Teks Konple Dokiman an
Teks ki soti nan dokiman orijinal la pou endeksasyon.
Office of Internal Audit and Investigations
Internal Audit of the
HAITI COUNTRY OFFICE
DECEMBER 2022
Report 2022/23
1
CONTENTS
Executive Summary ...................................................................................................... 3
Overall Conclusion
Summary of Observations and Agreed Actions
Context ........................................................................................................................... 6
Audit Objectives and Scope ......................................................................................... 8
Observations and Management Action Plan .............................................................. 9
1. Programme preparation
2. Programme monitoring
3. Resource mobilization
4. Advocacy
5. Evaluation
6. Prevention of sexual exploitation and abuse
7. Risk management
8. Security
9. Temporary staff
10. Partnership management
11. Liquidation of cash transfers
12. Humanitarian cash transfers
13. HACT assurance activities
14. Supply management
15. Warehouse management
Appendix ...................................................................................................................... 23
Definitions of Audit Observation Ratings
Definitions of Overall Audit Conclusions
2
EXECUTIVE SUMMARY
The Office of Internal Audit and Investigations (OIAI) conducted an audit of the Haiti Country
Office covering the period from January 2021 to August 2022. The audit was conducted in person
from 22 August to 8 September 2022 in accordance with the International Standards for the
Professional Practice of Internal Auditing. The overarching objective of the audit was to assess
the adequacy and effectiveness of the governance, risk management and control processes over
a selection of significant risk areas of the office including programme management (planning,
monitoring, evaluation, resource mobilization and advocacy), prevention of sexual exploitation
and abuse, cash transfers and assurance activities, procurement management, human resources
and security. The descriptions of the specific risks identified during the engagement planning
process are provided in this report in the Audit Objective and Scope section
Haiti's economic and social development continues to be hindered by political instability, natural
hazards, and persistently high levels of day-to-day violence. This context is indicative of a highrisk environment for input management, whether supplies or cash, programme implementation
and monitoring, and for sexual exploitation and abuse for children and women. For the period
January 2021- July 2022, the office spent US$ 31 million on cash transfers and US$ 6 million on
supplies. The audit sought to determine whether and how the office managed those risks.
Overall Conclusion
Based on the audit work performed, OIAI
concluded that the assessed governance, risk
management, or control processes were
Partially Satisfactory, Major Improvement
Needed, meaning that the weaknesses or
deficiencies identified were unlikely to have a
materially negative impact on the audited entity,
area, activity or process. (See the Appendix for
definitions of the conclusion ratings.)
Satisfactory
Partially Satisfactory,
Improvement Needed
Partially Satisfactory, Major
Improvement Needed
Unsatisfactory
Summary of Observations and Agreed Actions
OIAI noted several areas where the office’s controls were adequate and functioned well:
Feedback received from partners during interviews demonstrate that the office has
established good working relationships with Government counterparts, particularly within the
Ministries of Education and Health. Particularly appreciated was the easy access afforded to
programme staff and management. Also noted approvingly has been the proactive and quick
responses to emergencies, compared to other development agencies.
Partners also highlighted other positives such as UNICEF’s determination to meet its
commitments, its willingness to accompany and support the country without imposing itself
and its determination to highlight important themes of children's rights. For example, in August
2022, UNICEF made an impactful presentation on the results of a rapid nutrition evaluation.
This presentation of findings drew the attention of high-level decision-makers who in turn have
become more engaged more and have provided UNICEF with more support.
In 2021, the Human Resource unit managed the recruitment and onboarding of 34 staff on
Temporary Appointments (TA) and facilitated the release of 38 external surge staff (stand-by
and surge partners) in support of the response to the 2021 earthquake emergency.
3
The office proactively contributed, under the leadership of the Resident Coordinator (RC), to
negotiations for UN access to very high security risk areas, including Cité Soleil, home to
some of the country’s most vulnerable women and children. The office also hired a consultant
to lay the groundwork for possible interventions in hot spots controlled by non-government
groups and participated with inter-agency missions to deliver support to these areas.
The office established an effective humanitarian cash transfer process characterized by good
segregation of duties and oversight.
The audit also made a number of observations related to the management of the key risks
evaluated. In particular, OIAI noted:
Risk management: The office’s risk assessment was inadequate. In particular, it did not
identify potential root causes of the risks it had identified, making it difficult for it to be
reasonably assured of the adequacy and appropriateness of the mitigating measures it had
put in place.
Partnership management: Civil society organization partners were selected mostly through
a direct procedure, creating a risk of irregularities in the selection of partners and
compromising the ability of UNICEF to determine and select the most qualified partners and
thereby obtain the best value for its money.
Temporary staff: The high number of temporary staff (34 out of 130, or 26%, as of 29 August
2022) raises the question of the sustainability of the office’s staff structure. Elevated numbers
of staff on temporary contracts can contribute to lower staff morale because temporary staff
receive fewer benefits.
Harmonized Approach to Cash Transfer (HACT) assurance activities: Assurance
activities were not risk-based, thus limiting the office’s ability to effectively manage the risks
of misuse, waste, abuse and inefficiencies related to cash transferred to partners.
Warehouse management: Gaps in the access to and security of the warehouse, as well as
gaps in the conditions of storage and inventory accounting, pose the risk of waste and the
loss of resources that are needed to achieve planned results.
Security: The Office’s security improvement plan was not budgeted and responsibility for the
implementation of recommendations in the plan was not assigned, increasing the risk that the
Office’s security needs may not be promptly and effectively addressed. Given that the Office
operates in a constantly changing and heightened security risk environment, these
deficiencies may negatively impact on the effectiveness of the safety and security measures
it implements.
The table below summarizes the key actions management has agreed to take to address the risks
identified. The table also indicates the category and ratings of these risks. (See the definitions of
the observation ratings in the Appendix.)
4
OBSERVATION RATING
Category of
Process
Governance
Risk management
Controls processes
Area or Operation and Key Agreed Action
Rating
Temporary staff (Observation 9): Strengthen the process for
extending temporary appointments to ensure that a programmatic
and/or operational justification is provided and cleared by
management in line with organizational guidance. Establish a clear
strategy for long‐term regular staffing of field offices.
Medium
Security (Observation 8): Plan and implement security
assessments to ensure the conformity with the new SRM. Establish
a security action plan to address identified gaps. Ensure that
responsibilities
for
implementation
of
security-related
recommendations are assigned. Ensure there is adequate budget
for and monitoring of security measures.
High
Risk management (Observation 7): Identify root causes of the
risks and ensure adequate and appropriate mitigating measures in
line with those root causes are put in place to reduce significant
risks to acceptable levels. Ensure control effectiveness is assessed
and that there are clear links between risks, their root causes and
the corresponding mitigating measures.
High
Gender equality programming (Observation 1): Acquire gender
expertise as per the organization’s recommended benchmark and
ensure that gender equality is mainstreamed in the 2023-2027
Country Programme, in line with UNICEF’s 2022-2025 Gender
Action Plan.
Medium
Partnership management (Observation 10): Where possible,
encourage open selection for identifying CSO partners in order to
obtain the best value for money, using the UN Partner Portal as
applicable.
Medium
HACT assurance activities (Observations 13): Ensure a riskbased approach in planning and implementing assurance activities
by prioritizing assurance activities for high-risk partners and
partners that receive significant amount of DCT.
Medium
Warehouse management (Observation 15): Ensure that
temperature-sensitive supplies are stored within manufacturer’s
recommended temperatures. Ensure that obsolete and damaged
supplies are promptly and appropriately disposed of to avoid further
loss in value.
High
Management is responsible for establishing and maintaining appropriate governance,
risk management and control processes, and implementing the actions agreed
following this audit. The role of the OIAI is to provide an independent assessment of
those governance, risk management and control processes.
5
CONTEXT
Context of the audited entity and its operating environment
In 2020, Haiti had a GDP per capita of
US$2,925, the lowest in the LAC region.
According to the 2020 Human Development
Report, Haiti ranked 170 out of 189 countries,
placing the country in the “low” human
development category.
Past marginal gains in poverty reduction have
been undone by a succession of crises
including the COVID19 pandemic, the
assassination of the country’s President (in
July 2021), and an earthquake, in August
2021. Haiti is among the countries with the
greatest inequity in the region. The richest 20
percent of its population holds more than 64
per cent of its total wealth, while the poorest 20 per cent hold about 1 per cent.
Additionally, Haiti remains highly vulnerable to natural hazards, mainly hurricanes, floods and
earthquakes. More than 96 per cent of its population is exposed to these types of shocks. On
August 14, 2021, a 7.2 magnitude earthquake struck the south of Haiti, causing widespread death
and damage. In total, 2,248 people died, 12,763 were injured and 83,770 buildings were
damaged. Climate change is expected to increase the frequency, intensity and impacts of extreme
weather events.
Since June 2021, violent clashes between armed gangs have hugely disrupted the lives of
residents of the Port-au-Prince metropolitan area, spreading fear and terror. The overall security
situation continues to deteriorate, reaching new levels after April 2022. This situation continues
to negatively affect the operational environment for humanitarian actors and hinder their ability to
carry out life-saving assistance1.
Context of key risk areas covered in the audit
The current UNICEF Country Programme was initially for the period January 2017 to December
2021. It has been extended for a 14-month period, from January 2022 to February 2023. The
reason for this extension was political uncertainty, rising insecurity, civil unrest and institutional
instability that limited the Government’s engagement in policy dialogues and in the technical
consultations required to articulate a new Country Programme and UN-wide 2022–2026
Cooperation Framework.
The 2017-2023 Country Programme consists of six programme components (Health; Nutrition;
Water, Sanitation and Hygiene; Basic Education; and Child Protection) and one cross-sectoral
component (Programme Effectiveness). Humanitarian actions and gender and adolescent
development have been mainstreamed across programme results. The programme focuses on
the most excluded and disadvantaged children to ensure their survival, development, participation
and protection.
1
OCHA, July 2022
6
The total board-approved budget is US$ 172 million (US$ 27 million in Regular Resources and
US$ 147 million in Other Resources). In 2021, the office mobilized US$ 17 million of ORE for
HAC.
The breakdown of the office’s expenditures (in 1,000 US$) in 2021 and 2022 (as of July) is as
follows:
Expenditure categories
2021 amounts
Cash transfers
19,310
Staff cost
10,304
Operating costs
5,824
Supplies
4,996
Contract services
1,745
Travels
1,367
Other
314
Total expenses 2021
43,860
Source: SAP 2021 and 2022 trial balances
Percentage
44
23
13
11
4
3
1
100
2022 amounts
11,413
7,287
5,868
1,305
6,387
1,207
160
33,628
Percentage
34
22
17
4
19
4
0
100
Office structure and staffing: The Country Office is located in Port-au-Prince. Two zone offices
exist, in Gonaives and Les Cayes. The office has 106 approved positions, including 31
international professionals, 39 national officers and 36 general service posts. Of these, 12 posts
(11 per cent of overall staffing) were based in the zone offices. As of July 2022, there were 10
vacant posts.
7
AUDIT OBJECTIVES AND SCOPE
The objective of the audit was to assess the adequacy and effectiveness of the governance, risk
management and control processes over a selection of significant risk areas of the Haiti Country
Office. The audit scope included key areas, set out in following table, that were selected during
the audit planning process based on an assessment of inherent risks. 2
RISK AREAS
DESCRIPTION OF KEY RISKS
Risk management
The office may not effectively identify and assess the risks to its
programme results and thereby not take effective measures to manage
significant risks.
The office may not have established adequate processes to ensure
that projected funding gaps are promptly filled. In 2021, the office
mobilized US$ 15 million of OR, i.e., 75 per cent per cent of the target,
and US$ 17 million of ORE, i.e., 14 per cent of the target.
Advocacy activities may be conducted on an ad hoc basis without clear
objectives, coordination mechanisms and supporting evidence,
thereby failing to ensure the efficient and effective promotion of
children’s rights.
The office and its partners may fail to take adequate measures to
prevent and protect children against sexual exploitation and abuse,
thereby exposing beneficiaries to harmful actions and UNICEF to
reputational risks.
The office may not have sufficient evaluative knowledge and
information on impacts and outcomes of the Country Programme to
assess achievements of programme objectives, identify and share
lessons learned and inform future programme planning.
Partnership selection processes may not engage CSO partners that
may offer the best comparative advantages to achieving programme
results.
Cash transfers to implementing partners may not be properly
managed, resulting in fraud, loss of financial resources and nonachievement of results. This can lead to reputational risks.
Controls that have been established may not be adequate to ensure
the timely and efficient processing of disbursements or to provide
reasonable assurances intended beneficiaries receive those transfers.
They may not be sufficient to protect the personal data of beneficiaries.
Potential supply chain weaknesses may result in failures to achieve
results due to late provision and/or poor quality of supplies. Such
weaknesses may lead to supplies not being used for their intended
purposes, leading to loss of resources and reputational risks.
Inadequate resources to implement necessary security risk-mitigating
measures may result in injury and/or loss of lives and/or assets.
Resource mobilization
Advocacy
Protection against Sexual
Exploitation and Abuse
Evaluation
Partnership management
Cash transfers
Humanitarian cash
programmes
Supply management
Security management
The audit was conducted in person from 22 August to 8 September 2022 in accordance with the
International Standards for the Professional Practice of Internal Auditing. For the purpose of audit
testing, the audit covered the period from January 2021 to August 2022 and involved a
combination of methods tools and techniques. These included interviews, data analytics,
document review, tests of transactions, evaluations and validation of preliminary observations.
2
Inherent risk refers to the potential adverse event that could occur if management takes no actions, including
internal control activities. The higher the likelihood of the event occurring and the more serious the impact would be
should the adverse event occur, the stronger the need for adequate and effective risk management and control
processes.
8
OBSERVATIONS AND MANAGEMENT ACTION PLAN
The key areas where actions are needed are summarized below.
1. Country programme preparation
Medium
There was a lack of comprehensive and up-to-date data on the situation of children, as well as
disaggregated demographic data that could have permitted more targeted programming. Further,
the office did not have expertise or a dedicated gender position to support gender programming
in the new Country Programme.
Planning data: In line with UNICEF practice when preparing a
new Country Programme, in April 2022, the office prepared a
situation analysis on children and women in the country. The CO
used appropriate and diverse data sets and methodologies for this
purpose, including studies, evaluations, surveys and management
information systems. However, due to staff turnover, and the
diminished capacity of the Government, the CP lacked important
information. Missing information included that from the latest basic
large-scale surveys such as multi-indicator cluster surveys (MICS)
and the population census, which has not been conducted since
2003. These omissions resulted in a CP lacking comprehensive
and up-to-date data on the situation of children. For example, data related to social protection,
household living conditions as well as disaggregated demographic data that could have allowed
a more targeted programming were not available.
Large-scale surveys
that are usually
updated by the
Government, such as
MICS and population
censuses, were not
conducted in Haiti
since 2003.
The audit team met with the Deputy Special Representative of the Secretary-General, Resident
Coordinator and the Humanitarian Coordinator (DSRSG/RC/HC) in Haiti. These officials showed
interest in supporting inter-agency initiatives to advocate with the Government and to provide
support to conduct these large-scale surveys.
Gender equality programming. The Strategic Plan 2022-2025 reaffirms that gender equality is
an organizational priority, a fundamental value and a cross-cutting principle for all five strategic
plan Goal Areas, as well as across UNICEF’s programmes and workplaces. In May 2021, the
Latin America and Caribbean (LACR) Regional Director noted that Haiti ranked 150 th out of 189
countries (2018)3 on the gender inequality index and that the gender dimension was missing in
the Country Programme and needed to be addressed from a multi-sectoral perspective. The audit
noted that the office does not have the required expertise or a dedicated gender position to
support gender programming in the new 2023-2027 country programme, in line with UNICEF’s
2022-2025 Gender Action Plan (GAP)4. The UNICEF organizational benchmark has established
the recommended minimum standard for gender staffing at one full-time Gender Specialist, a
position that should be equivalent to the level of a Chief of Section in country offices whose annual
budget is above US$ 20 million, which is the case of Haiti.
Not addressing gender inequalities that affect girls and boys differently might lead to negative
results, such as poorer nutritional and learning outcomes.
3
4
http://data.un.org/DocumentData.aspx?id=415
https://www.unicef.org/executiveboard/documents/UNICEF-Gender-Action-Plan-2022%E2%80%932025-SRS2021#:~:text=About,United%20Nations%20Children's&text=Gender%20equality%20is%20essential%20to,across%20its%20programmes
%20and%20workplaces.
9
AGREED ACTION
The office agrees:
i.
Together with the RC/HC and with UNCT members, advocate with the Government
and strengthen its capacity to conduct large-scale/country wide surveys to collect
socio-economic data on the population.
ii.
Acquire the gender expertise as per the organization’s recommended benchmark and
ensure that gender equality is mainstreamed in the new 2023-2027 Country
Programme in line with UNICEF’s 2022-2025 Gender Action Plan.
Staff Responsible: Deputy Representative, Programme
Implementation Date: February 2023
2. Programme monitoring
Medium
The security situation which has been marked by escalating gang violence continues to limit the
freedom of movement of UN agencies, negatively impacting programme delivery and field
monitoring. The establishment of an office-wide third-party monitoring system could have helped
mitigate this risk.
According to the office’s security assessment, areas with high or very high security risks included
the Port-au-Prince metropolitan area and areas in five other Departments (Artibonite, Centre,
North-West, South and South-East) where the office was implementing programme activities in
WASH, Nutrition and Immunization. Freedom of movement in these areas was limited, negatively
impacting programme delivery and results for children.
In order to implement programme activities, the office established partnerships with local CSOs
which have access to these areas and are accepted by the communities. However, the office had
not established a structured field monitoring process in inaccessible areas, such as using the
same monitor to monitor different programmes operating in the same area. It also did not ensure
effective methods for verifying information collected by monitors. The audit suggested that the
office establish a third-party monitoring (TPM) mechanism for areas for which on-site visits are
not possible. However, the office did not agree with the proposal. It informed audit that TPM is
not possible due to prevailing insecurity and access challenges in gang-controlled areas. The
office stated that TPM staff would also be susceptible to attacks by gangs that control parts of the
country and any information they provide may not reliable. Instead of TPMs, the office indicated
that it would continue to use its own staff to conduct programme monitoring whenever access was
possible. In view of the explanation by the office, the audit did not make a specific
recommendation related to programme monitoring.
3. Resource mobilization
Medium
Haiti CO is heavily reliant on funding from Other Resources (OR) and Other Resources
Emergency (ORE), but the structure and the staffing level of the fundraising function are not
commensurate with the expectations. There is a risk of inadequate funding for the Country
Programme that might compromise the achievement of planned results.
Haiti is heavily reliant on Other Resources (OR) and Other Resources Emergency (ORE) funding
to support implementation of planned activities. In 2020-2021, the planned budget for OR and
ORE amounted to US$ 256 million, representing 97 per cent of the total planned budget (US$
263 million). To meet the remaining funding requirements, the office had prepared a resource
mobilization strategy which it had broken down into annual action plans. In 2021, the office
10
mobilized US$ 15 million of OR, about 75 per cent of the target, and US$ 17 million of ORE, about
14 per cent of the target. The unfunded proportion of the 2022 RWP was high, about 77 per cent
for Nutrition, 86 per cent for Education and 100 per cent for Child Protection.
The office indicated that the Resource Mobilization unit was understaffed, making it challenging
to meet the increased workload and the need for aggressive outreach and close technical support
with the programme sections. The staff support to resource mobilization included a Partnership
Specialist and a Donors Relations Specialist on a temporary appointment, both of whom were
assigned to the Monitoring and Evaluation section. In 2022, the office managed 33 donors,
monitored 61 grants and submitted 93 donor reports.
Inadequate funding of the Country Programme may compromise the achievement of planned
results. For example, due to lack of funding, only 48 out of a planned 150 schools were
constructed in 2022. This suggested about 30,000 children were unable to attend school. The
audit noted that the programme had only mobilized about US$ 5 million against a planned budget
in the signed work plans of US$ 58.9 million.
AGREED ACTION
The office agrees to strengthen the existing resource mobilization structure through staffing
that is commensurate with the resource mobilization workload.
Staff Responsible: Representative and Human Resources Manager
Implementation Date: March 2023
4 Advocacy
Medium
Lack of a structured advocacy strategy posed a risk that issues affecting children were not
adequately raised with policymakers and that advocacy activities were not sufficiently focused
on key themes or supported by adequate evidence.
The Country Programme Document (CPD) pointed to specific areas where advocacy would be
used to advance children rights. These areas included effective allocation of resources in the
health sector, systematic birth registration at all health
centres, the adoption and promulgation of a law
guaranteeing adolescents access to HIV prevention
The 2020-2023 advocacy
and reproductive health services, increased budget
strategy was still at the draft
allocation to the WASH sector and data collection
stage, because of competing
relating to child protection and management that was
priorities
meant to be mainstreamed into relevant existing
sectoral routine information systems.
The office prepared a 2020-2023 Advocacy Strategy with a focus on children victims of violence
as well as a 2022 Communication Strategy which included advocacy priorities. At the time of the
audit the 2020-2023 Advocacy Strategy remained in a draft stage because of other competing
priorities, including successive emergencies, the COVID-19 Pandemic and civil unrest. The audit
review noted that neither document met the requirements for effective advocacy as set out in the
UNICEF advocacy toolkit. Missing were an articulation of the specific and measurable advocacy
results, specific messages for each targeted decision-maker, definitions of the motivations of
target audiences as well as the identification of the appropriate messengers and evidence needed
to sway those audiences.
These gaps in the Advocacy Strategy risked that issues affecting children were not raised among
policymakers in a structured way and that advocacy activities were not focused on key issues or
11
supported by evidence and sufficient budgetary resources. The office recognized these
shortcomings and said that it would address them when finalizing the Advocacy Strategy.
The Committee on the Rights of the Child (CRC) noted that the inter-ministerial commission
relating to the implementation of the Convention was not yet operational. Furthermore, Haiti has
not ratified two additional protocols: on the involvement of children in armed conflict and on a
communications procedure. The Committee on the Elimination of Discrimination against Women
(CEDAW) recognized government efforts to establish an inter-ministerial coordination mechanism
but noted that the national gender equality policy and related action plan were not adequately
funded. These issues were still pending, and the office has not, so far, advocated with the
Government to address them. The audit could not determine the reason. A Government partner
that the audit team met with confirmed the need to advocate for the implementation of CRC and
CEDAW recommendations because they would create the conditions to further advance the rights
of children.
AGREED ACTION
The office agrees to finalize and implement its advocacy plan in line with UNICEF organizational
guidance. The advocacy plan will include plans to ensure that the advocacy objectives of the
Country Programme are fulfilled and include the implementation of the recommendations of
CRC and CEDAW.
Staff Responsible: Representative, Chief of sections and Chief of Communication
/ HR Manager
Implementation Date: April 2023
5. Evaluation
Medium
The office did not have a plan to strengthen the Government’s evaluation capacity and has not
ensured that programmes and initiatives are designed in a way that permits their evaluation at a
later stage. These gaps risk that the Government might not generate the knowledge needed to
improve its action and strategies around children and women’s issues and that programme
decisions regarding scaling-up might not be properly supported.
The country office prepared a Costed Evaluation Plan (CEP) for the 2017-2021 Country
Programme. The audit review of this plan showed the following areas for improvement:
Capacity building of national evaluation capacity: Although
UNICEF’s 2018 evaluation policy requires that country-level
Programmes and
costed evaluation plans include provisions for strengthening
initiatives should be
national evaluation capacities, the CO’s 2019 revised version of
designed in a way that
the CEP did not include any support for the national evaluation
permits evaluation at a
function. The Government entity in charge of the evaluation
later stage
function (External Cooperation Direction within the Ministry of
Planning and External Cooperation) did not have the technical
capacity to fulfil its responsibilities. The CO did not conduct any capacity-building in the area of
evaluation during the period under audit. The office said that it was not a priority.
The Government’s limited capacity to evaluate its programmes and investments means that it
does not generate the knowledge needed to improve its actions and strategies, particularly those
related to children and women.
12
Evaluability of programmes and initiatives: As per the 2018 evaluation procedure, “Country
Representatives should ensure that programmes and initiatives are designed in a way that
permits evaluation at a later stage (founded on well-defined objectives, supported by a theory of
change, have baseline information)”. The CO had implemented a number of initiatives in various
programmes such as Nutrition and Education. In its 2021 year-end RAM, the CO reported that
more emphasis should be put on systematically documenting and using evidence from pilot
initiatives. Pilot projects with the potential for scaling have to show impact and be backed with
sound evidence. However, no process in the office exists to systematically ensure that these
initiatives are designed in a way that permits evaluation at a later stage. Thus, there is the risk
that the office might not have the needed information to draw lessons, or whether to scale-up or
an initiative at some later stage.
AGREED ACTION
The Office agrees to:
i.
Engage with the relevant Government counterpart – the Ministry of Planning - and
within the Costed Evaluation Plan include provisions for strengthening national
evaluation capacity.
ii.
Establish a process to ensure that new initiatives/approaches are designed in a way
that will allow their evaluability in the future.
Staff Responsible: Deputy Representative, Programme and Chief of PME
Implementation Date: April 2023
6. Prevention of sexual exploitation and abuse (PSEA)
Medium
The PSEA action plan did not articulate specific results indicators, designate responsible staff or
indicate budgets where funds would be drawn from. All this made it difficult to reflect the action
plan’s activities within relevant sectoral workplans where funding could have been secured. In
addition, management did not monitor the implementation of this action plan. These oversights
pose a risk that planned results may not be achieved.
The office had established three dedicated PSEA positions, including one Specialist and two
Officers. It has completed SEA evaluations of its CSO
partners and has closely monitored the completion by
staff of the mandatory PSEA online course. The office
SEA allegations, given the
was the first agency to join the inter-agency community
operating environment marked
feedback mechanism led by WFP. The office has also
by violence and multi-layered
provided support to RCO on PSEA Coordination and
emergencies, were
other technical matters.
significantly under-reported. In
2022, only one alleged SEA
case was reported.
In an operating environment marked by violence and
multi-layered emergencies, SEA allegations have been
significantly under-reported. For example, up to August
2022, only one alleged SEA case was reported, which the survivor referred to the relevant
implementing partner (IBESR). To understand the reasons for such widespread under-reporting
the office organized two surveys, one through U-Report and the other utilizing Ground Truth
Solutions (GTS). Results of these surveys formed the basis for an office-wide PSEA work plan
including internal and external activities focusing on community engagement, awareness-raising
and mobilizing U-Reporters.
13
The audit noted that the 2022 PSEA action plan had shortcomings. It did not articulate specific
results indicators, designate responsible staff or allocate a budget. These omissions made it
difficult to reflect the action plan activities in the relevant sectoral workplans where funding could
have been secured.
The implementation status of PSEA activities was monitored through different platforms, including
Power BI (for staff training completion), eTools, inSight and KPIs (for risk assessment of partners)
and PSEA questions added to Programmatic Visit Report template (to increase ownership by
Program sections). However, the PSEA action plan implementation was not monitored by relevant
management, such as the programme coordination team or the CMT. Thus, there is a risk that
planned activities may not be implemented as intended and that bottlenecks will not be detected
and addressed in a timely way.
AGREED ACTION
The office agrees to ensure that the PSEA action plan includes all the required information,
that its activities are reflected in relevant workplans, and that management closely monitors
the status of its implementation.
Staff Responsible: PSEA Specialist and Section chiefs (monitoring by PMT/CMT)
Implementation Date: February 2023
7. Risk management
High
The office’s risk assessment was inadequate. For example, the Office did not identify potential
root causes of the risks it had identified, making it difficult for it to be reasonably assured of the
adequacy and appropriateness of the mitigating measures it had put in place.
The residual risks were not
rated, therefore, there was
no assurance that the office
was focusing its resources
on addressing the highest
residual risks.
Country offices should manage risks to the implementation
of programmes in a structured and systematic manner.
The organization’s Enterprise Risk Management (ERM)
policy requires that offices perform an annual risk
assessment to identify and assess their risks in line with
the risk structure developed by HQ. This assessment must
articulate a mitigation plan for each significant risk which
should address the root causes of the risk in question and
ensure that any residual within acceptable risk tolerance
levels.
The office has a risk management and audit committee, chaired by the Deputy Representative
for Operations and consisting of staff representing programme, operations and field offices. This
committee coordinated the update of the office’s 2022 annual risk assessment and presented it
for endorsement at the May meeting of the CMT. The assessment included three very high
inherent risks. These included economic deterioration, child poverty and access to water. Also
identified were fifteen high inherent risks. Mitigation measures were identified for most of these
risks.
The audit reviewed the risk assessment and noted significant omissions. For instance, root
causes were not clearly identified. Rather, they were described in terms of likelihoods (possible,
likely, almost certain), making it difficult to assess the adequacy of the related mitigating
measures. Further, the audit also noted inadequate explicit links between the mitigation measures
and corresponding risks. For example, the risk “Disruptive incidents, gang violence and civil
unrest prevent school opening and/or children attendance” was expected to be mitigated by
“including mitigation measures into workplans and strengthening resource mobilization”.
14
The audit also noted that residual risks ratings were not mentioned, suggesting that the Office
had not evaluated its mitigating measures. Failure to adjust risk rating based on evaluation of
mitigating measures may result in making investment in unnecessary controls.
The audit noted that the review and approval of the annual risk assessment lacked a robust quality
process.
AGREED ACTION
The office agrees to identify root causes of the risks and ensure adequate and appropriate
mitigating measures in line with those root causes are put in place to reduce significant risks to
acceptable levels.
Staff Responsible: The Country Management Team
Implementation Date: December 2022
8. Security
High
The security improvement plan was not budgeted and responsibility for the implementation of
recommendations in the plan was not assigned, increasing the risk that the office’s security needs
may not be promptly and effectively addressed. Given that the Office operates in a constantly
changing and heightened security risk environment, these deficiencies may negatively impact on
the effectiveness of the safety and security measures it implements.
Security management: The office conducted security-risk management (SRM) assessments of
all its properties. The security unit prepared a
consolidated security improvement plan to implement
For UNICEF there were two
recommendations stemming from these assessments.
outputs rated as
This plan included 29 actions of which 11 were completed
as of end of August 2022. There were eight actions
programme criticality one
pending decisions by management. Five actions had yet
and four outputs rated as
to begin. This plan was not budgeted and responsibility
programme criticality two.
for the implementation of its recommendations was not
This means that only these
designated by management. The office said that the
activities could be
implementation of the improvement plan was monitored
implemented in very high
during operations team meetings, but the audit could not
and high residual security
find evidence to support this assertion.
risk areas respectively.
A new SRM was prepared by UNDSS for the period 1
April 2022 to 30 January 2023. The SMT issued its findings on 15 August 2022. According to this
SRM, the residual risk level was rated “extreme” for crimes and “high” for civil unrests and
hazards. The office has yet to plan and implement security assessments of all its premises to
verify conformity with this new SRM and to take action to address potential gaps. Given the
significance of the security threats and volatile work environment, any and all security gaps must
be closed as soon as possible to avoid exposing staff to unnecessary security threats.
Programme criticality assessment 5 : The UN Country Team in Haiti along with the United
Nations Integrated Office in Haiti (BINUH) jointly completed a programme criticality assessment
5
Programme criticality framework is available at https://www.unsystem.org/content/programme-criticality-framework
15
for the period 1 August 2021 to 31 July 2022. This was later extended until 31 December, 2022 6.
As a result of this exercise, each output identified by the respective Agencies, Funds and
Programmes (AFPs) was rated according to its contribution to the UN strategic priorities and to
its likelihood of implementation. These ratings, combined with the residual risks defined by the
security risk assessment in a specific region, determined the activities that staff could carry out
within acceptable risk tolerance levels. For UNICEF there were two outputs rated as “programme
criticality one” and four outputs rated as “programme criticality two”. This means that only these
activities could be implemented in very high and high residual security risk areas.
AGREED ACTION
The Office agrees to:
i.
Plan and implement security assessments to ensure conformity with the new security
risk assessment.
ii.
Establish and implement an action plan to address identified gaps, and ensure that
responsibilities are assigned, the required is funds are provided, and implementation
of the plan is monitored regularly at the level of the Country Management Team.
Staff Responsible: Security Manager, Construction Manager, and Administration Specialist
Implementation Date: March 2023
9. Temporary staff
Medium
High number of temporary staff raises the question of the sustainability of the office’s staffing
structure and can have a negative impact on staff morale.
As of 29 August 2022, the
office staff complement
was comprised of 96
regular staff and 34
temporary staff, meaning
that 26 percent of the
current office staff was
temporary.
A temporary appointment is a time-limited appointment
which may be issued for less than one year (i.e., for 364
days or less) to meet seasonal or peak workloads and
specific short-term requirements. The office used this type
of appointment extensively in the past three years in order
to respond to successive national emergencies.
As of 29 August 2022, the office staff complement was
comprised of 96 regular staff and 34 temporary staff,
meaning that 26 per cent of the current office staff was
temporary. At the Les Cayes field office, the office
structure 7 included 10 approved positions and 21
temporary staff, meaning that 68 per cent of the field office staff structure was temporary. Such a
fluid human resources structures raises the question of sustainability, particularly since one
reason for establishing field offices has been to strengthen decentralization. Furthermore,
feedback from the staff association and staff embedded in field offices indicates that the high
number of temporary staff is having a negative impact on staff morale.
A temporary appointment may be extended beyond its initial length of 364 days only in specific
circumstances. Moreover, extensions should not exceed twelve months, for a total of 729 days.
Recommendations for such extensions must be accompanied by written justifications from direct
supervisors and are subject to satisfactory service and availability of funds. The audit review noted
that there were cases of temporary appointments that were extended beyond the maximum period
(including for a Child Protection Specialist, Child Protection Officer and Driver), and that the
recommendation for extending these temporary appointments was based solely on the availability
6
7
UNCT meeting of 25 August 2022
Les Cayes field office accountability framework revised in May 2022.
16
of funding. There was no other justification to extend the temporary appointment as per the
specific circumstances defined by the Organization.
AGREED ACTION
The Office agrees to:
i.
Strengthen its process of extension of temporary appointments, to ensure that
programmatic and/or operational justifications are provided and cleared by
management in line with organizational guidance.
ii.
Establish a clear strategy that articulates a long‐term regular staffing solution for field
offices.
Staff Responsible: HR Specialist and Chiefs of Sections. Supervisors, and Head of Office
Implementation Date: March 2023
10. Partnership management
Medium
The CO mainly uses direct methods for selecting NGO partners, missing the opportunity to identify
new partners or approaches. In doing so, it misses the opportunity to undertake comparative
analyses of different strategies and costs to achieve the desired results for children while ensuring
best value for money.
Out of 22 NGO partners that
the office worked with
during the audit period,
only two were selected
using a competitive
process.
UNICEF procedures encourage the use of open,
competitive, selection methods to identify NGO partners
providing the best comparative advantages for achieving
particular results.
The audit noted that out of 22 NGO partners that the office
worked with during the audit period, only two were selected
using a competitive process. This is a missed opportunity
to identify new partners and approaches and to undertake
a comparative analysis of different strategies and costs to
achieve the desired results for children.
Although the office had processes for more transparent selection and engaging with NGO
partners, it said that it did not apply these processes because of factors such as the short duration
of grants and the overall national emergency context. However, the office could have undertaken
a competitive selection process for regular programme activities, especially considering it had
signed regular PDs with the 22 above mentioned NGOs.
AGREED ACTION
The office agrees to encourage open selection for the identification of CSO partners where
possible in order to obtain the best value for money, using UN Partner Portal as applicable.
Staff Responsible: Dep Rep Programme /PRC chair (monitored in PMT/CMT meetings).
Implementation Date: March 2023
11. Liquidation of cash transfers
Medium
17
Long outstanding cash transfers poses the risk that activities have not been completed as planned
and increases the risk of funds not being used for their intended purposes or lost to fraud.
As of August 17, 2022, the office had outstanding DCT of
US$ 6.7 million, of which US$ 742,108 (11 per cent) was
The office did not record
outstanding between six and nine months and US$
DCTs with low probability
127,302 (two per cent) for more than nine months. This
of recovery.
poses the risk that activities have not been completed as
planned and/or that cash had been misused or lost to
fraud. It also creates a risk that relevant IPs lacked
required knowledge about UNICEF DCT procedures. In
one case, a government partner (the Ministry of Education) informed the audit team that its
Department of West had an outstanding DCT for over nine months because they did not know
how to liquidate the DCT received. The office pointed out that there is a high turn-over of IP staff
which was one among several reasons for such capacity gaps. However, closer collaboration with
IPs during the implementation of programme activities could have uncovered the need for
capacity building for specific partners.
Further, the audit noted that the office did not record DCTs with low probability of recovery, which
is contrary to acceptable accounting standards and UNICEF accounting policy. For example, a
DCT of US$ 32,350 to the NGO IDETTE was pending for 18 months with no possibility of
recovery.
AGREED ACTION
The office agrees to ensure that:
i.
Staff of new implementing partners are trained on HACT procedures.
ii.
A system is established to ensure timely impairment of doubtful liquidations.
Staff Responsible: Dep Rep Operation and Internal Control P3 position and HACT Officer
and Internal control P3 position
Implementation Date: January 2023
12. Humanitarian cash transfers
Medium
Information on humanitarian cash transfer beneficiaries was in some cases transferred without
using any data-security measures, raising the risk that beneficiaries’ personal data could be
exposed to unauthorized disclosure, destruction, theft, or alteration .
During the period between 2021 and August 2022, the office disbursed US$ 2.9 million in
humanitarian cash transfers to 8,000 households affected by the 2021 earthquake. The
beneficiaries were identified by the Government through their Ministries of National Education
and Social Affairs & Labor, which shared a list of beneficiaries with UNICEF which in turn shared
that list with two NGO partners that verified the existence and eligibility of would-be beneficiaries.
Upon verification, UNICEF transferred cash to the beneficiaries via a financial service provider
(FSP). The office established a partnership with an NGO to verify that cash was disbursed as per
the list provided by UNICEF to the FSP.
18
The office was aware that for cash-based interventions the
protection of the personal information of beneficiaries was
Data-security measures
of paramount importance. However, this audit reviewed a
include password protected
sample of six communications between humanitarian cash
and encrypted messages
transfer implementing partners and the financial services
provider and noted that the personal information of
beneficiaries was shared with no security precautions. The
audit determined that three transfers occurred without using any data-security measures, such as
password protection or encrypted messages. While the concerned partners had signed data
protection clauses, there is a risk that beneficiaries’ personal data could be exposed to
unauthorized disclosure, destruction, theft or alteration, which in turn could harm the beneficiaries
and/or UNICEF’s reputation.
AGREED ACTION
The office agrees to safeguard the personal identifying data of beneficiaries of humanitarian
cash transfers using passwords and encrypted messages.
Staff Responsible: Chief social policy and Social Policy specialist
Implementation Date: March 2023
13. HACT assurance activities
Medium
Assurance activities were not risk-based and the use of eTools was not optimized, resulting in a
risk that cash transfers may not be used as intended.
Programmatic visits. The audit noted that there no programmatic visits were conducted for 19
out of 50 high risk partners in 2021 and for 28 out of 51
high risk partners in 2022, up to August. This poses the
risk that disbursed funds could be misused or lost. The
No spot checks planned
main reason such visits were not performed was on-site
and implemented in 2021
inaccessibility due to security issues .
for four high risk IPs that
received US$ 1.8 million.
Planning of spot checks: The audit noted that there were
no spot checks planned and implemented in 2021 for four
high risk IPs which received more than US$ 100,000 each
(total of US$ 1.8 million). At the same time, the office
completed spot checks for partners which received less than US$ 50,000 in 2021. Spot checks
for high-risk partners and those receiving more than US$ 100,000 per year should have been
prioritized. Failing to do so create a risk that the office could not provide adequate assurance that
cash transferred was used for intended purposes.
Quality of spot checks: The audit team assessed the quality of six sampled spot checks and
noted that changes in IP’s internal controls and bank reconciliations were not systematically
reviewed in three cases out of six. The audit reviewed the spot check template used and found
that it did not include a field for documentation of internal controls as per the recommended
template.
Follow-up of assurance recommendations: The office did not adequately use eTools to track
and monitor the implementation of high-priority recommendations resulting from HACT assurance
activities. The audit noted that 26 high-priority recommendations from assurance activities were
overdue as of August 27, 2022. This poses the risk that the correct actions may not be
implemented by IP’s, resulting in ineffective implementation and/or loss of UNICEF’s assets.
19
In addition, the audit noted that some of the priority recommendations of assurance activities were
not documented in eTools for tracking their implementation. For example, the recommendations
of two programmatic visits of a sample of six reviewed by the audit, were not documented in etools for follow-up and tracking.
AGREED ACTION
The office agrees to:
i.
Ensure a risk-based approach in planning and implementing assurance activities
appropriate for the country context, including by prioritizing appropriate assurance
activities for high-risk partners and partners that receive significant amount of DCT.
ii.
Review the template used for spot checks and update it to capture minimum
requirements appropriate to adequately manage key risks.
iii.
Ensure that all assurance activity recommendations that require follow-up are
documented in eTools and the status of their implementation is updated regularly.
Staff Responsible: Deputy Representative and Section Chiefs (monitoring in PMT/CMT) and
HACT Officer
Implementation Date: March 2023
14. Supply management
Medium
Incomplete supply plans and lack of distribution plans raises the risk of not providing the inputs
required to the achievement of planned results.
As of August 2022, supplies
amounting to US$ 262,000
intended for direct delivery to
IPs were held in UNICEF
warehouse, resulting in
reduced warehouse capacity,
additional costs for transport
and delay in delivery.
Supply planning: Supply plans prepared by the office
in 2021 and 2022 were not complete. For example,
construction of 38 schools and one health center, for a
total amount of US$ 6.4 million in 2021 and 2022, were
not included in either the regular or in the emergency
supply plans. The audit could not determine the cause of
these omissions. This creates a risk of inadequate
planning and monitoring.
Distribution plans: Offices are required to have
adequate and complete distribution plans for procured
supplies to ensure their timely, cost effective and
accurate delivery. The audit reviewed a sample a five sales orders for direct delivery to
implementing partners and found that program sections did not provide related distribution plans.
This obliged the office to store material in its warehouses, resulting in reduced warehouse
capacity, additional costs for transport and delays in delivery. As of 25 August 2022, supplies
amounting to US$ 262,000 that were intended for direct delivery to IPs were still being in UNICEF
warehouse.
Management of user-access rights in SAP: The level of logical access in SAP for roles and
functions related to supply, logistics and warehouse management were not accurately assigned
thereby exposing the office to conflicting logical access rights that may result in unauthorized
creation, alteration and/or distortion of transaction/process flows. For example, Procurement L1
authority, which is usually granted to supply staff to allow them to create and amend institutional
contracts and to do solicitation, was given to programme and operations associates.
AGREED ACTION
20
The office agrees to:
i.
Review the reasons for incomplete supply plans and address them.
ii.
Ensure that distribution plans are prepared along with the sales orders.
iii.
Match relevant staff to expected logical access rights in SAP and provide delegated
authorities accordingly.
Staff Responsible: Programme Sections chiefs and Chief of Supply and Logistics.
Implementation Date: March 2023
15. Warehouse management
High
Gaps in the access to and security of the warehouse, as well as gaps in the conditions of storage
and inventory accounting, pose the risk of waste and the loss of resources that are needed to
achieve planned results.
The UNICEF warehouse (Cazeou warehouse) was located in an area that was rated as a “red
zone” high security risk. The warehouse had no reliable
internet connection and no access to a reliable mobile
Supplies worth US$ 761,075
network due to being near a gang-controlled area. This
were dispatched but
limits accessibility to the warehouse by UNICEF staff,
delivery was recorded for
transporters, handlers and implementing partners,
causing difficulties in management of UNICEF controlled
more than 6 months
inventories.
During a visit to the warehouse, the audit noted the following areas that needed strengthening.
The warehouse did not have temperature control devices to ensure proper storage of store
supplies that are temperature sensitive. Medical supplies that require temperature regulation
were noted to be stored in the warehouse. This is a risk that temperature sensitive supplies
can spoil even before their expiring dates and cause harm to beneficiaries and to UNICEF’s
reputation.
Regular stock was not separated from emergency stock thus making it difficult for warehouse
staff to distinguish regular stock from emergency materials. This poses a risk that responses
by the CO to emergencies may be delayed.
As of August 2022, the office had supplies worth US$ 761,075 in-transit (dispatched but
whose delivery was not yet recorded in the system) for more than 6 months. The office
indicated that the reason for such exceptions was failure to acknowledge receipt of supplies
by the programme section in VISION SAP once supplies had been received by implementing
partners. This poses the risk that the inventory report and related dashboard may be
inaccurate and thus not allow management to accurately confirm what supplies have been
actually received and what might have been lost or delayed before being received by
implementing partners. These omissions can prevent management from taking timely
corrective actions as needed.
Supplies of eight biomass incinerators valued at US$ 77,000 had not been recorded in the
system. The office said that these supplies were expected to be delivered directly to the
Ministry of Health, but this did not happen because of lack coordination, at the planning stage,
between the programme section, the supply/logistic and construction units and the respective
Ministry/IP. As a result, they were stored in a UNICEF warehouse and still remain under
UNICEF control.
21
The office did not comply with the policy that requires offices to submit to the Property Survey
Board (PSB) a list of obsolete/impaired items and/or surplus for disposal at least once a year.
The office had impaired inventory amounting to US$ 40,439 that had not been submitted to
the PSB for disposal processing. This risked that such inventory will totally be lost or misused
This was because the program section could not submit the impaired list to the PSB through
the online platform (ePSB) that should have been rolled out in June 2021.
Following the completion of the audit fieldwork, the office informed OIAI that it had identified a
new location for the warehouse and supplies have been moved to this new location. The audit
has not verified the condition of the new warehouse and therefore cannot comment on the
suitability of the new location for the storage of UNICEF supplies.
AGREED ACTION
The office agrees to:
i.
Ensure that temperature-sensitive supplies are stored within manufacturer’s
recommended temperatures and that emergency supplies are stored separately from
regular programme supplies.
ii.
Ensure programme staff promptly update VISION SAP once supplies are received by
intended implementing partners or beneficiaries.
iii.
Finalize the roll-out of ePSB and ensure that obsolete and damaged supplies are
reviewed in a timely way and disposed of.
Staff Responsible: Deputy Representative for Operations, Chief Supply and Logistics and
admin Specialist
Implementation Date: March 2023
22
APPENDIX
Definitions of Audit Observation Ratings
To assist management in prioritizing the actions arising from the audit, OIAI ascribes a rating to
each audit observation based on the potential consequence or residual risks to the audited entity,
area, activity or process, or to UNICEF as a whole. Individual observations are rated as follows:
Low
Medium
High
The observation concerns a potential opportunity for improvement in
the assessed governance, risk management or control processes.
Low-priority observations are reported to management during the
audit but are not included in the audit report. Action in response to
the observation is desirable.
The observation relates to a weakness or deficiency in the assessed
governance, risk management or control processes that requires
resolution within a reasonable period of time to avoid adverse
consequences for the audited entity, area, activity or process.
The observation concerns a fundamental weakness or deficiency in
the assessed governance, risk management or control processes
that requires prompt/immediate resolution to avoid severe/major
adverse consequences for the audited entity, area, activity or
process, or for UNICEF as a whole.
Definitions of Overall Audit Conclusions
The above ratings of audit observations are then used to support an overall audit conclusion for
the area under review, as follows:
Satisfactory
Partially
Satisfactory,
Improvement
Needed
The assessed governance, risk management or control processes
were adequate and functioning well.
The assessed governance, risk management or control processes
were generally adequate and functioning but needed
improvement. The weaknesses or deficiencies identified were
unlikely to have a materially negative impact on the performance
of the audited entity, area, activity or process.
Partially
Satisfactory,
Major
Improvement
Needed
The assessed governance, risk management or control processes
needed major improvement. The weaknesses or deficiencies
identified could have a materially negative impact on the
performance of the audited entity, area, activity or process.
Unsatisfactory
The assessed governance, risk management or control processes
were not adequately established or not functioning well. The
weaknesses or deficiencies identified could have a severely
negative impact on the performance of the audited entity, area,
activity or process.
23
Office of Internal Audit and Investigations
3 United Nations Plaza, East 44th St.
New York, NY 10017
www.unicef.org/auditandinvestigation
24