to shifted government priorities and
capacities.
(Change Process: Country Director
Approval – 2013 Level 2 Restructuring)
Indicator 3. (New) Roads
rehabilitated (km), non-rural
roads
N/A New. This indicator was added as a
core indicator to capture the number
of kilometers of roads rehabilitated
under the project.
(Change Process: Country Director
Approval – 2013 Level 2 Restructuring)
No change.
5
1.4 Main Beneficiaries
12. In response to the 2007 and 2008 hurricane seasons, project resources were
channeled to repair and reinforce selected infrastructure that were identified as key to
ensuring the continuity of the national road network and restore connectivity to the isolated
departments. Intended beneficiaries included the population living close to targeted areas
of intervention financed under the project. These interventions were meant to enable the
local population to preserve their livelihood base, including acces s to markets and to basic
social services.
13. The beneficiaries are divided into four categories:
• The population of the isolated departments (South, Grande Anse, Center, and
Artibonite) following the impact of FGHI;
• The riverside populations of targeted interventions of the activities, for example,
Mirebalais, Solon, Cavaillon, etc;
• The national population in general, through the strengthening of institutions in
charge of risk management and resilience MTPTC , MPCE, Inter-Ministerial
Committee for Territorial Planning (CIAT – Comité Interministériel
d’Aménagement du Territoire) under the Primature (Prime Minister’s Office),
Vulnerability Reduction Unit (CRV), SPGRD as part of the NDRMS;
• Government’s officials and public servants from MTPTC, MPCE, N DRMS, and
CIAT, benefitting from the technical assistance and capacity strengthening
activities financed by the project.
1.5 Original Components
14. The PDO was expected to be met through the four components described below
in Table 2.
1.6 Revised Components
15. All four project components were revised as a result of the three restructurings,
presented below in Table 2.
6
Table 2: Original and R evised Components
Original Project 2011 Restructuring 2013 Restructuring 2014 Restructuring
Component 1: Reconstructing Select
Bridges to Restore Access (US$7.2
million): This component retroactively
financed emergency works performed by
MTPTC to restore basic access in areas
where major bridges had collapsed (sub-
component 1.1). The component also sought
to rebuild two of the four damaged main
bridges (Mirebalais and Chalon), help the
MTPTC acquire a stock of emergency
bridges in preparation for future disasters and
provide targeted assistance to bridge
reconstruction works financed by other
donors (sub- component 1.2).
No change. Revised. Component 1: Implementing a
Program of Bridge Reconstruction (US$7.9
million): The costs for Component 1 were higher
than anticipated due to costs associated with the
rehabilitation of the La Theme bridge. As a result
of other cost overruns for several activities under
Component 1 due to compounded emergency
response activities following the Earthquake
(2010), Hurricane Tomas (2010), and Hurricane
Sandy (2012), several activities were dropped
from the project. These activities included: (i)
construction of Chalon Bridge; (ii) repairs of
Estimé Dumarsais Bridge; and (iii) rehabilitation
of the Roseaux and Voldrogue Bridges.
2
The title
of the Component was also revised to reflect
reconstruction during the post-earthquake
recovery and reconstruction phase.
Revised. Component 1:
Implementing a Program of
Bridge Reconstruction
(US$8.03 million): Financing
released under Category 4
(Component 4) was reallocated
to Component 1 to cover
continued cost overruns due to
the rehabilitation of La Theme
bridge.
Component 2. Improving the Resilience of
Transport Infrastructure (US$4.9
million): This component financed several
repair and consolidation works on damaged
or weakened bridges and road sections.
Before appraisal, an indicative list of works
was prepared by MTPTC, with the assistance
of a Bank mission that visited Haiti
immediately after the FGHI storms. This
component aimed to also finance
community-based routine maintenance
Component 2. Improving the
Resilience of Transport
Infrastructure (US$5.35 million):
Reallocation of unallocated funds
from Category 6 to Category 2
(Component 2). No change to
activities.
Component 2. Improving the Resilience of
Transport Infrastructure (US$4.64 million):
This restructuring involved a reallocation of funds
from Category 2 (Component 2) to Category 1
(Component 1) to finance cost overruns under Component 1. Financing under Component 2 was
released as a result of the dropping of Sub-
component 2.2 – Commun
ity Based Routine
Maintenance Activities. These activities were
directly undertaken by the Fond d’Entretien
Routier (FER), the maintenance unit within
Component 2. Improving the
Resilience of Transport
Infrastructure (US$4.64
million): Financing released
under Category 4 (Component
4) was reallocated to
Component 2 and financed 2
additional spot repairs.
2
These construction, repair and rehabilitation activities were transferred to and financed by the Disaster Risk Management and Reconstruction P roject
(P126346), and have since been completed.
7
activities, which sought to improve the
resilience of selected infrastructure damaged
by FGHI, and contribute to improved
management of bridge assets.
MTPTC with its own resources, and as such, these
funds were re-allocated to cover cost overruns
under Component 1.
3
Component 3: Improving Transport
Asset Management ((US$2,585,000). This
component financed a number of capacity
building activities aiming to develop good
practices in bridge asset management,
hydraulic monitoring and strengthening the institutional capacity of the MTPTC and its
regio
nal offices, including: (i) the
development of a comprehensive bridge
inventory; (ii) the development of a crisis
management unit in MTPTC; (iii) the
development of a bridge asset management
unit in MTPTC, in charge in particular of
managing the bridge inventory and of
piloting a hydraulic monitoring program; (iv)
launching of a Young Engineers Program in
MTPTC; (v) travel and subsistence costs for
MTPTC civil servants incurred as part of
emergency response or asset management
activities; (vi) development of a strong and
dedicated implementation team in UCE and
MTPTC; and (vii) financing of safeguards-
related studies, as well as project audits.
No change. Revised. Component 3: Strengthening
Transport System Asset Management
(US$2,556,000). This component was renamed to
reflect that project activities were strengthening,
rather than merely “improving” transport asset management. This restructuring also involved a reallocation of funds from Category 3 (Component
3) to Category 1 (Component 1)
to cover cost
overruns under Component 1 due to the
rehabilitation of La Theme bridge. However, the
restructuring also added technical assistance for
the establishment of a GIS unit, and associated
training, within the MTPTC. The administration,
supervision, and M&E activities, as well as
capacity building and technical assistance under
Component 3 were lower than both the original
and revised estimates, despite that fact that the
volume of activities following the project
restructurings increased.
Component 3: Strengthening
Transport System Asset Management (US$2,910,000).
Financing released under
Category 4 (Component 4) was
reallocated to Component 3
and financed the elaboration of
the Rural Access Index (RAI).
Component 4: Support Vulnerability
Reduction by Strengthening Haiti’s
NDRMS (US$4,900,000). This component
sought to finance a comprehensive technical
assistance package to support the creation of
Revised. Strengthening Haiti’s
National Disaster Risk
Management System (NDRMS)
(US$4,900,000). This component
was renamed to reflect the change in
Revised. Strengthening Haiti’s National
Disaster Risk Management System (NDRMS)
(US$4,900,000). Revised to support CIAT’s key
functions/thematic working groups: land-use
planning, water and risk management, habitat and
Revised. Strengthening
Haiti’s National Disaster Risk
Management System
(NDRMS) (US$3,615,000).
Revised to release unused
3
The activities were completed by FER.
8
a post-disaster recovery and coordination
unit within the MPCE and provide technical
assistance to strengthen the vulnerability
reduction capacities of the NDRMS per the
recommendations of the PDNA (sub-
component 4.1 & 4.2). Coordination
arrangements included MTPTC, particularly
with regard to the implementation of the
proposed project (components 1, 2 and 3),
but also other ministries and relevant
institutions. This component also sought to
pilot a more integrated approach to disaster
prevention through strategic studies to be
performed in selected areas particularly
vulnerable to natural disasters such as
Gonaives or Etang Saumatre-Lac Azuei
(sub-component 4.3).
the approach to the NDRMS
following the 2010 earthquake.
CIAT did not exist at project
preparation, as it was only
established in March 2009 to serve
as an inter-ministerial committee
comprised of six key-line ministries
working in conjunction to influence
development and territorial
planning. Under this Restructuring,
the GoH requested support for the
provision of technical assistance to
CIAT in lieu MPCE given its place
in the Premature and coordinating
role. BMPAD-UCP remained the
fiduciary unit for this Component,
not affecting the implementation
arrangements
urban development, and mapping/IT. BMPAD-
UCP remained the fiduciary unit.
funding to Categories 1, 2 and 3
(Components 1, 2, and 3). CIAT
continued to be responsible for
the preparation of the risk
assessment studies and
associated risk management
plans (PPRs) for the cities of
Cap-Haitien and Les Cayes.
BMPAD-UCP remained the
fiduciary unit.
Sub-component 4.1: Creation of a disaster
recovery and reconstruction coordination unit with the MPCE (US$1,180,000)
Revised. (US$1,685,000) to expand
the role of the Disaster Recovery and
Coordination Unit (DRCU) to cover
the establishment of the National
Framework for Vulnerability
Reduction, and the design,
preparation and integration of
vulnerability reduction policies and
tools into sectoral programs for key
line ministries. This also included
the renaming of the DRCU to the
Vulnerability Reduction Unit
(CRV).
Dropped. Financing for the CRV within MPCE
was discontinued as of November 2011 due to
changes in the national institutional framework for vulnerability reduction.
The CRV, and all its
capacities, were subsequently transferred to CIAT.
N/A.
Sub-component 4.2: Institutional support
program to the NDRMS (US$2,220,000)
Revised. (US$1,305,000).
Financing was transferred to expand the role of the CRV, and provision of
technical assistance to CIAT.
Revised. Sub-component 4.1: Provision of
Technical Advisory Services to NDRMS
(US$3,017,000) Activities under this sub-
component were reprioritized to focus on: (i)
Technical Assistance to assess the current status of
risk assessment in the country, to develop a
Sub-component 4.1: Provision
of Technical Advisory Services
to NDRMS (US$1,015,000).
Unused financing transferred to
sub-component 4.2
9
methodology for the preparation of Plans de
Prévention des Risques ( PPR – Risk Management
Plans) and to support the development of an
appropriate institutional and regulatory framework
for the integration of disaster risk management
into territorial planning; (ii) Technical Assistance
for the preparation and validation of two risk
assessment studies and associated PPRs for the
cities of Cap-Haitien and Les Cayes; and (iii)
Technical Assistance for the finalization and
dissemination of a National Multi-hazard Atlas.
These activities were to be implemented under the leadership CIAT in close consultation with other
stakeholders of the NDRMS, including SPGRD.
Sub-component 4.3: Integrated approaches
to disaster prevention (US$1,500,000)
Revised. Sub-component 4.3:
Integrated approaches to disaster
prevention (US$1,910,000) This
sub-component consisted of the
piloting of two watershed
vulnerability reduction studies
which were eliminated in favor of
financing the provision of technical
assistance and training to the
thematic working groups of the
CIAT, as per the request of the Prime
Minister’s Office.
Revised. Sub-component 4.2 – Technical
Assistance to Inter-Ministerial Committee for
Land-Use Planning (CIAT) (US$1,910,000):
Support to CIAT was extended throughout the
project extension period to target key
functions/thematic working groups of CIAT:
Land-use planning, Water and Risk Management,
Habitat and Urban Development, and Mapping/
IT.
Revised. Sub-component 4.2 –
Technical Assistance to Inter-
Ministerial Committee for
Land-Use Planning (CIAT)
(US$2,610,000): Financing
was transferred from sub-
component 4.1 to continue the
activities of CIAT.
10
1.7 Other significant changes
16. The Project was revised following the 2010 Earthquake to reflect the
modifications of activities and allow for more emergency works. T he Project underwent
three Level Two Restructurings. The first Restructuring (2011 Restructuring) occurred
following the January 12, 2010 Earthquake, when the GoH requested a restructuring to
reallocate unallocated funds from Category 6 to Category 2 to cover cost overruns in
Component 2 (see Table 4 in Annex 1) in addition to revisions in Component 4 (see Section
1.6). The level II Restructuring was approved by the Special Envoy on March 21, 2011.
17. The second Restructuring (2013 Restructuring), approved on May 30, 2013, was
at the request of the GoH to: (i) extend the closing date by 21 months, from June 30, 2013
to March 31, 2015, to allow for completion of the construction of the bridge Le Theme in
Mirebalais under Component 1 and(ii) reallocate funds from Category 2 and Category 3 to
Category 1 (see Section 1.6 and Table 4 in Annex 1) in addition to the changes described
in Sections 1.3 and 1.6.
18. The third Restructuring (2014 Restructuring), approved on October 10, 2014,
involved several changes, including: (i) extension of the closing date by 2 months, from
March 31, 2015 to May 31, 2015 to allow for completion of the Rural Access Index (RAI)
study under Component 3, and the risk assessment studies and associated Risk
Management Plans (PPRs) for the cities of Cap-Haitien and Les Cayes under Component
4; and (ii) reallocation of funds from Category 4 to Categories 1, 2 and 3 to accommodate
cost overruns.
Results Framework
19. The Results framework was adjusted throughout the lifetime of the project to
accommodate successive shocks in the country context and substantial institutional
changes. The rationale and changes of the three restructurings are reflected in Table 6 in
Annex 2.
2. Key Factors Affecting Implementation and Outcomes
2.1 Project Preparation, Design and Quality at Entry
20. Assessment of Project Design. The PDO was relevant and consistent with the
2006 Interim Strategic Note (ISN 2006) and was fully aligned with the needs of the post
FGHI storms context. Considering the emergency context and the PDO, the choice to
process the operation under OP/BP 8.00 guidelines was adequate. The strong involvement
of the government especially MTPTC staff and most of the technical directorates in project
preparation ensured full ownership.
21. Two aspects of the project design are particularly noteworthy in that they
contributed to the coherence of the project in a volatile environment and to laying the
foundation for future sustainability. First, the design was built on government ownership
11
and close coordination with other development actors which ensured complementarity
among efforts. The project design also benefitted from : (i) including the recommendations
from experienced international emergency bridge specialists that had been hired under a
financing agreement with the EU; and (ii) support from the “Donors Tables” (DTs).
Second, recognizing the current ad- hoc nature of community engagement in disaster
response and preparedness, the design incorporated a long-term reinforcement and capacity
building of institutions to respond to future adverse natural events.
22. The PDO was developed to respond to the emergency context and resulting
development priorities at that time. The PDO was realistic and reachable as it focused on
the outcome for which the project could reasonably be held accountable given its duration,
resources, and approach. To achieve the two PDO elements, the project was divided into
four operational components: Components 1 and 2 aim ed to contribute to urgent and
emergency response activities following adverse natural events. Components 3 and 4, were
aligned with new institutional needs, including data collection to understand various levels
of vulnerability and risk, and to support improved management of the road network with
increased knowledge and tools necessary to identify critical points.
23. Institutional arrangements. PROReV’s PIUs were also identified following
heavy consultation with the GoH and key-line ministries. The project rel ied on two
implementation units:
(i) The Coordination and Execution Unit (UCE – Unité Centrale d’Exécution) of the
MTPTC. Composed from a mix of civil servant and national consultants, UCE was
implementing most of the externally-financed investments in transport in Haiti, with
resources from the Inter-American Development Bank (IaDB), Canada (CIDA), and the
Bank-financed PTDT (P095523). As such, it has the benefit of capacity and the ability to
compensate for institutional weaknesses at the level of line ministries. While the UCE had
been very successful in assuming the fiduciary responsibility associated with these
operations, it had yet to demonstrate capacity in handling technically larger complex
interventions and in implementing activities under a tight schedule. Despite some
limitation at that time and considering the need to handle with celerity an emergency
response the UCE remained the best available option to manage transport investments
within MTPTC. To mitigate the potential related risks, P ROReV included activities to
strengthen UCE’s implementation capacity. UCE was charged with the overall
responsibility to implement Components 1, 2 and 3 of the project, as well as overall
supervision.
(ii) Bureau de Monétisations et Programmes d’Aide au Développement’s Unité de
Coordination de Projet (BMPAD-UCP) was responsible for serving as the fiduciary agent
on behalf of MPCE for activities under Component 4. The BMPAD fell under the tutelage
MEF and was one of the Government’s principal donor project management units . At the
time, the BMPAD-UCP was implementing several Bank -financed projects, including
select components of the Emergency Recovery and Disaster Risk Management Project
(ERDMP - P090159) and the PTDT (P095523). The BMPAD-UCP had a full complement
of technical and fiduciary staff and had been very successful in managing the
12
implementation responsibilities associated with these operations. Though BMPAD-UCP
managed the fiduciary responsibilities, MPCE was responsible for the implementation of
project activities under Component 4.
24. The project’s implementation arrangements through PIUs backed by Government
commitment to the objectives of the project allowed for responsiveness, flexibility, and the
achievement of concrete results, despite a highly volatile environment (disasters and
institutional change). In retrospect, regarding implementation arrangements, stronger
explicit policies and protocols for communication and coordination on Monitoring and
Evaluation (M&E) between Project Implementation Units (PIUs) could have improved
outcomes and should be put in place for future projects involving multiple implementation
entities. Section 2.2 will provide more detail on how the arrangement of two PIU s played
out over the course of implementation.
25. Incorporation of lessons learned. A s one of the first Emergency projects
following the Bank’s re-engagement in Haiti in 2005, the project could not build on many
examples of best practices especially in the area of DRM) since the first DRM project
(EDRMP) in Haiti was under implementation a t the time. Nevertheless t he project design
accounted for lessons learned from previous Bank-financed operations in Haiti and from
Bank-wide experience with emergency response operations and within the context of a
fragile state. In particular, the project took account of: (i) simplified objectives and scope
limited to 1 or 2 sectors; (ii) use of reinforced existing implementing agencies; (iii) strong
technical assistance packages to accompany implementation and build capacity.
26. Adequacy of government commitment. Both the MTPTC, through UCE, and
MPCE, through BMPAD-UCP, were firmly involved and committed in preparation
activities. Immediately following FGHI, the GoH initiated an emergency response by
restoring basic access on the major national roads. As part of the Emergency State Law
(Loi sur l’Etat d’Urgence) promulgated on September 15, 2008, the GoH had directly
contracted four main Haitian construction firms, using unit prices from on- going
competitively awarded contracts. The design of the objectives per Component, the choice
of enterprises (local SMEs vs. ICBs), the scale of intervention, choice of technology,
procurement, coordination with other donors, GoH priorities, were amongst the issues
raised by the government. The GoH drew up the lists of prioritized works and the Bank,
in collaboration with other donors, prepared a PDNA that supported and informed the
design of PROReV.
27. Risk assessment. The project design identified a number of risks, including: (i)
delays in reconstructed infrastructure prior to following hurricane season, affecting
credibility of Government, and donors and contributing to civil unrest and political
instability; (ii) combination of adverse natural events over-exceeds the capacity of Haitian
institutions to respond; (iii) design standard under-dimensioned to cope with future
hurricane seasons; (iv) institutional infighting; (v) insufficient capacity building; (vi)
reconstruction program is over focused on quick re-builds and less on preventative
measures and policies; (vii) government commitment to DRM diverted by other issues;
and (viii) ineffective coordination between project implementation units resulting in
13
BMPAD’s inability to engage the contribution of critical ministries. After taking possible
mitigating actions into consideration, the overall risk rating was High .
28. As reflected in the supervision reports, the achievement of the PDO was never at
risk. Although all of the above risks materialized to various extents, the proactive
implementation response (restructurings) and the flexibility demonstrated by staff and
Government in supervising the project helped mitigate their impacts. In particular, major
adjustments were made to respond to the 2010 earthquake which compounded adverse
natural events and institutional weaknesses.
29. Economic Analysis. As the project was developed under OP/BP8.00, no
economic or financial analysis was carried out.
30. Quality at Entry. No Quality at Entry evaluation was carried out.
2.2 Implementation
31. There are five important factors that impacted project implementation both
negatively and positively .
32. Public sector weakness: The weakness of public sector management was a long-
standing issue when project implementation began. Given the weakness of the central
administration and the need for capacity building within the ministries, the ‘parallel’ ad
hoc project structures (PIUs) that were selected were designed to fulfill immediate needs
and ensure project efficiency. Though the project could have been implemented using
alternative arrangements (e.g. management contracts with consulting firms), this would
have weakened the project’s longer-term objective of building capacity within Haitian
government institutions to manage vulnerability and build resilience to disasters.
33. Disruptions and delays caused by the 2010 earthquake: The 2010 Earthquake
caused catastrophic damage, resulting in unprecedented disruptions and delays, halted
regular administrative activities and diverted the focus of the MPCE and the N DRMS
(including the SPGRD) to short-term disaster relief and reconstruction efforts.
Additionally, the earthquake caused an almost complete collapse of government operations.
Luckily, UCE and BMPAD only suffered limited direct human losses and damage, and as
such, these institutions were able to maintain minimal activity in the immediate aftermath
of the earthquake and were called on to make massive contributions to disaster -relief and
reconstruction activities. The operating capacity of both institutions was quickly severely
overstretched. The earthquake also required the mobilization of the NDRMS diverting
sectoral efforts accomplished since 2004, and prevented the growth of an appropriate
environment for real DRM policy reform. These issues led to the revision/ removal of 6
indicators (two PDO level). Several adjustments were required to reflect the changing
institutional environment and priorities, including the creation of a new PDO level
indicator, allowing for a more complete understanding of the activities within the
implementation channels (see Table 6 in Annex 2).
14
34. Impact of other Natural Disasters. While the occurrence of natural disasters
hampered overall project implementation, the project nonetheless managed to respond to
these events in a rapid and flexible manner. Hurricane Tomas (2010) and Hurricane Sandy
(2012) both caused severe flooding resulting in significant loss of life and damage to
infrastructure. This led to an extension of the closing date and to a scale up in activities
under Components 1 and 2 to enable the project to adequately respond to these
emergencies.
35. Donor coordination and strategic alliances in the context of the emergency: The
Bank successfully coordinated with the USAID and Agence Francaise de Développement
(AFD) to address emergency transport needs. The Table Sectorielle Transport was also
used during project preparation to coordinate and orientate complementary interventions.
Strong cooperation between development organizations such as the Bank, AFD and the
USAID was a factor of success and responsiveness especially in the context of the
emergencies. For instance, when financing fell short for a 4
th
overpass to be built under
Component 1, AFD completed the work. Studies from the project were also used to
underpin works under other IDA projects (PRGRD). Such coordination was time
consuming but effective in a context where resources were limited.
36. Institutional arrangements : Initially, the establishment of a CRV within MPCE
seemed feasible but was quickly revised following the 2010 earthquake, given the
devastating impact on the key-line ministries. As a result, the institutional reforms
necessary to achieve the activities, provided for under Component 4, were revised given
the shift of GoH priorities, and their interest in building the capacity of CIAT as a
coordinating body. CIAT, as a central actor within the Premature, was designed to anchor
dialogue regarding vulnerability reduction resilience, among other things . Under the 2013
Restructuring, CIAT was identified as a more appropriate partner than MPCE because of
its high-level mandate and capacity to assemble 6 key-ministries as a central coordinating
committee, effectively accomplishing the same target as MPCE, but at a higher level with
the greater potential for impact. CIAT was widely considered an analytical leader in post -
earthquake reconstruction, and development strategies and programs. Ultimately, MPCE’s
responsibilities regarding the integration of DRM into territorial development were
transferred to CIAT, including the CRV. The se institutional arrangements also reinforced
Component 4 activities which depended on the capacity of a transversal entity that could
assemble and implicate the key ministries. BMPAD-UCP remained the fiduciary unit for
CIAT.
2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization
37. Design. The description of the M&E structure in the Emergency Project Paper was
in accordance with generally acceptable practices. This included the establishment and
operation of a Management Information System (MIS), technical audits, monitoring and
evaluation reports. Additional human resources and equipment was provided to CIAT,
BMPAD, and UCE. UCE was also tasked with completing an end -of-project impact
assessment. Indicators were appropriate for measuring the objectives at the time.
15
38. Implementation. Whereas data collection and monitoring for Components 1 and
2 were straightforward and easy to collect, for Components 3 and 4, measuring institutional
and capacity outcomes surpassed the capacity of UCE, BMPAD and CIAT. These required
assessing qualitative outcomes and institutional processes, which the implementing entities
were neither equipped nor mandated to do. By the end of the project however, it was clear
that more efforts had gone into developing processes and procedures for M&E to improve
overall capacity than into the effective collection of project data to report on the results
framework for these two components.
39. A technical and impact assessment report prepared by independent consultants
over six months prior to the closing of the project concluded that the project impact had
been positive. It found that PDO (i): to assist the Recipient in restoring access on selected
critical points of its transport system following the FGHI Emergency, was highly achieved.
And that, the second part of the PDO, (ii) to reduce vulnerability to national disasters by
strengthening its NDRMS, was substantially achieved. However, the report did not
adequately capture the outcomes for Components 3 and 4. M&E strengthening is a priority
across the Haiti portfolio and additional training, capacity building, and implementation
support is currently being provided.
40. The Mid Term Review (MTR) was originally scheduled for early-2011, however
the attention of the Government and PIUs at the time was entirely focused on the post-
earthquake reconstruction process. The formal MTR was therefore delayed and ultimately
cancelled given the disarray that prevailed at the time. Assessment of project progress and
adjustments to the operation were undertaken in the context of the three restructurings.
2.4 Safeguard and Fiduciary Compliance
41. Safeguards: The safeguard policies that applied to the project were
Environmental Assessment (OP/BP/GP 4.01), Forests (OP/BP 4.36), and Involuntary
Resettlement (OP/BP 4.12) and the project complied with environmental and social
safeguards. The potential adverse impacts from PROReV investments turned out to be
minimal. Road and bridge spot repairs had minimal impact of the environment and have
not triggered any resettlement except for the construction of L a Theme bridge. Compliance
was monitored by the team during the many supervision missions . Additionally, MTPTC-
UCE hired a new environmental specialist to monitor compliance and strengthened its
social management team as part of its capacity enhancement plan developed to address the
large increase of operations implemented by UCE . However, proper documentation on the
compliance with environmental safeguards was lacking―the required completion of the
environmental impact-assessment checklist for all civil works were not systematically
applied. Social Safeguards management was rated MU during two ISR periods to reflect
the lack of proper documentation of compensation to a few affected persons during the
construction of La Theme bridge. Following Bank mission recommendations and a
proactive response of the GoH, the situation was addressed and resolved. The PIU has
beneficiated from trainings, technical assistance and its capacity has improved over
project’s life.
16
42. Procurement . The project complied with the Bank’s fiduciary requirements with
respect to the procurement of consultants, goods and works financed under the project as
all project procurement, independent of amounts, was subject to the Bank’s prior
review. The execution of works, design and supervision by national firms was successful
and provided substantial stimulus to the increase of private sector participation in this
sector.
43. Financial Management (FM) and audits. The project complied with the
Bank’s fiduciary requirements with respect to the appropriate utilization of funds and
submission of financial information, and maintained adequate financial management
arrangement during project implementation. Audit reports submitted by the project units
involved in project implementation reported appropriate use of Bank funds. By the end of
the project, almost 100% of funds were utilized and the implementation units successfully
closed the project.
44. Project costs. Total final project cost was SDR 12.8 million (US$20 million
equivalent) at the time of project approval. The cost s for Component 1 were higher than
anticipated due to costs associated with the rehabilitation of the La Theme bridge.
Administration, supervision, and M&E activities, as well as capacity building and technical
assistance under Component 3 were lower than both the original and revised estimates,
despite that fact that the volume of activities following the project restructurings increased,
demonstrating excellent cost efficiency under this component .
2.5 Post-completion Operation/Next Phase
45. At the request of the GoH, the Bank prepared another investment operation
building on the successes of PROReV. The DRMDP (P126346) is currently on- going and
is building directly upon the construction of resilient infrastructure approach spearheaded
by PROReV. Additionally, the Center and Artibonite Regional Development Project
(CARDP - P133352) draws on the groundwork laid by PROReV in the departments.
Component 1 of CARDP aims to promote resiliency by building and rehabilitating major
connection points, such as bridges and spot infrastructure repairs. By successfully applying
many of the lessons learned from PROReV, these projects are sustaining the PROReV-
spearheaded concepts and Bank engagement in road network connectivity and resiliency
in Haiti.
46. The RAI allows for an evaluation of the degree of connectivity in the country:
only 39%, of rural people live within 2 km of an all-weather road. Data collected
highlighted particular rural connectivity issues and challenges: two-thirds of Haitians
living in rural areas are living in areas that are poorly connected, and 50% of the surface of
the country remains poorly connected. The project, and this RAI study in particular, have
led to increased involvement with the connectivity agenda. Based on the preliminary results,
MEF has increased the budget dedicated to strengthening rural connectivity in order to
enhance access to the most isolated areas . This financing will result in additional benefits
by: (i) linking small farmers to markets and (ii) allowing improved delivery of essential
basic services and contribute to support resilience of remote communities.
17
3. Assessment of Outcomes
3.1 Relevance of Objectives, Design and Implementation
47. Relevance of PDO. The PDO was highly relevant and consistent with the key
development priorities in Haiti―as evidenced by the GoH’s development framework and
the Bank’s ISN at appraisal (See Section 1.1 ). Various disasters (hurricanes, flooding,
earthquake) which occurred during project implementation, consistent access, DRM and
resilience remained high priorities on Haiti’s development agenda (See Section 2.1 and
2.2). The PDO remained highly relevant over the project’s life, and all subsequent ISNs,
Country Assistance Strategy and Country Partnership Strategy maintained reducing Haiti’s
vulnerability to disasters and increasing its resilience as a strategic pillar.
48. Relevance of Design & Implementation strategy. The design was highly
relevant and the implementation strategy was highly responsive to emerging needs.
Infrastructure investments restored access following the FGHI and other unforeseen
emergencies and the NDRMS was strengthened by creating and operationalizing VRUs
among other activities. Although the project was prepared as an emergency project, the
project design addressed fundamental institutional and technical weaknesses of the
Government that were increasing its vulnerability to disasters. Based on data available from
the independent evaluation, the improvement in technical and institutional capacities has
increased knowledge, capacity and alignment of investments with sectors strategies to
ensure that limited resources are increasingly focused on priorities. Building on this
integrated approach, the project managed to create the enabling environment for stronger
donor involvement and coordination among key stakeholders (See Section 2.2). The close
linking of PROReV and the subsequent large scale DRMRP and strong coordination with
other donor activities has built synergies and maximized the impact of the limited resources
under the project. These factors are critical to secure continued external financial support
necessary for the continued development of the Transport and DRM sectors in Haiti. Given
the above, the ICR rates the relevance of the project design as High.
3.2 Achievement of Project Development Objectives
49. The assessment of PDO outcomes takes into consideration that two PDO
indicators (#3 and #4) were revised and subsequently dropped and one was added over the
course of the project restructurings. These changes occurred in response to the 2010
earthquake, to adapt the project to the emergency context and altered government priorities
in the wake of the crisis and subsequent natural disasters, but did not affect the overall
achievement of the PDO.
PDO (i) assist the Recipient in restoring access on selected critical points of its transport
system following the FGHI Emergency:
50. The project achieved the objective of assisting the country in restoring access on
selected critical points of its transport system following the FGHI Emergency to a high
extent based on the evidence below.
18
51. Montrouis and Chalon bridges, and La Theme overpasses were operational within
two months following Hurricane I ke, among other urgent works, minimizing disruption to
access on two major roads connecting the northern (RN1) and the southern (RN2) parts of
the country. Damaged and weakened bridges and road sections were repaired with 20
interventions at critical spots, stabilizing access in four departments, resulting in
approximately two million direct and indirect beneficiaries. (Intermediate indicators #1, #2,
#3).
52. PDO indicator #2 was achieved with the creation of a fully staffed Bridge
Management Unit under this Component: 12 engineers were trained and are employed at
MTPTC. (Intermediate Outcome Indicator #7). This unit has completed the country’s first
comprehensive national bridge inventory (Intermediate Outcome Indicator # 6) and
diagnosis on maintenance needs. From April 2011 to date, the Unit cataloged 3455 bridges,
box culverts, and hydraulic crossings, including 174 large bridges .
53. The PDO Indicator #5 was 100% achieved and contributed to stabilized access
within four departments, resulting in approximately 2 million direct and indirect
beneficiaries. The bridges, protection, critical spot intervention and sections of the road
were all realized and delivered for final acceptance, resulting in the rehabilitation of 200
km of road (repaired damaged or weakened bridges and road sections with 20 interventions
on critical spots and mitigation works (Intermediate Outcome Indicator #4). This result was
fully achieved by contracting local SMEs, thereby promoting the growth and development
of small and medium civil work enterprises. Some of the scheduled activities were canceled
due to cost overruns but were completed under other projects (See Table 2).
PDO (ii) reduce vulnerability to national disasters by strengthening its NDRMS:
54. Project achievements regarding part (ii) of the PDO, reduction of vulnerability to
national disasters by strengthening its NDRMS, were substantial and considerable, despite
the delays resulting from the 2010 earthquake and compounded adverse natural events.
State capacities to respond to emergencies and institutional capacity to reduce vulnerability
were improved through the creation of a CRV within CIAT , both the CRV and Bridge
Management Unit within MTPTC, the collection and analysis of data, and risk assessment
studies and associated Risk Management Plans. The project has substantially contributed
to strengthen the NDRMS and to reduce vulnerability to national disasters .
55. PDO Indicator #1 targeting the implementation of two operational and
sustainable CRVs was achieved. The units and tools developed further contribute to
NDRMS’s capacity (including SPGRD ) in DRM and ability to intervene in cases of crisis.
A CRV within MTPTC was established, staffed and equipped with trained engineers. An
operational manual (included M&E tools) was also developed. The director of the unit is
also integrated to the NDRMS as a representative of the MTPTC.
(Intermediate Outcome
Indicator #7). A Multi- sectoral CRV was also established, tasked with mainstreaming
vulnerability reduction in strategic land planning policies. (Intermediate Outcome Indicator
#11). Transversal development strategies and instruments were successfully developed by
19
CIAT, including key strategic documents regarding the understanding of risks and the first
multi hazard atlas and guidelines for watershed management and urban resilience
(Intermediate Outcome Indicator # 12).
3.3 Efficiency
56. At project close, May 31, 2015, all activities were completed, and the project
disbursed a total of 99.98 percent over its lifetime.
57. Unit costs of roads and bridges. The choice to prioritize use of local SMEs vs.
large firm to perform rehabilitation work s and spot improvements was quite efficient in
term of costs (see T able 3 below) for the same quality standard. UCE developed suitable
procurement rules to contract SMEs. This process successfully contributed to local
employment generation in that the bulk of contracts for Component 2 w ere awarded to
local SMEs.
Table 3: Comparison of Unit Costs of Large vs. Small and Medium Enterprises
Type of
contractors
Meshed stone
works
(‘gabions’) (m3)
Landfill
(m3)
Reinforced
concrete (m3)
Masonry
(m3)
Concrete
gutters
(linear meter)
US Dollars
Large 138 35 350 143 136
SME 95 7.6 275 85 125
Source: UCE / Technical Department
58. Administrative costs. The administrative costs incurred by UCE and BMPAD
for the overall project administration and management were reasonable compared to the
amount of investment on the ground. This is primarily attributable to the scale up of
activities implemented by UCE relating to post- earthquake rehabilitation and
reconstruction: UCE increased its workload from one Bank-financed project to three
Bank-financed projects and three IaDB-financed projects.
59. Implementation delays. There were significant implementation delays for close
to three years of the lifetime of the project from 2010 to 2013, as a result of the 2010
earthquake and other adverse natural events (Hurricane Sandy 2012). As a result, the
project saw construction delays and delays in conducting institutional studies and capacity building foreseen under Components 3 and 4. La Theme Bridge construction was
completed in late 2014, and most of the activities under C omponent 3 and 4 were completed
in 2014 and 2015. The 2010 earthquake understandably diverted the attention of the GoH
and of the PIUs toward emergency recovery activities, and did not foster a conducive environment for long term planning, policy development, and institutional strengthening needed for reform.
60. Economic Evaluation: No economic evaluation was prepared during project
design. The nature of the project component did not allow for the carrying out of a cost-
20
benefit analysis, and a cost-effectiveness analysis was instead performed, which
demonstrated that the costs of the project activities were reasonable.
61. Based on the delay s outlined above, Efficiency is considered Modest .
3.4 Justification of Overall Outcome Rating
62. The assessment made in preceding sections justify the overall outcome rating as
Moderately Satisfactory:
Relevance: The design and implementation of the PDO were and remained relevant
despite the institutional disruptions caused by the 2010 earthquake. The relevance
is rated High .
Efficacy: The PDO (i) is rated H igh given that the targets were met. The PDO
(ii) shows a S ubstantial level of achievement; however the institutional impact and
anchoring of the units created to promote integration of vulnerability reduction in
sectoral policies still requires improvement.
Efficiency: The project was generally implemented in a cost-effective way
regarding unit costs and proportion of costs used for administration, management
and technical support vs. investment costs on the ground. Nevertheless,
considerable delays attenuated project performance. The efficiency is rated
Modest.
3.5 Overarching Themes, Other Outcomes and Impacts
a) Poverty Impacts, Gender Aspects, and Social Development
63. Poverty Impact. The strategic importance of an improved transport sector and
disaster risk management for economic growth is well recognized by the GoH, and both of
these were presented as key elements of the Poverty Reduction Strategy Paper (November
2007). The project itself was pro- poor for several reasons: ( i) the poor are usually the most
vulnerable in a natural disaster; (ii) areas that were the most badly affected by FGHI were
targeted; and (iii) risk mitigation activities undertaken address the poor’s vulnerability
reduction needs. Road rehabilitation and spot improvement demonstrably served their
assigned purpose, including enabling the population not only to access markets but also
providing access to basic social services.
64. Gender Aspects. Due to the emergency context of the project preparation,
PROReV aimed to reestablish access for both men and women after a major adverse natural
event. In addition, CIAT led the review and preparation of studies aimed at new investment
models and an integrated gender equality approach. The strategic work led by CIAT on
greater rural connectivity and markets have produced the first gender based approach for
roads (“La route à deux vitesses” and Haiti Tomorrow), accounting for the specific needs
of women in using roads, intermediary public transportation, and markets.
21
65. Social Development. The damage caused by FGHI had social impacts on a large
number of local communities with more than 2.5 million people across four Departments
with no or limited access following the storms. The project immediately re -established
connections on three critical axes (RN1, R N7, and RN2), through the financing of
provisionary works which connect the capital to t wo Departments (North and South). The
RAI is a tool which will allow for the development of investment within the rural zones .
Small labor-intensive works were carried out under Component 2 and have contributed to
improve the road infrastructure resiliency and enhanced local economic opportunities.
(c) Institutional Change/Strengthening
66. PROReV earmarked substantial resources to strengthen institutions such as
MTPTC technical, statistical and road maintenance departments, UCE, CIAT and BMPAD.
67. The establishment of a B ridge Management Unit and its integration within the
MTPTC demonstrates progress toward improved asset management and will specifically
increase attention to the maintenance of critical and costly investments , such as bridges.
68. The establishment of two CRVs accounted for the needs of each institution, and
enhanced NRDMS’ capacity to prepare strategically for adverse natural events based on
informed and recent risk information. The CRVs have also supported the strengthening of
CIAT in their inter-ministerial coordination function to integrate vulnerability upstream in
sectoral and planning policies.
(d) Other Unintended Outcomes and Impacts (positive or negative)
69. PROReV financed the operation of, and technical assistance to, CIAT whose
work, post-earthquake has allowed for strategic orientation and new te rritorial
development planning. Some studies led by CIAT have contributed to new/other projects,
including the strategic document Haiti Tomorrow, which served as the foundation for the
CARDP (P133352). Though many of these studies have not been widely disseminated, the
strengthened capacity of CIAT is without question, and its data has influenced transpar ency
in decision- making, which would go even further with the full dissemination of its reports.
This is also true of the completion of the RAI under Component 3. As such, a dialogue on
next steps with CIAT would be critical, and the inclusion of financing of some key
activities under the DRMRP project could close this loop.
3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops
N/A
4. Assessment of Risk to Development Outcome
Rating: Substantial
70. The project has had major achievements and reached its objectives in terms of
access to select critical points of the Haitian transportation system under road rehabilitation
22
(Components 1 and 2), and in reinforcing resilience vulnerability by strengthening the
Haitian National Disaster Risk Management System (Components 3 and 4).
71. The survey conducted within the framework of the RAI revealed that 50 percent
of the country remains isolated and that two -thirds of rural Haitians, an estimated 3.2
million people, live in poorly connected areas. This MTPTC survey, now endorsed by the
MEF, has allowed the GoH to announce the creation of a budget line for FY 2015- 2016,
which has dedicated investments to improve connectivity in rural areas. To be sustainable,
this measure will be accompanied by the funding of a genuine policy and tool for
monitoring and data collection on the state of road assets in real time.
72. Another achievement is the promotion of local civil work s Small & M edium
Enterprises (SME). Inexpensive and flexible, they increased infrastructure resilience; they
saved the cost of fixed assets on small contracts, while executing the mandate on time and
with the expected quality. Regular maintenance of the road network should maintain this
dynamic. It should be noted that maintenance remains underfunded, and that the FER is
still suffering from a lack of resources, which only allows financing for 50 percent of the
eligible network .
73. The multitude of data from RAI's activities, bridge inventory, works; the
definition of a strategy and the creation of a plan for crisis management, prevention and
reduction of vulnerabili ty; the creation of a CRV and a Bridge M anagement Unit, the
completion of Risk Management Plans (PPRs) for the cities of Cap-Haitien and Les Cayes
reflect an increasing awareness of a GoH management plan for risks and vulnerability. The
finalization the work that can be disseminated through the digital library funded under the
Bank-financed Infrastructure and Institutions Emergency Recovery Project (IIERP –
P120895) is critical. These positive results, however, are fragile and their durability is
directly linked to the capacity of the country to maintain gains and not lose the fruit of its
investments, including both physical investments and the structures and mechanisms
implemented to support those investments.
74. On a positive note, a national vulnerability study will be completed under
DRMRP, and this study is expected to contribute to major decisions concerning the
maintenance framework. Additionally, both the CARDP and DRMRP have built on
PROReV’s experience in reducing vulnerability, spot improvement and resilient
infrastructure.
75. The Municipal Development and Urban Resilience Project (MDRUP – P155201),
currently under preparation, also draws on the experience of PROReV including practices
related to mitigation and work aiming to reduce the vulnerability of investments.
76. The risk to the development outcome is considered substantial.
23
5. Assessment of Bank and Borrower Performance
5.1 Bank Performance
(a) Bank Performance in Ensuring Quality at Entry
Rating: Satisfactory
77. The project was prepared in the aftermath of the FGHI major disaster. PROReV’ s
design was based on the Bank’s longstanding experience with emergency contexts and in
compliance with the priorities of the GoH. The design also benefitted from dialogue and
outreach for synergies between other donors in a manner that maximizes the impacts and
use of the funds. The Project design took into account for and leverage d existing
mechanisms developed under the Bank- funded projects PTDT (P095523) and ERDMP
(P090150) and capitalized on the on- going dialogue. The disaster risk management and
transport teams have collaborated very effectively across two sectoral units.
78. Based on the above, Bank performance in ensuring quality at entry is rated
Satisfactory.
(b) Quality of Supervision
Rating: Satisfactory
79. Between 2008 and 2015, the Bank has conducted 14 formal supervisory missions.
These missions covered six month periods for reviewing the technical aspects of financial
institutions, as well as the aspects relevant to procurement and social and environmental
safeguards. From 2008 and 2010, close technical supervision missions provided extensive
technical guidance to support the government and the PIUs in order to validate the technical
design. From 2011 onward, PROReV benefitted from the presence of a senior
infrastructure specialist, which allowed for the establishment of a regular dialogue with the
GoH, generally with regards to the advancement of the project, but also addressing the
more transversal themes of: maintenance, planning and prioritization of investments. The
close supervision and day to- day support by the field- based team allowed for effective
implementation and disbursement. Bottlenecks and challenges were flagged and addressed
in a timely manner.
80. Supervision missions also served as the basis to prepare the three project
Restructurings, enabling responsiveness and adequate flexibility on the part of the Bank to
adapt to unforeseen circumstances, successive emergency situations and related complex
institutional contexts . Both the 2011 and 2013 Restructurings, which occurred during the
mid-way points of project implementation , helped capture project progress.
81. Based on the above, Bank supervision is assessed as S atisfactory.
(c) Justification of Rating for Overall Bank Performance
Rating: Satisfactory
24
82. Overall, the Bank has measured its involvement and the nature of its support as
required by the expectations and difficulties of beneficiaries and stakeholders. The
availability of permanent resources within Port-au-Prince, the regularity of the supervisory
missions, and the efforts made to increase dialogue are all the elements that contributed to
the reinforcing the partnership between the Bank and the MTPTC. Aligning itself to such
challenging context, the bank team demonstrated great flexibility and involvement to the
client needs delivering answers and solutions quickly.
83. On account of all of the above considerations, the Bank overall performance for
PROReV is rated S atisfactory.
5.2 Borrower Performance
(a) Government Performance
Rating: Satisfactory
84. PROReV was largely driven by the GoH at both the design and the
implementation stages. The GoH proved responsive and capable of taking full project
ownership demonstrated through little to no typical political pressure was required
regarding the emergency context. Although project implementation was adversely affected
by the earthquake under C omponents 3 and 4, the government demonstrated notable
resilience in responding to some of the emergency needs of the country relating to the
earthquake through the channel s of the project.
(b) Implementing Agency or Agencies Performance
Rating: Moderately S atisfactory
85. The UCE served as lead agency responsible for the overall project coordination
and responsible for Components 1, 2 and 3, as well as project evaluation. The BMPAD
was responsible of the fiduciary aspects under Component 4, and CIAT was in charge of
the implementation of Component 4. UCE was responsible for the following s pecific
project implementation tasks: (i) procurement and financial management; (ii) contract
management, including road engineering and construction contracts and consulting
contracts; (iii) day-to-day field supervision; and (iv) monitoring and evaluation. In
addition, UCE was responsible for preparing quarterly reports, bi-annual audits and ad hoc
impact evaluations.
86. CIAT was responsible for the consulting contracts management and technical
supervision of activities completed under C omponent 4. BMPAD was in charge of the
fiduciary aspect under this component, while CIAT had the responsibility for M&E of
Component 4. While UCE/BMPAD’s management performance was weak at the onset, it
improved as the project implementation unfolded, guided by supervisory recommendations.
Procurement reviews were satisfactory but financial management was concluded to be
moderately satisfactory due to insufficient budgetary planning. F inancial audits were
prepared by qualified external auditors. For M&E through the MIS, the UCE/BMPAD did
not introduce an operating MIS until very late in the project; as a result M &E was generally
25
of poor quality. The progress reports were often completed late, especially for the
Component 4.
87. UCE, BMPAD and CIAT performed all the above tasks separately at their own
level with insufficient coordination between themselves, which presented major challenges
resulting in no aggregate reporting for the project as a whole.
(c) Justification of Rating for Overall Borrower Performance
Rating: Moderately Satisfactory
88. The two Implementing Agencies have performed in a very challenging
environment, marked by several disaster events and political instability. However,
considering the performance under Components 3 and 4, the M&E, fiduciary and
safeguards, the overall borrower’s performance is rated as M oderately S atisfactory.
6. Lessons Learned
89. Based on this implementation course where both flexibility and discipline were
required, PROReV offers an array of lessons about general project implementation, works
execution, and capacity building in a continual emergency context. These lessons are
summarized below.
(a) General lessons
90. Strong cooperation between development organizations such as the Bank, AFD
and the EU can be a factor of success especially in the context where leadership and donor
coordination by the Government is weak. PROReV illustrated how cooperation under a
win-win framework emphasized the adding up of the comparative advantages of these
entities, especially in an emergency context.
91. The preparation of PROReV also allowed for the integration of complementary
research within an organized dialogue with the government responding to the needs of the
Haitian context in a coherent and coordinated manner. It was worthwhile and successful
in a context where resources were limited and quick reactions were necessary. The
consultation resulted in a suitable distribution of roles between the three donors with the
Bank taking the lead for the detailed engineering studies, the works regarding a major spot
intervention and the rehabilitation of the main bridges.
92. As part of project design, the provision of resources to address emergency issues
is required in post-conflict and disaster-prone countries. While this project was developed
to respond to the urgency generated by FGHI of 2008, no provision was made to respond
to the emergenc y resulting from the 2010 earthquake and subsequent hurricanes. A limited
budget, pre-defined activities and the absence of a budget provisioned to respond to
emergencies were all significant limitations. It would have been easier to be fully prepared
right from project design in an attempt to anticipate another emergency. In this sense, the
creation of a specific component to be triggered depending on needs would have been
helpful especially since the earthquake happened less than 2 years after the date of
26
effectiveness. While few could have predicted the scale of the emergency following the
earthquake, as a disaster vulnerable country, adverse natural events with significant
impacts during the life of the project could be anticipated upstream. This lesson has already
been heeded in the Bank’s recently approved and upcoming projects for Haiti that all
include such an emergency component that can be triggered depending on prevailing
emergency circumstances.
93. The evaluation of PROReV brought to light the difficulties of coordination and
the monitoring and evaluation within a project involving different entities. In reality, the
Haitian context does not lend itself easily to interaction between distinct institutions: the
deadlines for contracting and implementation are extended and implementation suffers.
This observation was already made in the framework of the implementation of PTDT. The
experience of PROReV reinforces this observation, particularly with regards to CIAT
BMPAD dissociating the implementation of fiduciary management.
(b) Lessons concerning transport projects
94. Stabilized access and i mproved all weather connectivity confirm conventional
wisdom based on international evidence: improved access facilitate access to economic
opportunities, but also school attendance , visits to health center and general access to basic
social services. Investments and tools developed under PROReV advocate for investing in
rural roads as part of a growth and poverty/vulnerability reduction strategy in rural areas.
95. A work strategy focused on SMEs for transport infrastructure can act as a catalyst
for developing private sector activities and generating employment. Under PROReV
Components 1 and 2, the inclusion of SMEs served the need to perform spot improvement
for a widely-scattered infrastructure. In addition to being cost-effective, the SME program
had spillover effects on local development initiatives, creating employment opportunities
for the local populations involved.
96. On the institutional level, the establishment of a B ridge Management Unit and its
integration within the MTPTC highlighted the importance of road and bridge maintenance.
PROReV served as a reminder that maintenance needs must be coordinated for both the
availability of resources (FER) but also in terms of information about the status of the
network (inventory, vulnerability study) and operationalization of planning tools.
(c) Lessons concerning institutional capacity in DRM and resiliency
97. PROReV also highlighted the difficulty of carrying out reforms in such a volatile
context such as Haiti, where disaster and political vulnerabilities loom. The difficulties in
the reform of SNGRD and the limited capacity of MPCE in the wake of the earthquake
emphasized the need to work on two levels: (i) the strengthening of sectoral ministries in
the collection and management of information with regards to the management of crises
and disasters; and (ii) inter-ministerial coordination for decision making and planning of
mitigation measures (prevention, resilience).
27
98. Improved information collection and management is important to ensure
adequate disaster risk management programs and policies. Haiti continues to face
difficulties in the collection and archiving of disaster-risk information and in generating an
improved understanding of their vulnerabilities and risk. To improve resilience and better
coordination and planning in vulnerability reduction activities, the enhancement of
information management at both national and local level is critical. There is a strong need
to move towards a more integrated approach.
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners
(a) Borrower/implementing agencies
99. The ICR report was shared and discussed with the MTPTC-UCE who accepts the
rating of Moderately Satisfactory for the outcome and agrees with the findings of the ICR.
100. MTPTC-UCE highlighted the ways in which the Project managed to achieve its
objectives, despite the unprecedented effects and disruptions which resulted from the 2010
earthquake and compounded adverse natural events.
101. The lessons learned identified in the draft ICR report have been endorsed by
MTPTC-UCE, which is already taking follow -up action with MEF and associated
institutions and partners to apply these lessons in thei r on-going and future operations.
(b) Co-financiers
N/A
(c) Other partners and stakeholders
N/A
28
Annex 1. Project Costs and Financing
(a) Project Cost by Component (in USD Million equivalent)
Estimated Disbursed
Components
Appraisal
Estimate
(USD
millions)
Revised
(2011)
Revised
(2013)
Revised
(2014)
Actual /
Latest
Estimate
(USD
millions)*
%
Appraisal
%
Revised
2014
Component 1: Implementing a Program
of Bridge Reconstruction
5.05 7,165,000 7,900,597 8,030,000 6,474,068.06 128% 81%
Component 2: Improving the Resilience
of Transport Infrastructure
4.95 5,350,000 4,643,139 5,445,000 4,191,140.18 85% 77%
Sub-component 2.1: Vulnerability
reduction and repair works
4,850,000 4,643,139 5,445,000 4,191,140.18
Sub-component 2.2: Community-based
routine maintenance activities
500000 0 0 0
Component 3: Strengthening Transport
System Asset Management
1.17 2,585,000 2,556,264 2,910,000 1,949,317.56 167% 67%
Component 4: Strengthening of NDRMS 3.60 4,900,000 4,900,000 3,615,000 3,373,578.25 94% 93%
Sub-component 4.1: (formerly): Creation
of a disaster recovery and reconstruction
coordination unit with the MPCE
1,180,000
1,685,000
0 0
Sub-component 4.1: Provision of
Technical Advisory Services to NDRMS
2,220,000 1,305,000 3,017,000 1,015,000
Sub-component 4.2: Technical Assistance
to Inter-Ministerial Committee for Land-
Use Planning
1,500,000 1,910,000 1,910,000 2,600,000
Unallocated 0.40
Total Baseline Cost 0.00 0.00
Physical Contingencies 0.00 0.00 0.00
Price Contingencies 0.00 0.00 0.00
Total Project Costs 0.00 0.00
Front-end fee PPF 4.83 4.83 100
Front-end fee IBRD 0.00 0.00 .00
Total Financing Required 0.00 0.00
*Source client connection November 30, 2015
(b) Financing
Source of Funds
Type of Co-
financing
Appraisal
Estimate
(USD millions)
Actual/Latest
Estimate
(USD millions)
Percentage of
Appraisal
Borrower 0.00 0.00 .00
IDA Grant 20.00 19.42 99.98%
29
Table 4: Project Component and Detailed IDA Allocation Revisions
Components/Activities Project Costs (US$m.)
Original Initial
Allocation
2011
Restructured
Allocation
2013
Restructured
Allocation
2014
Restructured
Allocation
Component 1: Implementing a Program of Bridge
Reconstruction
7,165,000 7,165,000 7,900,597 8,030,000
Component 2: Improving the Resilience of
Transport Infrastructure
• Sub-component 2.1: Vulnerability reduction and
repair works
• Sub-component 2.2: Community-based routine
maintenance activities
4,950,000
4,450,000
500,000
5,350,000
4,850,000
500,000
4,643,139
4,643,139
0
5,445,000
5,445,000
0
Component 3: Strengthening Transport System
Asset Management
2,585,000 2,585,000 2,556,264 2,910,000
Component 4: Strengthening of NDRMS
• Sub-component 4.1 (formerly): Creation of a
disaster recovery and reconstruction coordination
unit with the MPCE
• Sub-component 4.1: Provision of Technical
Advisory Services to NDRMS
• Sub-component 4.2: Technical Assistance to
Inter-Ministerial Committee for Land-Use
Planning
4,900,000
1,180,000
2,220,000
1,500,000
4,900,000
1,685,000
1,305,000
1,910,000
4,900,000
0
3,017,000
1,910,000
3,615,000
0
1,015,000
2,600,000
Unallocated 400,000 0 0 0
Total 20,000,000 20,000,000 20,000,000 20,000,000
30
Annex 2. Outputs by Component
Component 1: Implementing a Program of Bridge Reconstruction
1. Works undertaken under Component 1 were realized efficiently, completely and
according to their deadlines. Component 1 allowed for the realization of multiple urgent
works which contributed to the re-establishment of access to the Haitian road networks.
2. The Montrouis, Chalon and La Theme fords and overpasses were operational
within two months following Hurricane Ike, allowing minimal disruption to access on two
major roads connecting the northern (RN1) and the southern (RN2) parts of the country,
restoring important economic flow and traffic. (Intermediate Outcome Indicator #1) This
result was achieved by contracting local SMEs, promoting the growth and development of
small and medium civil work enterprises.
3. The completion of the La Theme Bridge was critical to restore access in Mirebalais.
It also facilitated access to the primary and most equipped hospital in the country, and to a
major regional road along the fertile valley of Artibonite, supporting the rice and mango
productions (Intermediate Outcome Indicator #2) Ten emergency bridges were purchased
(Intermediate Outcome Indicator #3). MTPTC staff were trained on the installation of
emergency bridges and seven of the ten emergency bridges purchased were used during
the project life to restore access on roads made inaccessible following adverse natural
events (Hurricane Thomas 2010, Sandy 2012). The outcomes of this Component were
tangible and timely.
Component 2: Improving the Resilience of Transport Infrastructure
4. Component 2 repaired damaged or weakened bridges and road sections with 17
interventions on critical spots and mitigation works ( Intermediate Outcome Indicator #4).
Component 2 contributed to stabilized access within four departments, resul ting in
approximately 2 million direct and indirect beneficiaries. The bridges, prot ection, critical
spot intervention and sections of the road were all realized and delivered for final
acceptance, resulting in the rehabilitation of 200 km of road (PDO Indicator #3). This
result was fully achieved by contracting local SMEs, thereby promoting the growth and
development of small and medium civil work enterprises. The initial target of section
repairs was revised under the 2011 Restructuring in light of the necessary cost reallocation
at the time. Cost savings during project execution allowed for the reallocation of funds
from slow disbursing Component 4 to this component increasing in the number of critical
spot interventions to a level close to the initial target. The proposed rating for the outcomes
of this component is Satisfactory.
Component 3: Strengthening Transport System Asset Management
5. PDO indicator #2 was also achieved with the creation of a fully staffed Bridge
Management Unit under this C omponent: 12 engineers were trained and are employed at
31
MTPTC. (Intermediate Outcome Indicator # 7). This unit has completed the country’s first
comprehensive national bridge inventory (Intermediate Outcome Indicator # 5) and
diagnosis on maintenance needs. From April 2011 to date, the Unit cataloged 3455 bridges,
box culverts, and hydraulic crossings, including 174 large bridges. A crisis management
and vulnerability reduction unit (DRM unit) was established, staffed and equipped within
MTPTC with trained engineers. An operational manual (included M&E tools) was also
developed. The director of the unit is also integrated to the National Disaster Risk
Management System as a representative of the MTPTC. (Intermediate Ou tcome Indicator
# 6). The completion of the RAI allowed for the characterization of the connectivity and
the isolation of half the country. Only 39 percent of the rural population in Haiti has access
to an all-weather road within two kilometers. The results of the RAI have proven to be
extremely useful, timely and resulted in MEF including measures in the budget to enhance
connectivity. These units and tools developed further contribute to MTPTC’s capacity in
asset management and ability to intervene in cases of crisis.
Component 4: Strengthening of NDRMS
6. PDO Indicator #1 targeting the implementation of two operational and sustainable
Disaster Risk Management Units was achieved. These units were adequately equipped and
well positioned to account for related institutions and responded to the specific needs of
both CIAT and MTPTC. Transversal development strategies and instruments were
successfully developed by CIAT, including key strategic documents regarding the
understanding of risk s and the first multi hazard atlas and guidelines for watershed
management and urban resilience. A Multi- sectoral Vulnerability Reduction Unit (CRV)
was also established, tasked with mainstreaming vulnerability reduction in strategic land
planning policies
(Intermediate Outcome Indicator # 8 and # 9) .
32
Table 5: Outputs by Component
Component 3
Outputs Description
DRM CRV unit, created staffed and equipped with
competent resources and tool within the MTPTC
Operational Manual
Action and work plans
Capacity building plan
MTPTC and SPGRD staff trained
Bridge management Unit created staffed and
equipped with competent resources and tool within
the MTPTC
The inventory of existing bridges is completed
3455 hydraulic crossings including 174 bridges evaluated.
12 young Engineers of MTPTC trained
Components 1 and 2
Type of Work Réception
1 Implementing a Program of Bridge Reconstruction
Ford construction Chalon April 2009
Ford construction Montrouis April 2009
Ford construction Mirebalais April 2009
Ford construction et protection works Rivière Gauche 2010
Retaining Wall Construction morne Saint Georges, RN2 2011
Deck Destruction and Removal La Thème Bridge, Mirebalais October 2010
Reconstruction La Thème Bridge (Mirebalais) March 2015
Rehabilitation Ford construction rivière Gauche January 2012
Protection et Reparation Works, (box Culvert) Deuxième plaine, RN2 December 2014
Protection and reconstruction works (nozzle), Saint Louis du Sud, RN2 – March 2015
Protection et Reparation Works (nozzle), Saint Louis du Sud, RN2 December 2014
Protection et Reparation Works (2 boxes culvert), Saint Louis du Sud December 2014
Protection et Reparation Works (nozzle), Saint Louis du Sud, RN2 December 2014
Construction Chalon Bridge PRGRD (complete)
Estime Dumarsais Bridges PRGRD
Voldrogue and Roseaux PRGRD & GoH
2 Improving the Resilience of Transport Infrastructure
Protection works (gabions), Cavaillon Bridge, RN2 January 2011
Reparation works (Abutments) La Gosseline, RN4 January 2011
Works protection, Pont Tabarre, RN8 February 2011
Reparation work (Box culvert), Bonnet Bridge Croix des Bouquets, RN8 November 2010
Reparation works (Abutments), Croix des Missions bridge, RN1 March 2013
Reparation and protection works, Piers, La Ravine du Sud Bridge, Cayes November 2011
Construction (boxes culvert), Gelée, Cayes January 2012
Protection works (Retaining Wall pont, gabions) Boumier, RN2 March 2011
Protection works (abutments) Grande Rivière de Jacmel Bridge , RN4 March 2010
Réparation work (Drainage system) pont Torbeck, RD25 March 2010
Rehabilitation works Jacmel, RN4 (UNOPS) November 2010
Drainage RN2/Port au Prince June 2011
Protection works Bretelle river Bridge, commune Cabaret, RN1 September 2012
Protection works, Bridge Route de Léon, Jérémie November 2011
Reparation works, Zanglais d’Aquin, commune Saint Louis du Sud, RN2 November 2011
Construction Box culvert, Mapang, route Cavaillon – Baradères July 2011
Protection works RN2, zone Bellevue, commune Aquin, RN2 April 2015
Construction works (ford) à Labattre, Chantal – Arniquet, Sud April 2015
Protection works Solon, RN2 April 2015
Construction works (for), Vieux Bourg d’Aquin, village La Ferme April 2015
33
Completion of the RAI establishing key numbers
and information on rural connectivity for Haiti
46 Members of MTPTC trained
44 maps produced
10 Departmental direction equipped with GPS and
computer
Component 4
Outputs
Transversal DRM CRV unit, created staffed and equipped with competent resources and tools within CIAT
Dissemination activities (Work shop; Publication; conference)
Completion of an Atlas of Natural Risks
Protected areas study
Elaboration and dissemination of urban national Forum proceedings
Compilation of existed laws and legal texts on urban planning
Drainage and Risk Management Plans (PPR) for the city of Les Cayes
Flood mapping and development of flood risk management plans for Cap Haitien
Corridor Nord Nord-est Master Plan
34
Table 6: Revisions to Results Framework
PDO
Original (PAD) 2011 Restructuring 2013 Restructuring 2014 Restructuring
The project’s development objective is to i)
restore access on selected critical points of
the Haitian transport system, and ii) support
vulnerability reduction by strengthening the
Haitian National Disaster Risk Management
System.
No change. No change. No change.
PDO indicators
Original (PAD) Proposed Changes
Disaster Risk Management Units within key
ministries are operational and sustainable,
with adequate resources and staffing
Revised. Disaster Risk Management
Units within key ministries are operational and sustainable, with
adequate resources and staffing before
the end of 2013
Revised. Disaster Risk Management
Units within key ministries are
operational and sustainable, with
adequate instruments/tools and staffing
before the end of the project.
No change.
MTPTC bridge management unit is
operational and sustainable, with adequate
resources and staffing
No change. No change. No change.
MPCE vulnerability reduction unit is
operational and sustainable
No change. Dropped. The Vulnerability
Reduction Unit (CRV - Cellule de
Réduction de la Vulnérabilité) in the
MPCE was discontinued as of
November 2011 due to changes in the
national institutional framework. Some
of its responsibilities related to the
integration of DRM in territorial
planning were transferred to CIAT.
N/A
Permanent Secretariat of Disaster Risk
Management (SPGRD) unit is reinforced, operational and sustainable
Revised. National Disaster Risk
Management System Policy and framework assessed and strengthened
before the end of 2013.
Dropped. The impact of the 2010
earthquake has not created a conducive environment for a policy reform on
DRM.
N/A
Roads rehabilitated (km), Non-Rural roads N/A New. Including new Core Indicator to
monitor progress.
No change.
35
Intermediate Results indicators
Original (PAD) Proposed Changes
Component 1: Implementing a Program of Bridge Reconstruction
Number of emergency fords and overpasses
built in the two months following
No change. No change. No change.
Number of bridges rebuilt with satisfactory
technical standards
No change. No change. No change.
10 emergency bridges purchased No change. No change. No change.
Component 2: Improving the resilience of transport infrastructure
Number of bridges and road sections that
have been repaired or consolidated with
satisfactory technical standards
No change. No change. Revised. Change in end target from 8
spots to 11.
Number of community-based initiatives
performing routine maintenance with
satisfactory technical standards
No change. Dropped. Sub-component linked to
this indicator has been dropped.
N/A
Component 3: Strengthening Transport System Asset Management
Bridge inventory completed and up to date No change. No change. No change.
Constitution of an effective crisis
management and vulnerability reduction
unit in MTPTC
No change. No change. No change.
Constitution of a bridge management unit in
MTPTC
No change. No change. No change.
Component 4: Strengthening of NDRMS
Establishment of Disaster Recovery and
Reconstruction Planning Unit within MPCE
Revised. Vulnerability Reduction Unit
established within MPCE and a National
Framework for Vulnerability Reduction
created, in place before the end of 2012
and integrated into sectoral policies and
programs before the end of 2013.
Dropped. : The Vulnerability
Reduction Unit (CRV) in MPCE was
transferred to CIAT as of Nov. 2011
due to changes in the national
institutional framework.
N/A
Presentation of Disaster Recovery and
Reconstruction Program
Revised. Timely presentation of
Disaster Recovery and Reconstruction
Program(s) are submitted and
coordinated every semester and yearly
by all stakeholders from second semester
of 2011.
Dropped. Dedicated PM’s office
installed after 2010 Earthquake has
been discontinued.
N/A
36
Number of Crisis Management and
Vulnerability Reduction Units created
within line ministries and within their
departmental directorates (where applicable)
Revised. Number of Emergency
Management and Vulnerability
Reduction Units (CRVs)
created/reinforced and operational
within line ministries and within their
departmental directorates (where
applicable) before the end of 2013.
Revised. Number of Emergency
Management and Vulnerability Reduction Units (CRVs)
created/reinforced and operational
within line ministries and within their departmental directorates (where applicable) before the end of the
project.
Revised. A Multi-sectoral Vulnerability
Reduction Unit (CRV) created and
operational within CIAT before the end
of the project.
Transversal development strategies
developed by CIAT (i.e.: watershed management, urban planning, territorial
development and land tenure).
Revised. Transversal development
strategies developed by CIAT and CRV
(i.e.: watershed management, urban
planning, territorial development and
land tenure) established and in place
before the end of 2013.
Revised. Transversal development
strategies and instruments developed by
CIAT (i.e.: watershed management,
urban planning, territorial development
and land tenure) established and in
place before the end of the project.
No change.
Disaster risk reduction principles integrated
into these transversal strategies:
Revised. Disaster Risk management
principals integrated and assessed into
these transversal strategies before the
end of 2013.
Dropped. Instruments to integrate
DRM in territorial planning will be developed as part of the previous
indicator.
N/A
37
Annex 3. Economic and Financial Analysis
N/A
38
Annex 4. Bank Lending and Implementation Support/Supervision Processes
(a) Task Team members
Names Title Unit
Responsibility/
Specialty
Lending
Solange A. Alliali Senior Counsel LEGES
Louis Boutaud de la Combe Consultant LCSUW
Ross Alexander Gartley Consultant LCSUW
Gregoire Francois Gauthier Sr Transport. Engr. LCSTR
Nicolas Peltier-Thiberge Senior Infrastructure Economis AFTTR
Leila Diana Sarquis Aquino Temporary LCSTR
Fily Sissoko Lead Financial Management Spec AFTME
Jose C. Joaquin Toro Landivar Senior Disaster Risk Managemen LCSDU
Yao Wottor Senior Procurement Specialist LCSPT
Supervision/ICR
Louis Boutaud de la Combe Consultant LCSUW
Olivier Devoret Temporary LCSTR
Ross Alexander Gartley Consultant LCSUW
Gregoire Francois Gauthier Sr Transport. Engr. LCSTR
Licette M. Moncayo Program Assistant LCSTR
Glenn S. Morgan Regional Safeguards Adviser LCSDE
Fily Sissoko Lead Financial Management Spec AFTME
Yao Wottor Senior Procurement Specialist LCSPT
(b) Staff Time and Cost
Stage of Project Cycle
Staff Time and Cost (Bank Budget Only)
No. of staff weeks
USD Thousands
(including travel and
consultant costs)
Lending
FY09 16.78 90.4
Total: 16.78 90.4
Supervision/ICR
FY09 10.66 111.86
FY10 18.08 187.60
FY11 20.40 92.13
FY12 13.83 56.59
FY13 19.66 79.96
FY14 22.19 132.00
FY15 33.85 154.19
FY16 7.43 42.94
Total: 146.10 857.27
39
Annex 5. Summary of Borrower's ICR and/or Comments on Draft ICR
Summary:
1. Le projet du PROReV a été approuvé le 18 novembre 2008 pour un don de l’IDA
de 20 millions d’US$ qui finance partiellement les coûts relatifs à la reconstruction et à la
réparation en urgence d’infrastructures clés détruites ou endommagées suite au passage des
quatre cyclones d’août et de septembre 2008. Les travaux ont ainsi été réalisés et prévus
dans un contexte d’urgence suite aux passages de ces cyclones. Les objectifs du projet
étaient de :
• rétablir l’accès à des endroits importants du système de transport haïtien ;
• soutenir la réduction de la vulnérabilité en renforçant le Système Haïtien de Gestion
des Risques et des Désastres et par la création de connaissances et d’expertises au sein
de l’appareil gouvernemental.
2. De ce fait, le PROReV a été constitué de quatre composantes dont les trois
premières relevaient de L’Unité Centrale d’Exécution (UCE), elle- même partie prenante
du MTPTC (Ministère des Travaux Publics, Transport et Communications). La quatrième
composante relevait du Comité Interministériel d’Aménagement du Territoire (CIAT),
exécutante du Bureau de Monétisation des Programmes d'Aide au Développement
(BMPAD). Les quatre composantes ont été établies conjointement par la Banque Mondiale,
l’UCE et le CIAT. Ces 4 composantes sont les suivantes:
• Composante 1: Reconstruction de ponts sélectionnés pour rétablir l’accès;
• Composante 2: Amélioration de la résilience des infrastructures de transport;
• Composante 3: Amélioration de la gestion patrimoniale du transport;
• Composante 4: Renforcement du système national haïtien de gestion de risque et
des désastres par le renforcement institutionnel et la coordination des différents
acteurs et institutions dans la prévention et/ou l’intervention en cas de catastrophes.
3. C’est à partir de ces 4 composantes qu’ont été déterminées les activités à réaliser,
tant sur le terrain que dans l’appareil gouvernemental. Ces activités sont mesurées par des
indicateurs. Les indicateurs ont été choisis par la Banque Mondiale et le Gouvernement de
la République d’Haïti dans le but de mesurer les deux objectifs principaux, dans un
contexte de reconstruction d’urgence et d’amélioration de la résilience et de gestion des
risques. Une matrice des résultats a été définies afin d’évaluer la réponse à ces indicateurs.
Chaque indicateur est évalué par une unité de mesure, avec une valeur cible prévue par
année afin d’en effectuer le suivi. Elle se compose d’abord de trois indicateurs principaux
qui répondent aux objectifs initiaux:
• Des unités de gestion du risque au sein des ministères clés sont opérationnelles et
disposent de ressources suffisantes;
• Une unité de gestion du risque est présente et opérationnelle au sein du MTPTC et
dispose de ressources suffisantes ;
• Le nombre de kilomètre de routes réhabilitées.
40
Ensuite chaque composante correspond aux résultats intermédiaires attendus dans le
PROReV. Ils sont également constitués d’indicateurs de mesure par année avec les valeurs
cibles. Entre la composition du projet initial et celui évalué dans le cadre de cette étude
d’achèvement, le PROReV a connu trois restructurations, modifiant le choix des activités,
les indicateurs ou la date de fermeture et effectuant le transfert des budgets d’une
composante à l’autre.
4. Aucune problématique particulière n’a été rencontrée à l’étape de la définition des
objectifs, indicateurs et concept du PROReV. L’urgence d’intervenir constituait le
principal moteur de la création du PROReV. Les mécanismes institutionnels se sont mis
en marche dès le moment où la Banque Mondiale a été sollicitée pour une assistance
financière suite au passage des 4 cyclones. Les acteurs impliqués au sein des différentes
institutions du Gouvernement de la République d’Haïti ont défini les critères du PROReV
dans une démarche cohérente, efficace et inclusive avec la Banque Mondiale. De ce fait,
la conception du projet a été conduite de façon conjointe par les cadres nationaux et les
cadres de la Banque Mondiale. Diverses missions de reconnaissance et de préparation ont
été effectuées durant l’année 2008 par l’UCE, assistée du personnel de la Banque Mondiale
et de consultants privés. Ces missions ont permis d’évaluer l’ampleur des dégâts en plus
de rencontrer les directions régionales et les collectivités locales et, ainsi, de cibler les
interventions à prioriser, tant sur l’axe routier de la route Nationale 2, dans la région du
sud, qu’à Mirebalais, dans le département du Centre. Des présentations ont été faites aux
partenaires nationaux et départementaux afin de confirmer la stratégie de mise en oeuvre,
le choix des interventions à prioriser et les problématiques à régler en termes d’accessibilité
et de création des connaissances.
5. Les parties prenantes dans le choix des activités à réaliser ont été l’’UCE pour les
composantes 1-2-3 et le BMPAD pour la composante 4; tel que relaté lors des différentes
rencontres, ce processus s’est réalisé de manière tout à fait indépendante et libre
d’influence extérieure. Selon les témoignages obtenus, le processus de passation des
marchés a suivi de manière rigoureuse les normes décrites dans le manuel d’opération
référant aux dispositions en vigueur. Cependant, il importe de souligner que les garanties
financières exigées auprès des entrepreneurs ont entrainé un retard dans le début des
travaux. En effet, pour plusieurs firmes haïtiennes, l’obtention de ces garanties constitue
un obstacle majeur nécessitant un délai important. De plus, le CIAT ne gérant pas
directement le budget de la composante 4, de nombreux allers-retours ont dû être effectués
auprès du BMPAD pour l’approbation du choix des études et des consultants ainsi que pour
le paiement des factures. En effet, puisque le CIAT est la branche exécutante du BMPAD,
celle-ci n’a pas le pouvoir de gérer les budgets du PROReV. Ensuite, les délais rencontrés
par le CIAT dans la validation et la réception des non- obligations de la Banque Mondiale
dans le choix des études ou la proposition d’avenants ont également fait retarder le
lancement de certaines études.
6. En ce qui a trait au déroulement des activités du PROReV et à la réalisation des
objectifs globaux, en fonction des témoignages recueillis, des visites de terrain effectuées
sur les projets échantillonnés et des rencontres tenues avec les bénéficiaires, les travaux
prévus aux composantes 1 et 2 ont été réalisées selon les délais impartis. Les ponts, dalots,
41
ponceaux et sections de routes ont tous été réalisé et livrés pour réception finale à la
satisfaction de l’UCE. De manière générale, l’objectif de rétablissement de l’accessibilité
du PROReV est atteint.
7. En ce qui a trait à l’objectif de renforcement des capacités, les activités
échantillonnées des composantes 3 et 4 démontrent que les formations prévues pour la
cellule d’ouvrage d’art, la création d’une cellule transversale de réduction de la
vulnérabilité ainsi que les collectes et traitement de données du RAI ont été réalisés, tout
comme les études d’aménagement du territoire du CIAT. Ainsi, cet objectif du PROReV
est atteint.
8. La matrice des résultats globaux indiquent que le PROReV a réalisé toutes ses
activités et a rempli tous ses objectifs, que tant au niveau global qu’intermédiaire pour les
composantes 1, 2, 3 et 4.
9. En fonction des informations et témoignages obtenus, le PROReV permet de
dégager des bénéfices selon trois horizons : court, moyen et long terme. Les bénéfices à
court terme correspondent à favoriser les entreprises haïtiennes dans les travaux de
reconstruction et de surveillance, la formation d’ingénieurs, faire des économies réalisées
grâce à l’emploi de firmes haïtiennes, effectuer l’inventaire des ouvrages d’art, la création
d’une cellule de réduction de la vulnérabilité au MTPTC et au CIAT. Les bénéfices à
moyen terme correspondent à avoir développé une méthodologie de collecte des données
sur la qualité du réseau routier. De ce fait, plusieurs ingénieurs ont pu être formés à la
méthode rigoureuse de collecte, ainsi qu’à la production de cartes avec les outils
géomatiques. Une telle expertise peut dépasser le cadre du PROReV (études économiques,
commerciales, touristiques, etc.). Le bénéfice à long terme correspond à la réalisation des
études sur l’aménagement du territoire, dont les résultats et conclusions permettent de poser
des actions sur le long terme afin de réduire la vulnérabilité du pays en cas de catastrophes
(reboisement, planification urbanistique, ensemencement, etc.).
Les principaux obstacles à la pérennité du PROReV sont de trois ordres, soit économique,
technique et institutionnel. Le premier obstacle, d’ordre économique, correspond au
financement récurent des organismes créés (cellule de crise) suite au PROReV ou retirant
un budget de fonctionnement (CIAT). Le second obstacle, d’ordre technique, correspond
à la maintenance des infrastructures afin d’en assurer la durée de vie et d’en optimiser le
fonctionnement. Le troisième obstacle, d’ordre institutionnel, correspond à la valorisation
des études, expertises et informations obtenues grâce au PROReV.
10. De manière générale, les parties prenantes sont satisfaites de leurs relations avec
leurs partenaires durant le PROReV, mais soulèvent tout de même les difficultés suivantes:
• Bien que cette situation soit en cours d’amélioration, plusieurs acteurs ont soulevé
les délais encourus auprès de la Banque Mondiale pour obtenir leurs non-objectifs;
• Le CIAT n’était pas un agent fiduciaire, elle doit constamment faire des aller-
retour auprès du BMPAD pour toute décision financière;
• Les acteurs remarquent que globalement, les réunions ne comportent pas
suffisamment d’aide-mémoires;
42
• Puisque les composantes 1, 2 et 3 étaient de la responsabilité de l’UCE, avec son
budget dédié et que la composante 4 était du ressort du BMPAD, il était parfois
difficile de connaitre l’état d’avancement des partenaires.
11. En ce qui a trait aux leçons apprises dans la réalisation du PROReV, elles
correspondent à :
• Le besoin d’une direction commune au sein du Gouvernement Haïtien pouvant
effectuer les liens entre le MTPTC et le BMPAD;
• L’assouplissement des garanties financières demandées pour les entrepreneurs
haïtiens;
• Des ressources supplémentaires pour la passation des marchés et assurer la
pérennité des infrastructures et retenir le personnel engagé par le PROReV au
CIAT;
• Des mécanismes de diffusion et de valorisation des études réalisées par le CIAT;
• L’amélioration des délais des non-objections de la Banque Mondiale;
• Une harmonisation des taux monétaires entre celle utilisée par la Banque Mondiale
(XDR) et celles du Gouvernement de la République d’Haïti (dollar américain et
gourdes)
Commentary: transmis par l’UCE/MTPTC
12. L’UCE/MTPTC a pris note que le projet P114292 PROReV est jugé modérément
satisfaisante et concorde avec cette évaluation.
13. Bien que documenté dans le rapport, l‘UCE/MTPTC tient à souligne r l’impact
dévastateur du tremblement de terre du 12 janvier 2010 ayant considérablement
fragilisé et perturbé l’ensemble des institutions et affecte la mise en œuvre du projet.
14. Le MTPTC note que la réactivité et le niveau de résilience desacteurs et institutions
concernees ont bien été documentées ainsi que les capacités d’adaptation du projet et des
parties prenantes pour l’atteinte des objectids de developpement..
15. Le MTPTC partage les conclusions du présent rapport sur le niveau considérable
d’achèvement obtenu dans des circonstances exceptionnelles et rappelle par ailleurs que
les retards constatés doivent être analysés au regard des dysfonctionnements occasionnés
par le tremblement de terre.
16. Les progrès réalisés en matière de renforcement de capacités institutionnelles ont
été substantiels et ont permis de jeter des bases solides pour améliorer la maintenance du
patrimoine d’ouvrages d’art et pour l’intergration de la reduction de la vulnerabilite dans
les poilitiques sectorielles et confirme son engagement a poursuivre les les efforts en la
matière.
17. Nous notons par ailleurs avec satisfaction que notre évaluation et celle du présent
rapport convergent vers des conclusions similaires.
43
Annex 6. Comments of Co-financiers and Other Partners/Stakeholders
N/A
44
Annex 7. List of Supporting Documents
• Project Appraisal Document, Report No: 34938 – HT, March 13, 2006
• Financing Agreement Emergency Bridge Reconstruction and Vulnerability
Reduction Project , February 12, 2009
• Restructuring paper (2011) Report No: 57816- HT March 21, 2011
• Restructuring paper (2013) Report No: 78211 v1 May 30, 2013
• Amendment to the Financing Agreement June 6, 2013.
• Restructuring Paper (2014) Report No: RES16344 October 8, 2014
• UNOPS Final Report, May 2015
• UCE/BMPAD, various quarterly reports
• Financial audits 2009- 2015
• Project Impact Evaluation Study, WSP , May 2015
• UCE Rapport d’Achèvement, June 2013
45