Teks Konple Dokiman an
Teks ki soti nan dokiman orijinal la pou endeksasyon.
Document of
THE WORLD BANK
FOR OFFICIAL USE ONLY
Report No. 19981
IMPLEMENTATION COMPLETION REPORT
HAITI
PORT-AU-PRINCE WATER SUPPLY PROJECT
(CREDIT 2052-HA)
December 21, 1999
Finance, Private Sector and Infrastructure Department
Caribbean Country Management Unit
Latin America and Caribbean Region
This document has restricted distribution and may be used by
recipients only in the performance of their official duties. Its contents
may not otherwise be disclosed without World Bank Authorization.
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
CURRENCY UNIT:
Gourde
EXCHANGE RATE FOR US$1.00
(Yearly Average)
1989 : 5.00 1995 : 15.1
1990 : 5.00 1996 : 15.7
1991 : 6.00 1997 : 16.7
1992 : 9.80 1998 : 16.8
1993 : 12.8 1999 : 16.9
1994 : 15.0
WEIGHTS AND MEASURES
Metric System
FISCAL YEAR
October 1 to September 30
ABBREVIATIONS AND ACRONYMS
AFD Agence Francaise de Developpement
CAMEP : Centrale Autonome Metropolitaine d'Eau Potable
IDA : International Development Association
IDB : Inter-American Development Bank
POCHEP : Projet de Poste Communautaire d'Hygiene et
d'Eau Potable
PPF : Project Preparation Facility
SNEP : Service National d'Eau Potable
UFW : Unaccounted For Water
Vice President: David de Ferranti
Country Director: Orsalia Kalantzopoulos
Sector Director: Danny Leipziger
Task Manager: Emmanuel Njomo
FOR OFFICMIL USE ONLY
Table of Contents
Page No.
Preface ....................................... i
Evaluation Summary ....................................... ii
PART I: Project Implementation Assessment ..................................... 1
A. Background .I
B. Project Objectives .2
C. Achievement of Project Objectives .3
D. Major Factors Affecting the Project .9
E. Project Sustainability .1
F. IDA Performance .12
G. Borrower Performance .13
H. Assessment of Outcome .14
t. Future Operations .15
J. Summary of Findings and Key Lessons Learned .15
PART HI: Statistical Annexes .................... . 18
Table 1: Summary of Assessments .19
Table 2: Related Bank Credits .20
Table 3: Project Timetable .20
Table 4: Credit Disbursements:
Cumulative Estimated and Actual .21
Table 5: Key Operational Performance Indicators .22
Table 6: Key Financial and Institutional Performance
Indicators .23
Table 7: Number of Water Connections .24
Table 8: Project Scope and Costs .25
Table 9: Project Financing .28
Table 10: Allocation of Credit Proceeds ................................. 29
Table 11: Economic Rate of Return ................................. 30
Table 12: Financial & Economic Evaluation ................................ 31
Table 13a: Etat des Resultats ................................. 32
Table 13b: Key Elements of Income Statements ............................. .33
Table 14: Bank Resources: Missions ................................. 34
Table 15: Bank Resources: Staff Inputs ................................. 35
Table 16: Status of Legal Covenants ................................. 36
Appendix: Borrower's Contribution ................................. 38
Map: IBRD No. 21564
This document has restricted distribution and may be used by recipients only in the performance of
their official duties. Its contents may not otherwise be disclosed without World Bank Authorization.
IMPLEMENTATION COMPLETION REPORT
HAITI
PORT-AU-PRINCE WATER SUPPLY PROJECT
(CREDIT 2052-HA)
PREFACE
1. This is the Implementation Completion Report (ICR) on the Port-au-Prince Water
Supply Project in Haiti. It was supported by Credit 2052-HA in the amount of SDR 15.2
million (US$20 million), which was approved on June 27, 1989 and became effective on
February 14, 1990. The last disbursement took place on November 29, 1999 at which time
an undisbursed balance of SDR 0.38 million was cancelled.
2. The Credit was suspended in October 1991, following a coup d'etat. The suspension
was lifted in December 1994 following which the project was amended on December 7, 1995
to adapt it to the post-embargo environment. The original Closing Date was extended to June
30, 1999.
3. The project was restructured in December, 1998 with one of the main aims of
fostering a deeper private sector involvement in the water sector in Haiti. Had this effort
been successful, the revised project Closing Date might have been further extended.
However, the water sector reform law ( prepared with IDB's assistance ) that would have
helped bring about significant changes has not yet been approved by Parliament and attempts
to use an alternative law have not been successful. The project closed on June 30, 1999. Co-
financing for the project was provided from the Agence Francaise de Developpement (AFD)
and the OPEC Fund.
4. This ICR was prepared by Bernard Decaux (consultant) and Emmanuel Njomo (Task
Manager), who visited Port-au-Prince, Haiti, from October 23 to 30, 1999. It is based on
information obtained during this mission and contained in the project files. The borrower
contributed to the preparation of the ICR by providing facts, figures and views. The ICR was
reviewed by Oscar Alvarado, Abel Mejia and Max Pulgar-Vidal.
5. A translated summary of the borrower's report on the project is attached as an
Appendix. The full report is available in the project files.
IMPLEMENTATION COMPLETION REPORT
HAITI
PORT-AU-PRINCE WATER SUPPLY PROJECT
(Credit 2052-HA)
EVALUATION SUMMARY
Introduction
1. Port-au-Prince is a city of almost 2 million inhabitants or about 25% of Haiti's
population. During the last two decades, the number of inhabitants has more than doubled,
mainly because of immigration from rural areas. This has led to a rapid development of low
income neighborhoods, with little access to potable water and deficient sanitary conditions.
Project Objectives
2. The original Government request was for IDA assistance to improve water services in
the Port-au-Prince Metropolitan area and strengthen the institutional capabilities of Centrale
Autonome Metropolitaine d'Eau Potable (CAMEP). The specific project objectives were to:
(a) develop CAMEP into an operationally and administratively efficient and financially
viable water utility; (b) improve and expand water services in the project area; (c) execute a
first stage investment program to rehabilitate existing water supply infrastructure; (d)
formulate a concrete plan for improving the sanitary conditions in Port-au-Prince; and (e)
attain the Government agreement on a strategy and a plan of action for achieving more
dynamic and efficient water sector. These objectives were addressed by three project
components: expansion of the water supply system through infrastructure investments,
institutional development, and technical assistance and studies.
Project Implementation
3. Credit 2052-HA was approved on June 27, 1989, and became effective on February
14, 1990. The original closing date was June 30, 1994; it was extended to June 30, 1999, to
make up for the delays resulting from the three year suspension that followed the coup d'etat
and the slow start of the project which was partly due to difficult procurement problems. The
project was restructured in December, 1998 primarily with the aim of fostering a deeper
private sector involvement in the water sector in Haiti. Had this effort been successful, the
closing date might have been extended further. However, the water sector reform law that
would have helped bring change about is still held up in the Parliament and attempts to use an
alternative law have not been successful. The preparation of this law was financed by the
IDB. The project closed on June 30, 1999. Total project cost is calculated at US$35.4
million of which, US$20.5 million were drawn from the IDA credit. In addition, cofinancing
in a form of two loans, totaling about US$15 million was obtained from the French Agency
of Development and the OPEC Fund. Only US$0.3 million came from the water supply
company and the Haitian Government.
iii
4. Project implementation did not really start until 1995, when the project was reactived
after the three-year suspension. After disbursements were resumed in 1996, progress in
expanding and rehabilitating the water supply works was relatively satisfactory. However,
progress in the implementation of the commercial, financial and administrative management
components was deficient and plagued by delays. Technical assistance provided by well-
known foreign consulting firms between 1996-1998 did not fully meet its objectives,
particularly in the commercial and human resources area.
Project Results
5. The project's physical objectives have been partially achieved. A well field was
constructed with seven productive wells, with a daily capacity of 19,760 cubic meters as
planned. Pumping stations and new reservoirs have been installed. Transmission pipes were
put in place and water mains were installed or rehabilitated. House connections increased by
4,600 since the project was reactived in 1995, which is below the 10,500 initial target. A
number of house connections have been disconnected due to non payment of bills by water
users or technical failures. Only 1, 000 water meters have been installed compared to 6,500
originally expected. A low percentage of existing meters is effectively working and/or read.
Population served has increased but water users served through legal connections represent
only about 18% of the total population against 25% ten years ago, reflecting among other
things the rapid increase in population of the Port-au-Prince Metropolitan area ( about 78%)
during the project period.
6. The unaccounted for water is estimated no less than 55%, which exceeds the already
high 50% average of the countries in Latin America. Other key performance indicators such
as water billings and connections remain unsatisfactory. Improvements in commercial and
financial management have been limited. There are still problems with water quality and
reliability. There is a serious leak problem, and the program of control of connections and
meters remains inadequate. The poor results achieved in the institutional performance of the
company (which was conceived as the project's most important objective, as confirmed by the
1998 Amendment to the Credit Agreement) outweigh the progress made on physical works,
leading to an overall "unsatisfactory" rating of the project. The financial rate of return is
estimated at -8.26% due mainly to the high rate of illegal connections and a collection rate of
approximately 80%. The economic rate of return is estimated at 7.08% compared to the
10.1% estimated during appraisal. The result of the economic rate of return reflects the
considerable differential between the prices charged by private vendors and that charged by
CAMEPI which are deemed closer to the real economic benefit.
IDA Performance
7. IDA's performance was unsatisfactory in identification, preparation and appraisal
phases of the project. The difficulties inherent in attempting to strengthen the water utility
over the five-year project period, given Haiti's subsequent history of instability and weak
institutional setting, were vastly underestimated. After the project was reactivated in 1995,
following a three year suspension of the credit, IDA staff enthusiasm proved short lived given
the deep seated problems in the water company and the slow progress achieved. A more
I CAMEP's prices of about US$ I/m
3
are estimated close to marginal cost, according to experience in other
regional utilities. Vendors charge about US$4/m
3
on average.
iv
fundamental restructuring of the project should have been undertaken following the lifting of
the suspension. Subsequent supervision efforts as well as technical assistance by reputable
international firms were not sufficient to solve the difficult issues encountered during the
implementation of this poorly designed problem project.
Borrower Performance
8. The overall performance of the Borrower was uneven. At the start of the project, the
entire management and cadres of CAMEP were fired and replaced by inexperienced staff.
CAMEP's performance was further impaired during the three-year suspension which
prevented the inflow of external resources that would have financed investments needed to
increase access to potable water and improve service. The relatively numerous changes in
personnel in the commercial and financial departments were detrimental at times.
Nevertheless, the working relationship between CAMEP and IDA staff was often good, and
the dialogue contributed to the timely resolution of a number of specific problems relating to
procurement, disbursements, institutional development and audits.
Assessment of Outcome
9. The project outcome is rated as unsatisfactory on the basis of the original project
objectives, even though physical objectives have been reasonably achieved and the rate of
project implementation attained represented a commendable outcome under the political and
social conditions existing in Haiti. The target relating to production capacity was met fully.
About 50% of the planned transmission mains were constructed. Two pumping stations were
constructed, as opposed to a single station expected during appraisal and 83 km of
distribution pipes were laid, instead of the 60 km planned. However, the number of house
connections amounted to only 2,580 or 50% of the new connections envisaged under the
project. CAMEP was in the process of planning a major push to expand house connections
during the visit of the ICR mission. Because of rationing, the estimated water consumption is
still 46% below the expected water demand, although illegal connections and other methods
of indirectly obtaining CAMEP's supply of potable water abound.
10. Unaccounted for water is high (55%). Only two-thirds of the bills are collected. The
collection period is 355 days. 2 Only about two-thirds of the bills are collected. The
collection period is 355 days partly as a result of CAMEP's reluctance to write-off its bad
debts because of its impact on operating profits. The ratio of collections to billings increased
from 51% in 1994 to an average of 77.5% between 1995-1999. CAMEP showed an
operating profit annually through out the entire 1995-1999 period, averaging about US$0.8
million. CAMEP also made a modest profit during this period except in 1998, when it
incurred a loss of about US$1 million. Nonetheless, CAMEP's profits are overstated because
it did not service the debts owed to the state. The average tariff level has been raised, but a
number of de facto structural distortions remains, due to the quasi absence of meters which
prevents the application of the tariff structure.
11. A positive outcome of the project has been the sharp increase in the number of people
served through stand pipes in low income neighborhoods. Only about 350,000 people, or
2 This is mainly caused by the need to provide sufficient quantities of water into the network, in order to avoid
negative pressures and hence contamination. Besides, there are many illegal connections and leaks.
v
18% of the population, are served through legal connections. Another 734,000 are estimated
to obtain potable water services either through neighbors or illegal connections. About
514,000 residents (up from nil in 1994) of low income areas are served through water kiosks
managed by water committees selected by the residents themselves, with the assistance of
NGO's. Despite the good progress in expanding the access to potable water during the ten-
year project implementation period, the overall outcome is still considered unsatisfactory.
This negative assessment is based on the levels of key performance indicators, linked to the
project's original objectives, which remain deficient. In addition, important institutional
objectives were not achieved in spite of the combined efforts of the project co-financiers,
international consultants and IDB's support for sector reform. Despite the achievements in
the physical aspects of the project, CAMEP can not be considered financially viable. The
bacteriological quality of the water being supplied by CAMEP continue to be mixed, though
considerably improved, and water rationing remains a fact of life in Port-au-Prince.
Furthermore, the hoped for reform of the sector, although within reach, has not materialized.
Summary of Findings, Future Operations and Key Lessons Learned
12. The failure to achieve institutional strengthening outweighs the reasonable physical
accomplishments, as it introduces great uncertainty in project sustainability. The present
administration and donor agencies support a major reorganization of the entire water supply
sector, in the hope that institutional weaknesses will be eliminated with a deeper involvement
of the private sector, by putting CAMEP under a management contract, which would be
subsequently followed by a concession.
13. Even with a management contract for a period of about five years, CAMEP will need
significant resources to finance the investments proposed in the new Port-au-Prince master
plan for potable water, which was prepared by an IDA-financed consultant. The needs of the
water sector in Port-au-Prince are enormous. Tentative projections for the period 2000-2005
indicate that investments required may amount to US$200 million. The bulk of this amount
would have to come from external donors including IDA. Beyond 2005, when a private
concessionaire would eventually take over, some of the investments could be financed by
such concessionaire, the remainder (substantially less than in the period up to 2005), would
be made available to support works that are needed, but which are not attractive to the private
sector (e.g. water supply in marginal areas, technical assistance, etc.). An alternative
approach would be to continue to support the above-mentioned community-based program of
water supply to low income sections in the Port-au-Prince area, where a fast growing
population lack water distribution networks, but is nonetheless increasingly being served
through water kiosks, managed by community groups with NGO support. This program has
already made a successful start and deserves to be continued with donor support. Its
decentralized management and focus on poverty alleviation would be in line with IDA's
overall development strategy for Haiti.
Key Lessons Learned
14. The project provided several important lessons for water supply operations.
* Early on in project preparation, consideration should have been given to private
sector management or ownership as an alternative to relying on the public sector.
vi
Institutional strengthening is a very difficult and time-consuming task. The role
of the private sector and the modalities for its involvement should have been
properly evaluated during project preparation. The option of introducing a
management contract, concession or affermage should have been studied as a
viable alternative before the project was approved. Even though this is now
evident and a law has been drafted to reform the sector and enhance the role of the
private sector, the law is presently stymied in Parliament.
Project design should be flexible to take advantage of unexpected developments
during project implementation. The project had originally envisaged the
construction and improvement of about 150 stand pipes to serve residents of low
income areas. During project implementation, CAMEP expanded this approach to
include the provision of bulk water to water kiosks that were managed by the
community with the assistance of NGOs. This approach turned out to be quite
successful, as it led to considerable savings in potable water expenditures and
fostered community self-help and participation in their own development .At
present over half million low-income residents are benefiting from this program.
They are among CAMEP's best paying customers, since they pay when they
receive service. This approach should be studied to determine its replicability in
other low income areas in Haiti and in similar situations in other countries.
* A careful assessment of the feasibility of institutional strengthening programs and
the establishment of realistic objectives in this regard should have been
undertaken from the onset. This is especially true in unstable political
environments where frequent government changes result in high staff turnover in
public sector institutions as well as frequent policy reversals. In situations where
a project supports a phased investment program, project performance indicators
should also be phased.
* Clear and realistic objectives and goals were not established prior the
commencement of project implementation. The two main objectives of the
project -extension of service coverage through physical works and institutional
development -were initially presented on the same footing. As project
implementation proceeded, the institutional development aspects of the project
began to lag behind the physical aspects. The IDA began to stress institutional
strengthening (which was reflected in amendments made to the project) and AFD
supported additional technical assistance. This re-orientation of emphasis was not
fully appreciated by the management and employees of CAMEP. This led to
misunderstandings and failures during implementation. Poor project design is
often very hard to correct during implementation.
* Close cooperation is necessary among co-financiers in order to achieve shared
objectives. Working in tandem would lead to more information sharing, and a
consensus on project performance targets. Given the gaps in potable water
services, all donors were concerned about water facilities network expansion;
however, there were divergent views on institutional matters, in particular with
regard to the role and timing of private sector involvement as well as on the
urgency for attaining institutional targets.
I....I .
IMPLEMENTATION COMPLETION REPORT
HAITI
PORT-AU-PRINCE WATER SUPPLY PROJECT
(Credit 2052-HA)
PART 1: PROJECT IMPLEMENTATION ASSESSMENT
A. Background
1. At the time of appraisal in 1988, water service levels for Port-au-Prince's 1 million
residents were very low and among the lowest in the Western Hemisphere. Only about 15%
of the population had a house connection; another 65% obtained water from a neighbor with
a house connection; about 5% relied on public stand pipes; and about 25% resorted to other
means such as cisterns, water vendors and natural surface-water sources. Water was severely
rationed and supply limited to less than six hours per day; many people received water no
more than two hours every other day. The water provided was generally unsafe and often
insufficiently disinfected. In addition, Port-au-Prince did not have a water-borne sewerage
system.
2. Given the lack of safe water and the poor sanitary conditions prevailing in the area,
diseases generally associated with unsafe water and poor sanitation ranked second among all
causes of mortality. Infant mortality, with a reported 77 deaths per 1,000 live births, remain
among the highest in the Western Hemisphere (compared to between 25 to 55 recorded in
other Latin American countries).
3. Two agencies are responsible for operating water supply facilities in Haiti: Centrale
Autonome Metropolitaine d'Eau Potable (CAMEP) for the Port-au-Prince area; and Service
National d'Eau Potable (SNEP) for the rest of the country. In 1978, SNEP received a US$6.6
million IDA Credit (747 -Ha) in support of an investment program including the expansion
and rehabilitation of water systems in seven provincial towns and institutional strengthening
of SNEP. The project was completed in 1984 with a 2.5 year delay. Objectives of the project
were achieved only partially. A Project Performance Audit Report (PPAR) issued in 1987
found that physical components were executed, but financial and institution-building goals
were not met. SNEP remained a very weak institution with chronic funding problems and
poor management, largely unable to operate and maintain the water supply facilities under its
responsibility. The PPAR concluded that in spite of the project's shortcomings and limited
achievements, there appeared to be no cause for doubt that it was justified, if only for social
and health reasons.
4. One very important and perhaps overriding factor for the sector's limited potential for
revenue generation and CAMEP/SNEP water performance was without doubt the high
proportion of the Haitian population below the poverty line, currently estimated at over 65%.
IDA had a long-standing strategy of providing assistance to Haiti through lending operations
in the social sector with a strong impact on improving the living conditions- of the poor.
2
Support to the water sector matched closely the IDA strategy, as the improvement of water
services to the inhabitants of Port-au-Prince would meet the social aspects of this strategy. It
was also hoped that assistance to CAMEP would promote more efficiency in the operation of
an important public enterprise, and the introduction of more appropriate cost recovery
policies would ease the government's need to provide operating subsidies. On these grounds,
an IDA credit supporting a Port-au-Prince water supply project was approved in June 1989.
B. Project Objectives
5. The project, to be executed during 1989-1994, was to support the execution of the
first phase of a 1988-1998 investment program proposed by consultants in the Port-au-Prince
Water Supply master plan.
6. The original Government request was for IDA assistance to improve water services in
the Port-au-Prince Metropolitan area and strengthen the institutional capabilities of Centrale
Autonome Metropolitaine d'Eau Potable (CAMEP). The specific project objectives were to:
(a) develop CAMEP into an operationally and administratively efficient and financially
viable water utility; (b) improve and expand water services in the project area; (c) execute a
first stage investment program to rehabilitate existing water supply infrastructure; (d)
formulate a concrete plan for improving the sanitary conditions in Port-au-Prince; and (e)
attain the Government agreement on a strategy and a plan of action for achieving more
dynamic and efficient water sector. These objectives were addressed by three project
components: expansion of the water supply system through infrastructure investments,
institutional development, and technical assistance and studies.
7. The detailed Project components were as follows:
* Infrastructure Investments
a. Water Supply Infrastructure consisting of:
(i) construction of a well field with an average daily capacity of
about 20,000 cubic meters/day and connection of the well field
to the water transmission system at the reservoir known as
R120 including: construction of six wells, installation of
pumps, electrical power lines, and pressure pipes (10
kilometers);
(ii) replacement/construction of transmission mains conveying
water from existing sources to the transmission system.
b. Expansion and Rehabilitation of water transmission, pumping and storage
infrastructure consisting of:
(i) construction of about 50 kilometers of transmission mains (200
to 800 millimeters diameter).
(ii) construction of three storage reservoirs with an aggregate
capacity of about 5,000 cubic meters (R120, Gentil and
Madame Baptiste).
3
(iii) construction of a pumping station (200 cubic meters/hour).
(iv) installation of monitoring and regulating equipment of CAMEP
water systems.
c. Distribution Network and Connections
(i) construction of about 60 kilometers of water distribution pipes
(less than 100 millimeters).
(ii) installation of about 5,000 new and the rehabilitation of about
5,500 existing connections.
(iii) installation of about 2,500 water meters.
(iv) installation of about 2,600 flow limiting devices.
(v) construction of 100 new and improvement of 50 public
stand pipes.
(vi) installation of about 50 fire hydrants.
d. Construction of an Operations Building.
* Institutional Development of CAMEP
(i) acquisition of equipment, including vehicles and tools, required for
maintenance and operation of CAMEP water supply facilities.
(ii) carrying out a program of technical assistance and training to promote
the development of management capabilities within CAMEP.
* Technical Assistance and Studies
Provision of technical assistance for:
(i) supervising and engineering of the works included in the Project.
(ii) studies for purposes of developing and designing a follow up project
including final designs and specifications.
(iii) studies for the purpose of preparing a plan to improve sanitation and
waste disposal facilities and services in the Project Area.
C. Achievement of Project Objectives
8. The objective of expanding the water supply infrastructure has been relatively well
achieved despite continued shortcomings at the distribution level. While physical
achievements were relatively satisfactory, the project objectives related to institutional
strengthening were unsatisfactory. Key performance indicators on the basis of the original
project design (unaccounted for water, water billings and collections) were not attained.
Total project cost is calculated at US$35.6 million of which US$20.5 million were drawn
from IDA funds, US$12.9 million from Agence Francaise de Developpement (AFD) and the
Government loan and US$2 million from the OPEC Fund. CAMEP contribution was
minimal, at US$0.3 million. This amount is nearly identical to the appraisal estimate of US$
35.5 million. However, funds allocated to CAMEP institutional development and technical
4
assistance were 50% higher than anticipated (US$6.6 million instead of US$4.4 million) due
to the need to address deficiencies in CAMEP performance which were exacerbated by the 3-
year suspension due to the coup d'etat.
9. An economic ex-post evaluation was carried out, using incremental revenues
generated by the investments and the price paid for water delivered by water vendors as a
proxy for CAMEP's customers' willingness-to-pay. However, to take into account the
increase in quantity demanded due to CAMEP's lower price, it was assumed that the quantity
purchased by CAMEP's customers prior to the switch in supply, represents only about one-
tenth of their current purchases from CAMEP. On the cost side, it includes investments
carried out for expansion and rehabilitation of the water supply system (IDA, French AFD,
OPEC) as well as incremental operating costs. Expenditures related to operations
improvement and technical assistance were also included to the extent they represented
actions taken to improve water supply investment productivity. On the benefit side,
incremental revenues generated from tariffs together with connection fees, as well as
consumer surplus brought about by savings due to the differential between the average
vendor price (Gds. 132/m3) and CAMEP's tariffs or final price to Kiosk customers (Gds.
15.8/m3). The internal economic rate of return (IERR) of the project was estimated at 16%,
taking the revenues and savings by kiosk customers and CAMEP's regular customers. If
only the savings of CAMEP's regular customers are taken into account, the IERR drops to
14%. If only the savings of the kiosk customers are taken into account the IERR drops
further to 4%. The financial internal rate of return (IRR) was estimated at -1.4%.
10. Project completion was delayed because of political problems that resulted in the 3-
year suspension of the project between October 1991 and 1994. The suspension was lifted in
December 1994 and the project was amended on December 7, 1995 to adapt it to the post-
embargo environmentl. Investments carried out in 1991-93 by the French AFD were modest,
totaling US$0.8 million and consisting of studies and some drilling activities. IDA did not
disburse any amount before 19962. No operating costs nor benefits were obtained by the
project before and during the suspension period and the financial and economic evaluation
was thus carried out for the period starting in 1995.
11. The result of the economic evaluation appears reasonable. However, the project is
clearly not financially viable. The negative financial return is explained by much lower
demand than anticipated
3
, and to the delay in upgrading the commercial system, a process
that is still underway. In addition, the high proportion of illegal connection and "customers"
obtaining service from their neighbors (about 46% of total) has meant that CAMEP could
only charge for less than half the water produced. Unaccounted for water
4
was about 55% in
1998, the level of accounts receivable measured in number of days of billing rose from 216 at
appraisal in 1989 to 355 in 1999 and the ratio of collections to billings ranged from 51% in
1 The Amendment to the Credit Agreement reflected the Bank's efforts to help the Government of Haiti and
CAMEP in gaining flexibility for project execution.
2 Except for a PPF (US$837,000) disbursed in 1990/91.
3 Estimated annual water consumption was 24.5 million cubic meters in 1995 compared to 39.7 million
anticipated at appraisal. Consumption remained at that level until 1998.
4 Technical and administrative losses. Technical losses are caused by poor pipe connections, faulty water meters
and broken pipes.
5
1994 to 77% in 1999, with a high of 84% in 1996. Despite the high proportion of illegal
customers, CAMEP was able to cover its operating costs fully, following the lifting of the
suspension. Nevertheless, although CAMEP did show positive net income during the project
period except for 1998, actual net income was negative because CAMEP was not able to
service its debts to the state. Considerable wastage occurs as a result of a lack of meters and
the flat rate billing system for consumption. The working ratio
5
has in fact increased from
71% in 1995 to 76.7% in 1999, whereas it was assumed to decrease by half between appraisal
and project completion. These project outcomes support the overall unsatisfactory rating
given to the project.
12. It became evident in 1998 that the project, as originally designed would not be able to
meet its original development objectives. The key problematical objective called for
transforming CAMEP into an operationally and administratively efficient and financially
viable utility. CAMEP was not financially viable nor was it expected to become so before
the project closing date of June 30, 1999. Other original development objectives that were
not expected to be attained were: (i) improving the bacteriological quality of the water being
supplied by CAMEP; (ii) eliminating severe rationing; and (iii) attaining agreement on a
strategy and a plan for achieving a more dynamic water sector. The principal cause for the
failure to attain these project development objectives was the three year suspension of the
projects in Haiti. As a result of the hiatus, project implementation fell behind as CAMEP's
network deteriorated due to lack of maintenance. Given the institutional development
constraints, the objectives of the project were simplified
6
in order to bring them in line with
the skills available in Haiti. Care was taken to reorient the project emphasis toward the
institutional development of CAMEP as opposed to stressing only physical implementation.
Physical Implementation.
13. Implementation of the infrastructure components was generally satisfactory, despite
intermittent delays. After substantial initial problems, procurement went relatively smoothly.
The supply and installation of some transmission and distribution pipes had to be re-tendered
because all the offers received exceeded the project budget. The construction of the
operation building was delayed because the firm that originally won the contract went
bankrupt as a result of the embargo that was imposed following the overthrow of President
Aristide. Improvement in operations has taken place and include an increase in water
production and an expansion of transmission and distribution pipes network.
A. Water Supply Infrastructure
(i) Construction of a well field at Tapage Galette: production capacity
reached 19,760 cubic meters as planned. Eight wells (as opposed to 6
planned) with a depth of about 120 meters have been drilled of which
seven are productive. Pumps and related hydraulic and electrical
equipment have been installed. An electric power line of 4 kilometers
(against 11 km planned because the circuit was modified) has been
constructed. About 20 kilometers of pressure pipes (against 10
S Ratio of operating costs to operating revenue.
6 The Development Credit and Project Agreement were formally amended on December 21, 1998.
6
kilometers planned) with diameters ranging from 200 millimeters to
800 millimeters have been installed. Accelerated urbanization in the
Port-au-Prince area led to the expansion of the pressure pipes network
and to changes in the original plan for transferring water to reservoirs.
(ii) Transfer of water from existing sources to the transmission system.
Water was to be transferred from seven existing springs and one new
source (Gentil Spring). The Gentil Spring was not developed due to
excessive price claimed by the landowner. Work was undertaken on
only four sources leading to the replacement of 5.6 kilometers of
transmission mains instead of the 11.2 kilometers planned. It appears
that the reallocation of funds to other priority tasks, led to the decision
not to replace some existing pipes considered as still in working
condition.
B. Expansion and Rehabilitation of Water Transmission, Pumps and Storage
Distribution
Construction/rehabilitation of 19.3 kilometers of transmission mains was undertaken
compared to 40 kilometers originally planned. The number of storage reservoirs to be
constructed/expanded was reduced from three to two but with an identical combined
capacity of 5,000 cubic meters. Due to the cancellation of the Gentil Reservoir
component (since the Gentil Spring could not be developed), and of the Mrs. Baptiste
Reservoir in the same area, the works plan was modified: an additional water tank was
put in place at the Christ-Roi Reservoir; a pumping station was installed at the Nazon
Reservoir site; an additional water mains was installed between the Bourdon and
Nazon existing reservoirs; and the distribution network around the new Reservoir
R120 was extended, with a new pumping station installed at the Freres 1 Reservoir.
The result was to facilitate the "sectorisation" of water distribution, allocating specific
springs and reservoirs to particular urban sectors, thus ensuring better control of
distribution and consumption.
C. Distribution Network and Connections.
About 80 kilometers (as compared to 60 km planned) of distribution pipelines with a
diameter of less than 200 mm were constructed. The number of new and rehabilitated
water connections was less than originally planned, due to difficulties in reaching
some overbuilt areas but mainly due to the reluctance of potential customers to pay
3,400 gourdes (US$200) connection charge, which is a sizable sum for low income
people. About 3,600 new meters were purchased in May 1999 by CAMEP but only
1,000 have been installed (compared to 2,500 water meters planned). Present tariffs
discourage the use of meters, particularly since water is still severely rationed in a
number of areas. Flow limiting devices have been abandoned (2,600 were planned)
due to improper use of such devices by users. Only 14 fire hydrants have been
installed in new sections instead of 50 planned.
14. While the project's original objectives were only partially achieved in the distribution
field, highly satisfactory results were obtained regarding the installation of public fountains
in Port-au-Prince poor districts and slums. CAMEP support of a potable water supply
7
program initiated by a French NGO
7
in 1994 led to a significant improvement in the service
to low income areas that were being served by private vendors using water trucks. The
program initially encompassed 14 districts with about 210,000 inhabitants. Currently about
514,000 customers are served under the program. This program consists of the construction
of water kiosks inside the shanty towns. CAMEP provides the bulk water but the
management, operations and maintenance of the kiosks are undertaken by water committees,
elected by beneficiaries. The water is sold by attendants employed by the water committees.
Even though water is sold by containers, the price to users (US$1 per cubic meter) is not
negligible for the poorest families, but affordable for the majority of families, who previously
had to purchase water from water trucks at 2 to 3 times the price. The revenues generated are
sufficient to cover all expenses of the local organizations, including the payment of water to
CAMEP, the maintenance and some revenue left for investment in small collective
infrastructures (especially in sanitation).
15. About 20 km of pipes have been installed, providing water to 60 fountains. In 1998,
it was estimated that 50 more stand pipes and 500 homes were connected to the system. This
program was financed in 1994-1998 by the European Union and the French Agency for
Development (AFD). In 1998-1999, AFD also financed installation of stand pipes supplied
by CAMEP in 13 other districts. At these stand pipes water is also sold by the container (at a
price roughly equivalent to about US$1/m3). Total population in these 27 districts totaled
500,000 people, i.e. about 25% of the almost 2 million population living in the Port-au-Prince
area. Although it entails an extension of the original scope of the project, the positive results
obtained by the public stand pipes program have compensated to a significant extent (from a
social view point mainly) for the relatively modest results achieved by CAMEP in the
distribution field. Besides, these customers have evolved to be among CAMEP's best paying
customers, since they pay at the time that service is provided.
Institutional Development of CAMEP
(a) Acquisition and utilization of equipment
16. Equipment, including vehicles and tools, was purchased for maintenance and
operations of CAMEP facilities, including the works included in the project. The amount
spent on trucks and pickups was US$604,000 while equipment purchased was valued at
US$2,797,000
8
.The largest item was equipment for the rehabilitation and construction of
10,000 connections supplied in July 1998 for US$1,029,000. Other big items included
equipment for repairing leaks (US$418,000), macro and micro meters (US$121,000), water
pipes 12" to 1/2" (US$411,000) and electronic and computers equipment (US$391,000).
Actual payment of US$3.4 million was thus 3.5 times higher than the US$1 million estimated
at appraisal. This substantial deviation is an indication of the extent of the work required for
maintenance and repair of a water network in extremely poor condition.
7 GRET (Groupe de Recherche et d'Echanges Technologiques).
8 Excluding US$622,000 for regulating equipment to maintain water pressure included under water transmission
infrastructure investments.
8
(b) Development of CAMEP's management capabilities
17. At the time of appraisal, CAMEP was an inefficient water utility. It had made some
progress towards improving its operational efficiency with the assistance of French
consultants under a French Agency for Development (AFD) Emergency Program and an IDA
PPF (US$764,000) but had a long way to go for achieving levels comparable to the Latin
American average
9
.IDA consequently accorded the utmost priority to assisting CAMEP in
its efforts to become a viable entity. Monitoring indicators were set at appraisal (and revised
downwards in 1998 when it became clear that the original objectives were not achievable).
18. Technical assistance was provided by AFD. A detailed and useful organizational and
management study was performed in 1995/1996 by a French water company (Lyonnaise) at a
cost of US$535,000. Some training was provided for CAMEP staff in France. It was
immediately followed in 1997/98 by the arrival of a team seconded by another French
company (Compagnie Generale des Eaux, CGE). They worked inside CAMEP on such
issues as reporting, accounting, budgeting, financial planning, electronic data processing.
Total cost of this assistance was US$1.42 million. Unfortunately it appears that poor working
relationship between CAMEP staff and CGE personnel substantially reduced the transfer of
expertise and the efficiency of the technical assistance. The local staff had the impression
that the management of CAMEP would be on its way out, with the possibility of a deeper
private sector involvement in CAMEP. This view led to the resentment of the CGE experts.
The outcome was thus relatively unsatisfactory. At present the principal problems remain: a
lack of a viable customer billing and accounting system and adequate information on the
customer data basel; poor management of accounts receivable; treatment of debt service
payments due to the state; ad hoc change to journal entries; and lack of an updated fixed asset
register.
Technical Assistance and Studies
(a) Supervising and engineering of the work included in the Project
19. Another French consulting firm (SAFEGE) was selected in 1991 to assist CAMEP in
preparing a detailed work program and supervise submission of bids and signing of contracts.
In 1995, SAFEGE was again selected to help CAMEP to reactivate the project, after the
embargo was suspended. It revised project costs, analyzed bids and generally supervised the
execution of work. Total SAFEGE assistance amounted to US$3.26 million over the years
1991 and 1995-1998 and was entirely financed by AFD. SAFEGE's performance has
generally been considered satisfactory under difficult conditions.
(b) Follow-up project
20. A Belgian consulting firm (TRACTEBEL) was selected to carry out a Potable Water
Investment Program covering the period 2000-2015 with detailed project costs estimates and
9 For instance, 20 staff per 1,000 water connections against 6-10 in Latin America. Also 4% of university
graduates at CAMEP compared to 8%-15% in Latin America.
10 Although some progress has been recently made following a census of water customers conducted by a
consultant financed by IDA.
9
plan of action up to 2005 for the Port-au-Prince Metropolitan area. The consultant's Master
Plan submitted in November 1998 recommended accelerated rehabilitation efforts in order to
reduce technical losses; installation of meters and improved management to reduce
unaccounted for water ( estimated at 55%); and an increase in the water rates in order to
moderate over consumption. The cost of the study (financed by IDA instead of AFD as
originally planned) was US$826,000.
(c) Sanitation Master Plan
21. IDA supported the preparation of a Sanitation Master Plan for the Port-au-Prince area,
undertaken by consultants (a French/Canadian/Haitian consortium) at a cost of $398,000 in
1998/99. The Plan provided an excellent diagnosis and made detailed recommendations
although a financially viable strategy remains to be developed to address the enormous needs,
via a demand responsive approach.
(d) Census of CAMEP customers
22. At appraisal a census of customers was not formally included in the Project but was
definitely considered useful since the lack of data on effective users was one major source for
under-billings and non payment by customers. A French consultant (CGE) was selected to
carry such a census based on 50,000 "fiches" and on that basis water users (regular or
potential) were located through an aerial photo system. CGE was supposed to install
software to manage the "fiches" and to train CAMEP staff in its use, in order to enable
CAMEP to survey other areas and to undertake future updates of the customer data base. The
census was completed in July 1998 and is now being continued by CAMEP trained staff.
The census was conducted in 1997/98 at a cost of about US$1 million, financed by IDA.
D. Major Factors Affecting the Project
23. Credit 2052-HA was approved on June 27, 1989, and became effective on February
1990, seven months after Board approval. Only a few month later, CAMEP faced significant
problems in its organization, finances and operations. The Government replaced CAMEP's
Director General and all department heads. The previous team had been able to initiate a
number of positive changes in CAMEP's organization. Their departure was motivated by a
strike of CAMEP staff opposed to the company's improved efficiency. Under the new
management, CAMEP's administrative operations were not coherent and communications at
all levels were inadequate. The new Director General fired the company's external auditors
aggravating the situation and delaying the preparation of the audit report. In addition to the
time lost due to these changes, the project fell behind schedule due to delays in the
procurement of major civil works contract. The lowest bid for a large water supply system
and distribution networks was about 2.4 times the engineer's estimate at appraisal and funds
were not available under the Credit to cover the cost overrun. New bids were sought, but it
took a considerable time to re-tender.
24. Along with all other ongoing IDA credits to Haiti, the Credit for the water supply
project was suspended in October 1991, following the coup d'6tat that ousted president
Aristide. At that time US$0.736 million of the original US$20 million had been disbursed,
which represented mainly the refinancing of the PPF. The French AFD had spent US$0.309
10
million on wells drilling operation out of an original US$9.5 million loan. The suspension
was lifted in December 1994, i.e. more than three years later, after President Aristide's return
to power, and the project was amended on December 7, 1995 to adapt it to the post-embargo
environment.
25. The closing date was extended to June 30, 1999. A special account (US$750,000)
was established in the Central Bank to facilitate disbursements after the project was
reactivated in 1995. A major concern was also the non availability of counterpart funds
promised by the Haitian authorities for the project. The financing plan presented in the 1989
SAR included US$6 million of counterpart financing (including interest) of project costs
from the Government. Counterpart financing was immediately needed in 1995 to cover 20%
of the works being launched (contracts for a total of approximately US$5.1 million, i.e.
US$1.02 million for the Government). To help solve this issue, additional funding was
provided by the OPEC Fund for International Development to the Government, amounting to
US$2.05 million, to cover a portion of its counterpart financing needs. This loan, originally
made in 1990, was confirmed in 1995.
26. At the end of the embargo (end 1994), CAMEP was financially bankrupt. The Board
of Directors had never met, showing thus an absence of policy guidance and control: there
was no finalized balance sheet (only a trial balance at the end of September); there was a lack
of a management information system; the bulk of the accounting transactions was recorded
manually; no annual budget was prepared: most of the clients were government state or local
entities who never paid; the amount of stocks appearing in the balance sheet was unreliable,
etc. With project reactivation, the three principals in the Finance/Accounting Department -
who had not performed well -were replaced by two more competent professionals and an
Institutional Strengthening Study financed by AFD began in 1995.
27. By end 1996, the project's physical implementation appeared to be on track, with the
exception of the distribution network. Water wells, reservoirs and transmission pipes were
being fabricated and installed despite the political uncertainty during this period. However
CAMEP, although slowly progressing, remained a weak institution, particularly in the field
of finance and commercial operations, lacking customer orientation. Significantly, CAMEP's
management agreed to turn over, in the future, the management of the distribution systems to
a private firm under an affermage arrangement. In July 1996, a Unit for the Reform of the
potable water sector (URSEP) was put in place by the Government with IDB financing:
URSEP prepared in July 1997 a draft law for reforming the Potable Water and Sanitation
Sector and which was submitted to Parliament by the Ministry of Public Works. However
the law could not be considered because of the absence of a Prime Minister, the Head of
Government under Haiti's constitution. When a Prime Minister was finally approved by the
Senate, the Government was thrown into yet another crisis when disagreement over the
outcome of provisional elections led to a boycott and subsequent suspension of the
Parliament by the President. So far the law and an IDB loan (US$45 million) linked to its
passage continue to languish in the Parliament. The Government attempted to pursue other
modalities ( through the Conseil de Modernisation des Entreprises Publiques ) for involving
the private sector in CAMEP's operations prior to the ratification of the reform law by the
Parliament. This attempt was not successful.
11
28. Given the continuing slow institutional development of CAMEP, the Government and
CAMEP agreed by end 1998 that the objectives had to be simplified to bring them in line
with the skills available in Haitill. They also agreed that the project objectives should
include a clear role for the private sector in managing CAMEP's operations in the future. The
emerging consensus was that the private sector would be brought in under a management
contract for a period of 5 years or so, and during the last year of the management contract,
proposals would be sought for a deeper private sector involvement, such as a concession or
affermage. However the Conseil de Modernisation des Entreprises Publiques (CMEP) in
charge of the privatization program had no budget or funding source to pay for the
preparation of bidding documents in order to solicit proposals for the management contract.
So far the issue of involvement of the private sector has thus not been solved, which has a
direct impact on CAMEP's management and operations. Had the efforts to enhance the role
of the private sector in CAMEP's operations been successful, it is conceivable that the
project closing date might have been extended.
E. Project Sustainability
29. The failure to achieve institutional strengthening outweighs the reasonably good
physical accomplishments as it introduces great uncertainty concerning project sustainability.
In addition sustainability is undermined by the fact that only 345,000 customers are served
directly through house connections, with an additional 514,000 through stand pipes and
kiosks, while the majority of CAMEP's customers (734,000) obtain their water either
illegally or through neighbors. The present administration and donor agencies support a
major reorganization of the entire potable water sector in the hope that institutional
weaknesses will be eliminated by a reform of the sector and private concessionaire for
CAMEP, thus enhancing project sustainability.
30. When CMEP was attempting to accelerate the institutional reform of CAMEP, CMEP
requested the services of a consultant to review the options for private sector involvement.
The consultant recommended in February 1999 that the private sector be brought in under a
management contract for a period of 5 years or so and after this period proposals would be
sought for a deeper private sector involvement, such as concession or affermage. The
consultant's recommendations appear to have been accepted by CMEP
12
.However, further
work could not proceed because of budgetary constraints. At this stage, the consensus among
the donors is that the 1997 water sector legislation should be approved by Parliament
(elections are scheduled for March/April 2000) and that the privatization of the CAMEP
operations (at least in the first phase of a management contract) should be well under way
before additional external resources should be provided to the sector.
31. To the extent that a management contract would provide for operations and
maintenance as well as supervision of new/rehabilitation investments up to 2006, CAMEP
I1 Agreement was also reached on a limited number of performance indicators (physical, financial, institutional
on which to assess future project implementation progress).
12 A three-year contract would be given through a management contract (instead of five years) with a part of the
contractor's revenues fully guaranteed and another part linked to performance (reduced water losses, better
billings, etc.)
12
will need to find financial resources to fund investments proposed in the new Port-au-Prince
master plan for potable water (TRACTEBEL study). A US$45 million loan has already been
approved by the IDB, but access to the IDB loan is contingent on the passage of the water
sector reform law by the Parliament. The law also entails a merger of SNEP with CAMEP.
Presumably other donors will likely follow IDB's lead and provide assistance to the sector
only if the law is enacted and the reforms are implemented. Until a clear timetable is
available regarding the privatization process and a new management system is put in place,
CAMEP's future and project sustainability would remain uncertain.
32. The current needs in the sector in Port-au-Prince are enormous, including sewerage,
storm water drainage and wastewater treatment systems. The main purpose of any future
project would focus on investments that would not be the responsibility of a new private
operator, particularly during the management contract phase. This financing (which would
include a technical assistance component in setting up the regulatory framework) would help
make the water (and sewerage) investment program feasible and help ensure the transition to
a future concessionl
3
.Such assistance would definitely increase project sustainability.
Furthermore, any IDA involvement in the potable water sector in Haiti should include further
support for the extension of potable water service to low income residents utilizing kiosks
and stand pipes managed by water committees with the support of NGOs.
F. IDA Performance
33. The IDA's performance was unsatisfactory in preparation and appraisal phase of the
project to the extent that: (i) lessons leamed from the previous project with SNEP which
indicated that physical components were executed but financial and institutions building
goals had not been met, were not taken into account in designing the CAMEP project; (ii) the
performance targets for CAMEP were overly ambitious given the unstable political
environment, and limited human resources capabilities; and (iii) the difficulty in
implementing institutional reforms was considerably underestimated.
34. IDA staff originally supported a much more ambitious investment program which
would have provided more adequate means for dealing with the enormous problems resulting
from the disastrous Port-au-Prince water supply situation. However a much scaled down
program was finally decided upon because of doubts on CAMEP's ability to implement the
project and doubts showed by the French cofinancier. Nevertheless, the reduced program
was not accompanied by a tight institutional building program required under the
circumstances then prevailing.
35. The company management was inclined to put emphasis on physical investments,
given the severe operational constraints and the extent of network deterioration, while
according a lower priority to the negotiated reforms. When the project was reactived in 1995
after the embargo was lifted, disbursements had been considerably delayed, and in order to
make up for lost time, the IDA and the French AFD decided to restart the project as originally
conceived which proved not to be realistic. The stress was put on investments (need to
achieve implementation targets for infrastructure). This attitude was exemplified by the
13 After an initial five year management contract.
13
French co-financier, insisting on the need to "push the works", which was understandable,
given the low level of service following the reactivation of the project.
36. As regards institutional strengthening, the IDA became increasingly concerned with
lack of progress, particularly in 1996-1998. However the entire technical assistance program
was financed exclusively by the French and remained AFD's prerogative. As a result, there
was relatively little coordination between IDA and AFD staff and unfortunately technical
assistance to CAMEP did not prove very effective. In addition, there was a lack of trust
which adversely affected the effectiveness of a significant portion of the technical assistance
program.
37. The project was based on a five year implementation schedule. The technical
assistance was supposedly tied to a specific plan of action to strengthen CAMEP's
management and operations. All this fell apart in 1991 when the project which had a slow
start to begin with, was abruptly suspended as the result of the embargo. The enthusiasm
with which the IDA reactived the project in 1995 proved short lived because of the lack of
progress in solving CAMEP's persistent problems, problems which, with the benefit of
hindsight, had been considerably underestimated and had been exacerbated by the 3-year
hiatus brought on by the suspension. A more fundamental restructuring of the project should
have been undertaken following the lifting of the suspension.
38. IDA's project preparation, involving about 95 staff weeks, was relatively intense.
Project supervision amounted to about 124 staff weeks and the project was at most time
adequately staffed. These were four task managers. The last IDA task manager supervised
the project for three years (from May 1996 to present), thus providing continuity. Many of
the issues related to the physical implementation of the project entailed procurement and they
were satisfactorily addressed. With respect to the institutional aspects, assistance was
provided in setting up the internal auditing unit in strengthening CAMEP's management
information system and in addressing some of the internal control issues that were raised
during external audits. Nonetheless, this period was marked with persistent deep rooted
problems which finally led the staff to rate the project as unsatisfactory in April 1998.
G. Borrower Performance
39. The overall performance of the Borrower was uneven. At the start of the project, the
entire management and cadres of CAMEP were fired and replaced by inexperienced staff.
CAMEP's performance was further impaired during the three-year suspension which
prevented the inflow of external resources that would have financed investments needed to
increase access to potable water and improve service. The relatively numerous changes in
personnel in the commercial and financial departments were detrimental at times. The
situation settled down when the current Director General took over for the second time in
1995. He has been in place now for several years, and has put in place a coherent
management team.
40. On a number of occasions CAMEP's staff and consultants produced good data and
information to review and analyze. Working relationship with IDA staff was often good, and
an effective dialogue during supervision between IDA staff and borrower contributed to
timely resolution of a number of specific problems (procurement, disbursements, institutional
14
development and audits). However, in the area of covenant compliance, specifically as it
related to financial issues, the Borrower performance is considered to have been lacking. The
overall Borrower's rating is unsatisfactory.
H. Assessment of Outcome
41. The project outcome based on the original project objectives is rated as unsatisfactory.
Credit 2052-HA's original development objectives aimed at increasing water service coverage
to 93% and at strengthening the company into a solid and financially viable institution. The
project's physical objectives have been reasonably achieved with planned works virtually
completed. The installation of meters and house connections is however below the initial
targets and water coverage is also below the initial target. But about 500,000 people in
disadvantaged sections of the Port-au-Prince area are now being supplied through kiosks and
stand pipes. This success story has contributed to the considerable favorable social impact of
the project and ameliorated the lack of progress in investments in distributing facilities and
individual house connections. Through collaboration with an NGO, CAMEP was able to
contribute to developing a cost effective method for providing potable water services to the
poor in its service area.
42. In contrast, one of the main original institutional objective, of transforming CAMEP
into a financially viable water utility, was not achieved and had to be abandoned during the
project restructuring. Despite recent improvements, CAMEP's performance has remained
modest. Unaccounted for water, is at least 55%14. Only about two-thirds of the bills are
collected. The collection period is 355 days, since CAMEP is reluctant to write-off its bad
debts because of its impact on operating profits. The ratio of collections to billings increased
from 51% in 1994 to an average of 77.5% between 1995-1999. CAMEP showed an
operating profit through the entire 1995-1999 period averaging about US$0.8 million.
CAMEP also made a modest profit during this period except in 1998, when it incurred a loss
of about US$1 million due to high administrative costs brought on by its sectorization
program and a 90% increase in depreciation charges. Nonetheless, CAMEP's profits are
overstated because it did not service the debts owed to the state. On the other hand, the state
made practically no transfers to CAMEP during the project, except for US$ 74,000 provided
to CAMEP for the purchase of land. The number of employees per thousand connections
remained high, although it registered a slight decline from 14.4 in 1995 to 12.6 in 1999. The
average tariff has been raised but, due to the small number of metered connections, water
supplied through private connections is paid on the basis of estimated consumption at low
prices.
43. Potable water is now used by a higher number of the city's poorer residents. However
the proportion of consumers directly served through connections has actually decreased in the
last decade compared to the total population of the Port-au-Prince metropolitan area (now
almost 2 million people). Despite some progress in the ten-year period of implementation,
there is still considerable way to go before CAMEP is transformed to a financially viable
water utility which was central to the project.
14 This is mainly caused by the need to provide sufficient quantities of water into the network, in order to avoid
negative pressures and hence contamination. Besides, there are many illegal connections and leaks.
15
I. Future Operations
44. The proper operations and maintenance of project financed facilities is linked to the
privatization process and continued donor support. Without the passing of the sector reform
law and the introduction of the private sector, the future of IDA facilities would largely
depend on the availability of internally generated funds by CAMEP. Despite uncertainties
regarding project sustainability linked to the privatization process and to a future private
management contractor decisions regarding future operation, the needs in the sector in Port-
au-Prince remain enormous. Tentative projections for the period 1999-2005 indicate that
investments may be required for US$200 million. During the management contract period
(no investment being made by the contractor) and in the absence of meaningful possible
contribution by CAMEP and/or the Haitian authorities, the bulk of this amount would have to
come from external donors. Beyond 2005, when a private concessionaire would eventually
take over, some of the investments would be financed by such concessionaire, the remainder
(substantially reduced compared to the period up to 2005) being made available to support
works needed but not attractive to the private sector (water supply in marginal areas, flood
control and technical assistance).
45 Any future operations in the potable water sector involving IDA should consider
continued support for the improvement of access to potable water in low income areas
managed by water committees elected by the communities themselves. The committees are
elected for a fixed term during which they manage the water kiosk on behalf of the
community. The price charged is sufficient to cover the price of bulk water and to pay the
attendant, with funds left over for small community projects. The communities are assisted
by an NGO at least through one election to change members of the committee. Such support
will be consistent with IDA's strategy of providing assistance to Haiti through lending
operations aimed at improving the living conditions of the poor. It will also support good
governance and self- help among the poor.
J. Summary of Findings and Key Lessons Learned
46. The main lessons learned from this project can be summarized as follows:
* Early on in project preparation, consideration should have been given to private sector
management or ownership as an alternative to relying on the public sector.
Institutional strengthening is a very difficult and time-consuming task. The role of
the private sector and the modalities for its involvement should have been properly
evaluated during project preparation. The option of introducing a management
contract, concession or affermage should have been studied as a viable alternative
before the project was approved. Even though this is now evident and a law has been
drafted to reform the sector and enhance the role of the private sector, the law is
presently stymied in Parliament.
* Project design should be flexible to take advantage of unexpected developments
during project implementation. The project had originally envisaged the construction
and improvement of about 150 stand pipes to serve residents of low income areas.
During project implementation, CAMEP expanded this approach to include the
provision of bulk water to water kiosks that were managed by the community with the
16
assistance of NGOs. This approach turned out to be quite successful, as it led to
considerable savings in potable water expenditures and fostered community self-help
and participation in their own development. At present over half million low-income
residents are benefiting from this program. They are among CAMEP's best paying
customers, since they pay when they receive service. This approach should be studied
to determine its replicability in other low income areas in Haiti and in similar
situations in other countries.
* A careful assessment of the feasibility of institutional strengthening programs and the
establishment of realistic objectives in this regard should have been undertaken from
the onset. This is especially true in unstable political environments where frequent
government changes result in high staff turnover in public sector institutions as well
as frequent policy reversals. In situations where a project supports a phased
investment program, project performance indicators should also be phased.
* Clear and realistic objectives and goals were not established prior the commencement
of project implementation. The two main objectives of the project -extension of
service coverage through physical works and institutional development -were initially
presented on the same footing. As project implementation proceeded, the institutional
development aspects of the project began to lag behind the physical aspects. The IDA
began to stress institutional strengthening (which was reflected in amendments made
to the project) and AFD supported additional technical assistance. This re-orientation
of emphasis was not fully appreciated by the management and employees of CAMEP.
This led to misunderstandings and failures during implementation. Poor project
design is often very hard to correct during implementation.
* Close cooperation is necessary among co-financiers in order to achieve shared
objectives. Working in tandem would lead to more information sharing, and a
consensus on project performance targets. Given the gaps in potable water services,
all donors were concerned about water facilities network expansion; however, there
were divergent views on institutional matters, in particular with regard to the role and
timing of private sector involvement as well as on the urgency for attaining
institutional targets.
.Full commitment of the stakeholders is necessary for successful project
implementation. Lack of complete commitment (at the ministerial level and in some
cases at the managerial level), insufficient training, as well as the existence of vested
interests against change, led to a prolongation of the implementation period1
5
, and to
the initial rejection of the reform efforts. The understanding of a particular society,
culture and institutions is essential both at the design stage and also during
implementation, if institutional and behavioral changes are to be achieved. For
instance, the reluctance of poor people to pay for water as well as the "cultural"
attitude toward testing the company's ability and/or willingness to collect bills before
paying has to be carefully evaluated at the preparation stage. It is not sufficient to
hope that "close supervision" will be enough to do the job. Potential conflicts
between the social/subsidized approach and the cost recovery/autonomy approach
have to be assessed to make sure that beneficiaries (ranging from managers to
engineers and employees) fully agree with the project objectives and thus feel really
15 Obviously aggravated by a three year suspension period.
17
committed'6. Intensive evaluation of behavioral issues is needed to: a) identify local
perception of problems and constraints; b) identify values and attitudes to which
project responses must be adapted; and c) obtain the commitment of appropriate
stakeholders.
* The government should set tariffs at levels that allow the long-term sustainability of
the system and reduce the distortions in the tariff structure, leading in particular to
discrimination against the poor. In addition, the tariff structure should be set to
encourage, rather than discourage, connections to the system as was the experience of
CAMEP where high connection charges caused some customers to refuse a
connection. Besides, sustainability can only be ensured if tariffs generate enough
resources to operate the system, finance the expansion of the service to new customers
and ultimately replace the facilities after their useful life.
* A sustained effort should be made to collect the payment of bills in order to increase
revenues and enable the water company to adhere to the principles of viable financial
policies.
* System reliability and performance need to be improved to lower Unaccounted-for-
water (UFW). Physical leakage and administrative losses have substantially increased
the cost of water production and supply because of a deteriorating distribution system.
Systematic and much increased metering should be implemented, preferably, not
through small and piece meal contracts often resulting in only minor improvements,
but by contracting the activity out in its entirety. This may provide for the
introduction of a more viable and effective leak detection and control program within
a shorter time frame.
* Important financial covenants between IDA and CAMEP were often not complied
with. Covenants requiring critical action to be taken, should be regularly supervised
and updated if needed. When the project was reactivated in 1995, a number of
covenants had clearly become out of date and unrealistic. However they were kept as
they were, and were de facto largely ignored. Only one '-,efore the Credit was
closed, it was amended and more modest objectives ani monitoring indicators
introduced. The lesson is that, once agreed, covenants should be enforced with all the
leverage available to the IDA and, if this proves not feasible, should be formally
revised, amended or waived.
16 It must be recalled that the entire managemnent and senior staff was removed by the government unable to
face a strike by CAMEP employees against project objectives which they did not fully understand.
PART II:
STATISTICAL ANNEXES
19
TABLE 1: SUMMARY OF ASSESSMENTS
Macro Policies J
Sector Policies J
Financial Objectives I
Institutional Development I
Physical Objectives I
Poverty Reduction I
Gender Issues J
Other Social Objectives J
Environmental Objectives I
Public Sector Management V
Private Sector Development V
B. ~staiatU* §S&ii JI. ike1 Uinfincer t-
.--- fi. ....... .---ii C. ID)A Per~mne~*~-- eiin
Identification
Preparation j
Appraisal V
Supervision I
[D. So r,,_ma...
Preparation j
Implementation
Covenant compliance V
.... .... ... .c 1*-gb1y;
t ''''' .. , t'iii i'i ',7 iiii,'iiiii' £'': '' ; .V
20
TABLE 2: RELATED BANK CREDITS
CREDIT 757-HT
Provincial Towns 6.6 1977 SNEP 6.6
Water Supply Project
TABLE 3: PROJECT TIMETABLE
L I !0 ~~~~~~January 23-29, 1983 January 23-29, 1983
tl 0 ~~~~November 9, 1984 October 6-10, 1986
? Lj ~~~~January 15, 1988 July 6, 1988
7 iil 1 : | ai ~~~March 16-20, 1989 March 16-20, 1989
F ~~May 12, 1989 June 27, 1989
-1 : | ~~~August 9, 1989 August 9, 1989
g ! ~September 11, 1989 February 14, 1990
_ ~~June 30, 1994 June 30, 1999
21
TABLE 4: CREDIT DISBURSEMENTS: CUMULATIVE ESTIMATED AND ACTUAL (US$ MILLION)
1.10 6.50 1420 18.70 20.00
0.76 0.84 0.4 0.84 0.84 0.84 257 793 1580 1971 2015
69.1 12.9 5.9 4.5 4.2
Date of Final Disbursement: October 30, 1999.
Note: As of October 20, 1999, undisbursed amount of the credit was US$877,276, i.e. 4.2% of total IDA Credit of US$21 million (SDR
15.2 million).
22
TABLE 5: KEY OPERATIONAL PERFORMANCE INDICATORS
Total population in Port-au-Prince area 956 1 058 1 113 1 171 1 250 1 328 1 412 1 500 1 595 1 700 1 79 182
Population served by CAMEP - 542 559 595 609 698 753 852 953 1 364 1 47 159
Population directly served through - 255 263 280 286 294 301 307 314 324 331 345
connections
Population served indirectly - 287 296 315 322 404 452 498 550 607 662 734
(neighbors, illegal)
Population served through paying - - - - - - - 47 89 433 482 514
stand pipes
% population directly connected - 47.0 47.0 47.0 47.0 42.0 40.0 28.0 33.0 24.0 22.0 22.0
(CAMEP)
% total population connected - 24.1 23.6 23.9 22.9 22.1 21.3 20.5 19.7 19.1 18.5 18.2
Water demand (10
6
m
3
) (1) 34.5 37.4 39.0 40.6 42.2 44.4 46.8 50.9 54.6 57.6 60.3 63.1
Estimated water consumed (106 M
3
) 24.2 25.1 25.2 23.2 19.0 20.7 21.1 24.5 30.1 26.3 24.3 34.5
Estimated physical water losses (%) 30 30 30 30 28 28 28 27 27 25 20 20
Waterproduced (106 m
3
) 34.6 35.8 36.1 33.1 26.4 28.7 29.4 33.5 41.2 35.1 30.4 43.1
Averageproductionrequired 1 092 1 185 1 235 1 288 1 336 1 408 1 484 1 610 1 730 1 820 1 912 2000
(m
3
/sec)(2)
Average production capacity 1 097 1 136 1 143 1 050 836 911 950 1 062 1 308 1 113 964 1 367
(m
3
/sec)(3)
Excess average production capacity 5 (49) (238) (238) (500) (497) (554) (548) (422) (707) (948) (633)
(m
3
/sCc)
Safety margin (%) (4) - (4.3) (8.0) (22.7) (59.9) (54.6) (59.6) (51.6) (32.3) (63.5) (98.3) (46.3)
Source: CAMEP.
(1) Water produced minus estimated losses. (2) Estimated water consumed. (3) Derived from water produced. (4) Margin between production required and production
capacity. These numbers are gross estimates, since meter use is not widespread.
23
TABLE 6: KEY FINANCIAL AND INSTITUTIONAL PERFORMANCE INDICATORS
Level of accounts receivable (No of 107 164 216 184 136 261 361 407 453 518 472 435 355
days of billing)
Ratio of collections to billings () na na na na na 73.6 83.9 51.0 73.1 83.7 73.6 79.9 77.2
Coverageofoperatingcostsby 1.03 1.01 1.17 1.16 0.83 1.02 0.97 1.52 1.41 1.27 1.32 1.04 1.30
operating Revenues
Working ratio (1) 97.0 99.2 85.6 86.5 121.1 97.6 96.6 66.0 71.0 78.5 76.0 96.1 76.7
Operatingratio(2) 117.6 119.5 102.5 102.0 148.1 141.4 139.6 68.6 95.2 85.0 89.1 118.8 92.3
(3) (3)
Debt/(Debt + Equity) Ratio 54.4 50.9 50.1 57.5 72.9 87.8 97.9 94.9 92.4 76.9 98.6 114.9 107.3
Current ratio (4) 1.27 0.81 1.64 2.07 1.16 1.05 0.98 1.25 1.25 1.32 0.93 1.29 1.46
Number of employees per 1000 na na 18.5 19.9 15.1 17.2 16.1 16.1 14.4 13.5 14.2 13.2 12.6
connections (domestic)
Personnel costs as % of opera-costs 64.0 60.5 65.6 70.5 53.7 66.7 70.9 72.4 70.5 64.7 60.3 54.8 52.1
Source: CAMEP
(1) Ratio of operating costs (excluding depreciation) to operating revenues. (2) Ratio of operating costs (including depreciation) to operating revenues. (3) Equity became negative in 1998
and in 1999 (- G. 48.77 million in 1998 and -G 37.91 million in 1999). (4) Current assets / current liabilities.
24
TABLE 7: NUMBER OF WATER CONNECTIONS
with meters 1 074 1 234 1 221 1 218 1 346 1 311 1 100 1 023 1 013 1 016 946
without meters 24 771 25 677 27 749 28 540 29 549 29 998 31 076 32 062 33 048 34 407 35 848
Sub-total 25 845 26 911 28 970 29 758 30 895 31 309 32 176 33 085 34 061 35 423 36 794
with meters 329 334 341 341 339 333 333 336 331 331 332
without meters 5 757 5 630 5 691 5 710 5 529 5 989 5 806 5 847 6 068 5 665 6 042
Sub-total 6 066 5 964 6 032 6 051 5 868 6 322 6 139 6 183 6 399 5 996 6 374
with meters 1 403 1 568 1 562 1 559 1 685 1 644 1 433 1 359 1 344 1 347 1 278
withoutmeters 30508 31307 35002 35809 35078 35987 38315 37909 39116 40072 41890
Total 31 911 32 75 36 564 37 368 36 736 37 631 39 748 39 268 40 460 41 419 43 168
Source: CAMEP.
Note: A number of connections (specially domestic), have been disconnected for non-payment of bills or various technical factors. Such number was estimated at 9,000 in
1998.
25
TABLE 8: PROJECT SCOPE AND COSTS (IN THOUSANDS OF US$)
(Page 1)
.. * ....
e .~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~P
a) Water Production and Transfer (i) 1 water spring development 5 wells (2 + 3) 40 168
(ii) Transmission mains from transmission mains 2 060 1 040 (est.)
sources to transmission system
(11.2 kilometers) (5.6 kilometers)
2 100 1 308
b) Water Transmission, Pumping, (i) transmission mains transmission mains 7 205 3 600 (est.)
Storage Infrastructure (40 kilometers) (19.3 kilometers)
(ii) 3 storage reservoirs 2 storage reservoirs 940
(5 000 m
3
total) (5 000 m
3
total) < 4 696
(iii) I pumping station 2 pumping stations 230
(iv) regulating equipment regulating equipment 200 622
8575 8918
c) Distribution, Network and (i) 60 km pipes 83 km pipes 1 560
Connections
< 4 710
(ii) 10 500 water house 2 580 connections (new) 2 130
connections (1)
(iii) 2 500 water meters 1 000 water meters 500 183
(iv) 2 600 flow limiting devices not done 210
(v) 200 public stand pipes 26 stand pipes (2) 210 na
(vi) 50 fire hydrants 14 fire hydrants 50
4 600 4 893
d) Equipment, Vehicles, Stocks 1 000 3 401
(1) (f which 5 000 new connections and 5 500 rehabilitations. (2) Excluding stand pipes financed outside the project.
26
TABLE 8: PROJECT SCOPE AND COSTS (IN THOUSANDS OF US$)
(Page 2)
e) Building Operational building Done 350 603
f) Studies Sanitation study Done 200 399
Other studies -- 1 851
g) Miscellaneous PPF PPF, training, financial expenses 765 832
TOTAL BASE COST 17 650 22 205
Physical contingencies 1 900
Price contingencies 2 600
Sub-total 22 150 22205 (1)
Structures for pumps, electrical Done 5
equipment__ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
4 285 8 931
b) Technical assistance, studies Consultant services Services provided 2 100 1 954
and training
c) Supervision ofPconstruction Consultant services Technical assistanceprovided 1 000 1 996
d) Preparation of follow up project Consultant services done (IDA financed) 400
TOTAL BASE COST 4 285 12 881
Physical contingencies 600
Price contingencies 1 100
Sub-total 9 485 12 881
27
TABLE 8: PROJECT SCOPE AND COSTS (IN THOUSANDS OF UJS$)
(Page 3)
C00st
~~~~~ ~~~~~~~~A k 8 A >f at
Purchse ofLa))dacquiiti
- 1- -Ad "-w'qu7¾on 4 00' 25 6 (2)
Base Cost
25 070 -35 3 42'
Physical conitingencies
2 500--
Price contingencies
3 700
Total Project Cost
31 270 35 342
(I.) Including OPEC contribution (substitution for CAMEP financing) for US$ 2 million.
(2) Including US$ 74 000 contribution by Haitian govermnment.
28
TABLE 9: PROJECT FINANCING
US$ million % US$ million %
IDA 20.0 56.3 20.2 57.1
AFD (French) 9.5 26.8 12.9 36.4
OPEC _ _ 2.0 5.6
CAMEP 4.6 13.0 0.2 0.6
Government 1.4 3.9 0.1 0.3
TOTAL 35.5 100.0 35.4 100.0
29
TABLE 10: ALLOCATION OF IDA CREDIT PROCEEDS (US$ MILLION)
Civil Works 7.5 12.7 12.96
Equipment and Materials 8.0 4.4 4.84
Consultant Services 0.2 2.0 1.93
Refund of PPF (1) 0.8 0.8 0.76
Unallocated 3.5 0.1
TOTAL 20.0 20.0 20.49
(1) PPF = Project Preparation Facility
30
TABLE 11: ECONOMIC RATE OF RETURN
1995 390 (390) (390) (390)
1996 4467 573.4 (4452-7) (4037.3) (3957.5)
1997 9454 1037.3 (8600.3) (8023.6) (7658.5)
1998 9496 2047.2 (9214.9) (8428.6) (8024.5)
1999 4439 3116.7 (2721.9) (585.1) (154.3)
2000-2024 3116.7 1717.1 3853.9 4284.7
Assumptions
1. No new investment is assumed between 2000-2024.
2. Project incremental operating costs for 2000-2024 use 1995 as the base year.
3. Source of operating costs is financial statements.
4. Source of revenues is financial statements.
5. Projected benefits remain constant between 2000-2024.
6. Benefits included savings experienced by customers when they switch supply from private vendors to CAMEP.
7. Vendor prices are a proxy for willingness-to-pay. Vendor purchases assumed to be equal to 1/10 purchases from CAMEP.
31
TABLE 12: FINANCIAL RATE OF RETURN
.k 4
1995 390 (390)
1996 4467 574.3 640.0 (4400.4)
1997 9454 1037.3 893.3 (9639.0)
1998 9496 2047.2 1422.0 (10121.2)
1999 4439 3116.7 3390.0 (4165.7)
2000-2024 3116.7 3390.0 273.3
FIRR = -8.26%
Assumptions
1. No new investment is assumed between 2000-2024.
2. Project incremental operating costs for 2000-2024 use 1995 as the base year.
3. Source of operating costs is financial statements.
4. Source of revenues is financial statements.
5. Projected benefits remain constant between 2000-2024 and a collection rate of 80% is assumed.
32
TABLE 13A: ETAT DES RESULTATS 1994 -1999
(Montant en Million de gourdes)
ETAT DES RESULTATS
Revenus de Facturation 34.02 38.61 45.84 62.37 67.93 109.0
Devis 0 0 0 0 1.09 0.50
Frais de reconnection 0.63 0.49 0.67 0.85 0.20 0.10
Autres 0 0 0 0 0.48 1.0
Revenus d'exploitation 34.65 39.10 47.51 63.22 69.70 111.6
Frais de Personnel 16.55 19.59 24.11 28.98 36.70 44.60
Produits Chimiques 0.03 0.50 0.59 0.97 1.56 1.70
Electricite 0.97 1.21 4.68 4.74 5.00 5.31
Material Hydralique 0.69 2.21 2.73 3.56 8.59 11.05
Mauvaises Creances 1.41 2.04 1.51 2.24 3.97 4.37
Frais d'adminstration 3.21 2.23 3.67 7.54 11.18 18.62
Total des depenses d'exploitation 22.85 27.78 37.29 48.03 67.00 85.65
Profit avant Amort. & Frais Financiers 11.79 11.32 10.22 15.19 2.70 26.04
Amortissement 9.2 9.46 3.08 8.28 15.81 17.39
ProfitavantFraisFinanciers 2.59 1.86 7.14 6.91 -13.11 8.65
Frais Financiers 0.56 1.53 1.03 4.18 4.80 5.28
Revenus Exceptionnels 0 0 0 0 0 0
Profit Net 2.03 0.33 5.31 2.73 -17.91 3.37
Rapport de Travail (dep. d'expl/Rev. d'expl) 65.97% 71.05% 70.45% 75.97% 96.13% 76.59%
Rapport Operationnel 92.53% 95.24% 64.97% 89.07% 118.61% 92.26%
Rate of Return
33
TABLE 13B: KEY ELEMENTS OF INCOME STATEMENTS 1993 -1999
(In Gourdes Millions)
Total Revenues
Appraisal Estimate 57.23 68.08 90.73 NA NA NA NA
Actual 22.90 34.65 39.10 47.51 63.22 69.70 111.60
Total Operating Costs
Appraisal Estimate 27.86 30.78 34.72 NA NA NA NA
Actual 22.13 22.85 27.78 37.29 48.03 67.00 85.65
Operating Profit
Appraisal Estimate 29.36 37.30 46.01 NA NA NA NA
Actual -7.07 11.79 11.32 10.22 15.19 2.70 26.04
Depreciation
Appraisal Estimate 10.14 12.40 14.87 NA NA NA NA
Actual 9.84 9.20 9.46 3.08 8.28 15.81 17.39
Net Profit
Appraisal Estimate 12.38 17.06 23.30 NA NA NA NA
Actual -9.75 2.03 0.33 5.31 2.73 -17.90 3.37
34
TABLE 14: BANK RESOURCES: MISSIONS
Preparation October, 1986 2 5 F
Appraisal July, 1988 2 N/A. F
Supervision 1 July, 1990 2 6 F 2 1 2 1
2 March, 1991 1 17 C 2 2 2 1
3 Nov., 1995 3 10 F, E 2 2 2 S (1)
4 June,1996 4 8 F, E 2 2 2 S
5 Sept., 1996 2 5 F 2 2 1 S
6 May, 1997 3 5 F S S S (2) S
, Feb, 199. 3 9 Tj T I t J (13)
l > t .:2lay, 1 )t:39 1 _ _ _ 1 ---- 1 ------ -g .1 ..g ...___ 1~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ -- --------
._ .__ _ _ . _. [
_..,
(1) S = Satisf4ctor>y =Egne
(2) Counterpart Funds l I inancial Analyst
(3) U = Unsatisfactory C Consultant
35
TABLE 15: BANK RESOURCES: STAFF INPUTS
Project Preparation 95.1 232.7
Project Supervision 124.0 331.1
TOTAL 219.1 563 .8
36
TABLE 16. STATUS OF LEGAL COVENANTS
2.01 (b) C Maintain key managers acceptable to IDA
2.05 (c) C Review IDA the status of project implementation
by May 31 in each year
2.06 (a) PC By May 31 in each year furnish to IDA an Partially complied
Institutional Improvement Plan and an operational Institutional Plan and
plan including monitoring indicators and financial revised monitoring
projections. indicators in December
1998
2.06 (b) PC Implement the Action Plan Action Plan partially
implemented in 1997-1999
3.01 (ii) NC CAMEP shall pay interest on the outstanding Not complied due to
balance CAMEP financial
of the Subsidiary Loan at a rate of 7% per year difficulties
3.04 (a) C Furnish to IDA by June 30 1990 a report on the Cul Complied with in July 1990
(i) de Sac Aquifer Management study and the
CAMEP's Water Supply needs
3.04 (a) CD Furnish to IDA by June 30 1990 a plan for the Water supply study
(ii) development of Water Supply and sanitary completed in December
facilities outside the Project area 1996; Sanitary facilities
study completed in June
1999
3.04 (c) CD Not later than March 31, 1991, take actions to Drilling of wells
(i) implement the recommendations of the Aquifer undertaken and protection
Study of springs ensured through
fencing in 1999.
3.04 (c) PC Not later than March 31, 1991, take actions to Partially with creation of
(ii) improve water and sanitary facilities sector URSEP (government Unit
institutions in the Country in charge of water sector
reform) in 1997
3.05 C Review of project performance with IDA of each Complied from 1995 to
I year June 30 1999
37
TABLE 16. STATUS OF LEGAL COVENANTS (CONT'D)
3.06 PC Open account for the purpose of the project by Partially complied Special
October 15, 1989 and make deposits and account opened for
expenditures exclusively for the project counterpart funds in
February 1996
4.01 (a) PC Maintain separate accounts for expenditures related Partially complied Separate
to the Sanitation Study, have those accounts Accounts maintained for
audited and furnish audited reports to IDA no later the study but no separate
than 4 months after the end of each fiscal year audit.
4.01 (b) C Maintain adequate records and accounts, and have
them audited annually and submit audit report to
IDA, by January 31 of each year
4.02 (a) NC Maintain operating ratio of 90% in 1989, 75%/O in Not complied Revised
1990, 65% in 1991, 50% in 1993 and thereafter project restructuring in
1998 not complied with
4.05 (a) PC Raise tariffs annually according to inflation plus Tariffs raised by 6% in
4% in 1989-1992 and by a percentage equivalent to December 1989, in
inflation rate thereafter December 1996 and in July
1998 by 90%
4.05(b) NC Maintain a ratio of metered and un-metered
connections under maximum charges to total
connections of:
20% in 1989
30% in 1990
40% in 1991
50% in 1992
55% in 1993
65% in 1994
4.05 (c) PC Maintain a number of employees per 1000
connections, not higher than
19 in 1989,
18 in 1990,
17 in 1991,
16 in 1992,
14 in 1993,
13 in 1994 and thereafter
C: Covenant complied with CD: Complied with delay
PC: Partially complied with NC: Not complied with
38
Appendix
Page 1 of3
TRANSLATION OF SUMMARY OF BORROWER'S CONTRIBUTION
All in all it could be said that the project was executed to the satisfaction of the
borrower in spite of the delay encountered at the start of the project. However, with respect
to certain components, the scope of implementation could have been less than that specified
in the project. These shortfall could be attributed either to the bad financial evaluation of the
concerned component by consultants or by a delay in the execution of the project.
Unfortunately certain subcomponents of the project could not be executed because the land
was not available at the beginning of project implementation. On account of the lack of land,
the project had to be modified. The quantities expected in the contracts signed with
contractors and suppliers have been supplied and/or executed. The amendments were signed
for works and related goods and for studies. In most cases, the project contracts were
executed on schedule.
Not all the project objectives were accomplished. The quality of water can be
improved, losses reduced, and the network extended to the new service areas. The population
served by CAMEP is estimated at 1,593,200. The production during 1999 was 43,106,822
mi
3
.From the perspective of institutional development, progress has been made and certain
procedures have been put in place. Thanks to the acquisition of certain equipment, the
working conditions at CAMEP have improved.
Presently, an evaluation of the project can be made. However it would be necessary
to complete all the installations and allow for a number of years of operations in order to
develop an idea about the project's results.
The works of this project included in the master plan for potable water in 1987 for the
Port-au-Prince Metropolitan area were executed 10 years after the signing of the
Development Credit Agreement. Even if these works did not lead to the expected results
envisaged in the master plan, they nonetheless have led to a significant improvement of water
supply in Port-au-Prince.
The 30% increase in average daily production, the removal of illegal connections, the
rehabilitation of several dozen kilometers of mains and thousands of connections have
enabled a significant reduction in technical losses in the network, and the possibility of
supplying water to a number of neighborhoods which until recently had very poor service or
which did not have any service at all, particularly the spontaneous habitats in which nearly
half of the population lives.
These works have especially started a process to enable CAMEP to take charge of its
network by putting in place a distribution plan, based on the reconfiguration of networks in
isolated sectors which would be progressively put in place.
39
Appendix
Page 2 of 3
In the short-term, the "sectorization" of the network will permit a better control of the
distribution, the reduction, if not the elimination, of a number of valve operations as well as
rapid detection of leaks in the network, and as a result, the improvements of the quality of
water supply, the billing of water consumed by the installation of meters upstream of the
distribution networks and micro-meters in house connections.
Thanks to this project and to the new structure of service to our clientele, the
management methods at CAMEP have been modernized and the principal indicators of
perfornance have been improved. The master-plan of 1987 was implemented and the
feasibility study of the works for the second project have been prepared. The result of this
study have indicated that about US$ 100 million would need to be invested on the network
during the next 5 years.
A study undertaken by the French firm "Ingenieurs Conseils et Economistes Associes
(ICEA) on the options for the modernization of CAMEP has demonstrated that at the present
phase, only a management contract can be envisaged. This study, whose results were
presented at the beginning of 1998, in other words, at the end of the works of this project,
utilized figures and indicators for the years prior to 1997. They thus merit being updated.
Furthermore, this study related progress made under the present management paradigm to
the previous years, and has not considered the possibility of maintaining the current status of
CAMEP. It did not also propose the methods necessary to improve the performance of a
public operator. Instead, its main conclusion is potable water services will need to be
privatized!
Management contract implies the participation of a private operator in all levels of decision
making at CAMEP. This private operator will be compensated on the basis of performance
indicators which have not been clearly defined. Only the state can make this type of
commitment to the donors because the state is responsible for investments.
According to this study, the current state of the network and the limited ability-to-pay of the
population exclude any possibility of investment by the private sector. In effect, more than
half the population live in low income areas and 50% of the other half do not have steady
incomes.
The privatization of the provision of potable water has social and political cost for which
there must exist the means to pay. This operation must set-up within a framework whereby
partners or the private sector can be involved financially as well. International experience
has demonstrated that management contract has failed in the majority of cases. The financial
commitment of the private operator constitute an important motivating factor in guaranteeing
success. At the current circumstances, two scenarios can be envisaged:
40
Appendix
Page 3 of 3
(i) Reinforce the means and improve the management capabilities of the public
operator by (a) undertaking investments by the state, aimed at improving the condition of the
network; and (b) call for a concession ( after 5 years ).
(ii) Orient the option of modernization toward an affermage, even though this option
was not anticipated in the (CMEP) law. Consequently, it would be necessary to amend the
law to include the option of affermage and the private operator would need to participate in
investment expenditures.
lIRD 21564
00 72124 [2o22 , 72&21)' 72 1S ,, C U L D E S A C 72-12' V. TllT SAHAMAS _ I
CUL DE SAC
,AtHAITI " -?(GROUNDWATER)
PORT-AU-PRINCE WATER SUPPLY PROJECT CUBA
1 Project Arpe, portiol eoponrtoolreliobititetlen > 2( f ...t.5 .... 6 9 .- ., - -/ WELLFIELD --~- tWELLFIELD
* of itc/froennsisior end dstrlbotion p;Eg / -i;e r + y t ' t_MAIS GATE st,oMIS HAir I so DCWCAN
ood mono connectb ionsIR C C | T E 50 L E g L ~> _ Pq rEq%-_rlLTd,rd ( REP
o Well5 to be Con51udd AV,AlICA -,
O R-srolm to b. Coo-stITE OtEd
--0 lorosetsieePiipes to be ConstructddJ
---- To-trrise Pipeso be bnpoodrb.lltoed.
Dlqinit E Cist dsRuSprlno
0 Prosture Zone Propsed by Mento Pin72
WELPFIELD
B'>,e de P-r RV- P i Reesooms 1 "20 TAPAGE GALETTE
PORT-AU-PRINCE' . A
CARREFOUR -- -32'-
fI
t ~~~~~~~~~~~~~~~~0 <6'~~~~~~~~~~~~~~~~~~~~~~~~
C..~ ~ ~ ~ ~ ~ ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~tge
--I
Conoed~~~~~~~~~~~~~~~~~~~~~~~~~ ~~~~~~~ -~~~~~E10-IL
C.,;~e <N
Muse tnptAS IF DE LA SEiE MOtT IN
-18,30' T&.d. KIUmETER
Et~~~~~~ 0SPIN S
KILOMEOtRS ~ ~ ~ PRL 98