Pwojè Alyans pou Pwoteksyon Timoun: Plan Fèmti
Rezime — Plan fèmti akò koperasyon Alyans pou Pwoteksyon Timoun, ki fini sèz mwa anvan lè.
Dekouve Enpotan
- Records a project end sixteen months early: scheduled 25 July 2019, requested 15 March 2018.
- The award was US$6,049,908 under cooperative agreement AID-521-A-16-00004, signed 26 July 2016.
- Summarises the five research streams delivered in year one, which are the four published reports and a global systematic review.
Deskripsyon Konple
Plan fèmti akò koperasyon Alyans pou Pwoteksyon Timoun, ki fini sèz mwa anvan lè. Yon sibvansyon US$6,05 milyon sou twa zan yo te siyen an jiyè 2016 fèmen an mas 2018 olye jiyè 2019, epi se plan fèmti a ki di sa: se sèl dokiman nan dosye a ki di travay la kanpe olye l fini.
Teks Konple Dokiman an
Teks ki soti nan dokiman orijinal la pou endeksasyon.
Title: Alliance for the Protection of Children Project Closeout Plan
Cooperative Agreement No.: AID-521-A-16-00004
Recipient: American Institutes for Research (AIR)
Funding value: $6,049,908.00
Project Start Date: July 26, 2016
Scheduled Project End Date: July 25, 2019
Requested Project End Date: March 15, 2018
Recipient’s Contacts:
Amy West Jose Palacios
AIR Home Office Project Director AIR Senior Pricing and Contracts Specialist
International Policy, Practice and Systems Change 1000 Thomas Jefferson Street, NW
1000 Thomas Jefferson Street, NW Washington, DC 20007
Washington, DC 20007 Tel: +1 (202) 403-6543
Tel: +1 (202) 403-5961 E-mail: jpalacios@air.org
E-mail: awest@air.org
Recipient’s Authorized Representatives:
Jerrold Keilson Joseph Wagner
Vice President Vice President, Contracts, Grants, and Procurement
International Policy, Practice and Systems Change 1000 Thomas Jefferson Street, NW
1000 Thomas Jefferson Street, NW Washington, DC 20007
Washington, DC 20007 Tel: +1 (202) 403 5292
Tel: +1 (202) 403 6091 E-mail: jwagner@air.org
E-mail: jkeilson@air.org
Recipient’s Local Representative:
Patrick Camille
Chief of Party
11 Rue Oge, Platinum Plaza, 2nd Floor
Petion-Ville, Haiti
Tel: 509-3721-2506
E-mail: pcamille@air.org
1
Contents
1.0 PROGRAM ACTIVITIES ......................................................................................................................................4
1.1 Background..........................................................................................................................................................4
1.2 Analysis of Progress to Date ................................................................................................................................8
2.0 PIPELINE ANALYSIS ...........................................................................................................................................8
2.1 Leverage ..............................................................................................................................................................9
3.0 PROGRAM REPORTS ..............................................................................................................................................10
3.1 Quarterly Financial Reports (SF425) ..................................................................................................................10
3.2 Technical/Program Reporting ...........................................................................................................................10
4.0 SUBCONTRACTS/SUB-AWARDS .............................................................................................................................10
5.0 INVENTORY AND PROPERTY DISPOSITION PLAN ...................................................................................................10
5.1 Non-Expendable Property with a purchase price over $5,000 transferred to or acquired under the
Cooperative Agreement ..........................................................................................................................................10
5.2 Expendable Property with a purchase price under $5,000 acquired under the Cooperative Agreement or
transferred from another Federally-Funded Project ..............................................................................................10
6.0 PERSONNEL PHASE-OUT ........................................................................................................................................11
6.1 Cooperating Country National Staff ..................................................................................................................11
7.0 OTHER GENERAL DEMOBILIZATION PROCESSES ...................................................................................................11
7.1 USAID Field Office- Port-au-Prince ....................................................................................................................11
2
Acronyms and Abbreviations
AIR American Institutes for Research
BPM La Brigade de Protection des Mineurs
APC Alliance for the Protection of Children
CRC United Nations Convention on the Rights of the Child
CNLTP National Committee to Combat Human Trafficking
GoH Government of Haiti
IBESR Institut du Bien-Être Social et de Recherches
M&E Monitoring and Evaluation
PD Positive Deviance
RQA Rapid Qualitative Assessment
SNPE National Child Protection Strategy
UNICEF United Nations Children's Fund
UNHCR The Office of the United Nations High Commissioner for Refugees
USAID United States Agency for International Development
VACS Violence Against Children Survey
3
1.0 PROGRAM ACTIVITIES
1.1 Background
The Alliance for the Protection of Children (APC), or Alliance pour la Protection des Enfants was a U.S. Agency for
International Development (USAID)-supported activity designed to be implemented over the course of three years
by the American Institutes for Research (AIR). The APC aimed to support strategic objectives on the part of USAID
and the Government of Haiti (GoH) to strengthen the protection of vulnerable children. The APC worked to ensure
that its work supported the Haitian National Child Protection Strategy (SNPE) through a plan of work that would
strengthen activities under Objectives 3, 4, and 5, as well as reinforce laws that govern the protection of children in
Haiti. AIR in the course of its 19 months of operation worked in partnership with the Institut du Bien-Être Social et
de Recherches (IBESR), Brigade de Protection des Mineurs (BPM), National Committee to Combat Human Trafficking
(CNLTP), Lumos, UNHCR, UNICEF, Université d’Etat d’Haiti (UEH), Zanmi Lasante (ZL), Combite pour la Paix et le
Développement (CPD), Restavèk Freedom/OPREH (RF), ENPAK, Terre des Hommes and others. Protection of children
from abuse, exploitation and violence was the priority of this program; this was realized through the design of project
activities and deliverables that were centered on the premise of reducing violence against children; mitigating the
trafficking and forced labor of children; protecting unaccompanied and separated migrant, stateless, and refugee
children; integrating street children into safer learning and care spaces; preventing the separation of children from
their families; and exploring alternative care and protection services. The Alliance for the Protection of Children had
four distinct phases, of which the first and second were realized prior to USAID’s request for close-out: (1) Research;
(2) Design of Pilot Interventions; (3) Implementation of Pilot Interventions; and (4) Evaluation and Learning.
OUTCOMES ??
Year 1 Activities
AIR believes that development interventions must be based on solid foundational research. The methodology and
approach to research proposed as part of Year 1 project activities intended to ensure that the design and
implementation of any pilot intervention would be contextually-relevant, evidence-based and owned by the
communities involved. The research proposed in Year 1 covered individual, family, community and system level
attitudes, behaviors and responses to violence against children and identified those factors that were mitigating or
perpetuating cycles of violence. OUTCOMES ?
In Year 1, the Team gathered evidence by conducting five different streams of research. 1 First, a systematic review
was conducted of existing child protection models and behavior change communications literature globally. In
addition, the Team conducted four different streams of community-based research: rapid qualitative assessment
of existing child protection activities in target communities, ethnographic/anthropological cultural models and
positive deviance (PD) research, and a scan of influencers/followers of social and broadcast media. Together, the
five streams of research provided the evidence-base for working with stakeholders to identify and prioritize pilot
interventions for roll-out in Years 2 and 3 of the project.
WAS SUPPOSED TO "IDENTIFY" INTERVENTIONS BASED ON RESEARCH BUT USAID HAD ALREADY PLAN FOSTER CARE & MESSAGING
The research conducted in Year 1 reflected two fundamental elements of the project – 1) leveraging local assets
within Haiti and 2) building the capacity of local organizations by strengthening existing work or processes. AIR
worked with the Universite d’Etat d’Haiti (UEH) and three local subaward partners (ZL, CPD and Restavèk Freedom)
to design research protocols and implement the research. AIR provided several trainings with partners on research
theory, protocol development, data collection procedures according to the protection of human subjects, and
facilitation of the Co-InterpretationSM process. The following deliverables were implemented and achieved with
partners:
1. Identification of cultural models through in-depth interviews and analysis
1
AIR submitted all relevant protocols to AIR’s IRB process, and when not exempted as in the case of
Cultural Models Research, the protocols were submitted to the Comité d’Ethique which is Haiti’s internal IRB
system.
4
2. Determination of the presence of any existing PD practices
3. Mapping of the influencers and followers of broadcast and social media
4. Assessing the existence of existing child protection activities through a rapid qualitative assessment
Research Design
HOW DID THEY DO COMMUNITY BASED WHEN WORKING ONLY WITH FOREIGN NGOs?
The Team followed a research design that included a systematic review of existing literature, community-based
anthropological and ethnographic research for cultural models and positive deviance, mapping of broadcast and
social media followers and influencers, and a rapid assessment of existing child protection activities in target areas.
Three key questions were at the core of AIR’s research design and detailed in AIR’s project Scope of Work:
KEYWORD IS "IMPLICIT CULTURAL"
(Q1) What are the shared implicit cultural patterns of thinking in Haiti that structure understandings,
beliefs, and actions regarding the rights, development, and protection of a child?
Are there causal factors or predictors that guide who or what perpetuates or influences violence
(including, abuse, neglect, exploitation) or the separation of children from families and who or
what does not?
Are there causal factors or predictors that guide who or what prevents, protects or responds to
violence against children or their separation from families (examples of positive deviance)?
(Q2) Which larger societal, economic, political, and contextual factors are most ripe for change; what are
the most promising strategies for initiating such change; and which options are most feasible and confer
the greatest benefit in reducing violence against children and increasing alternative care, support and
protection options?
Which larger societal, economic, political, and contextual factors are barriers to change?
Understanding these, what are the most relevant and feasible prevention or protection system
strategies that need to be developed and implemented for the greatest impact (i.e., for large
numbers of children, most vulnerable children)?
EXISTING EVIDENCE (LET'S SEE THAT)
(Q3) What is the existing evidence regarding small- and large-scale interventions that prevent or respond
to any form of violence against children in Haiti or in similar developing country contexts?
Engage in a rapid evaluation in select locations in Haiti of existing child protection activities, PREVENT
including work done to prevent separation of children from their families, work to remove REMOVE EXTRACT
children from residential institutions, work to extract children from harmful child labor or SUPPORT
trafficking contexts, and/or work to support children in displaced or abandoned settings.
The cultural models research and to some extent the social and broadcast media mapping focused on answering the
first series of questions. The series of questions under Q2 were addressed by the rapid qualitative assessment,
positive deviance and systematic review. And the series of questions under Q3 were addressed by the systematic
review and rapid qualitative assessment work.
A Co-InterpretationSM workshop was developed as part of the third Advisory Committee meeting activity in Year 1
of the project. This workshop was envisioned to engage stakeholders in a substantive discussion of the five
research reports developed under Year 1 activities and allow for wider stakeholder thinking and feedback on the
prioritization of pilot interventions for Years 2 and 3 of the project based on the research reports. As such,
Advisory Committee standing and participating members were invited to participate in the meeting, as well as a
wider group of government, international and local non-governmental organizations, and community leaders. The
WHAT DATA INDICATED THE NEED FOR FOSTER CARE AND MESSAGING??
5
BASED ON THIS LIST THERE ARE NOT HAITIAN ORGANIZATIONS WORKING WITH TARGET CHILDREN
two-day workshop was attended by twenty-nine representatives of key stakeholders in the project.2 Key
stakeholders that attended the workshop were community leaders from project target communities in each of the
four departments selected by the Advisory Committee: Northeast, Southeast, West, and Artibonite; NGO and
Government members from La Brigade de Protection des Mineurs (BPM), Institut du Bien Etre Social et des
Recherches (IBESR), International Organization for Migration (IOM), Save the Children, Groupe d'Appui au
Rapatriés et Refugiés (GARR), Jesuit Service for Migrants (SJM), and Chapitre Haïtien de l’Association Internationale
des Femmes Juges (CHAIFEJ); standing and participating members from the United States Agency for International
Development (USAID), American Institutes for Research (AIR), Lumos, IBESR, United Nations High Commissioner
for Refugees (UNHCR), United Nations Children's Fund (UNICEF), Zanmi Lasante (ZL), Combite pour la Paix et le
Développement (CPD), and Restavèk Freedom. In addition, four representatives from the Mayor’s Office of Port-
au-Prince came to observe the workshop; one of whom was engaged as a participant in the workshop.
All five research reports were submitted to USAID Haiti for approval in July 2017 per the Year 1 Workplan timeline.
Resource partner: In Year 1, Lumos remained less than communicative with AIR. AIR attempted to establish a direct
line of communication with Lumos throughout the Year 1 period of activities both in order to coordinate on activities
as well on reimbursement of receipts from travel that were part of the project budget. In both cases, these attempts
to communicate went unanswered. AIR’s Project Coordinator in Haiti was able to maintain regular contact with
Lumos-Haiti’s representative on the ground. That said, decision-making seemed to be at the Lumos UK level. Lumos-
Haiti was invited to workshops held by the research team for NGO partner trainings and contributed to the design
of the rapid qualitative assessment protocol in 2016. Lumos was present at all the scheduled advisory committee
meetings held in September 2016, December 2016 and July 2017. In April 2017, Lumos point of contact, Amanda
Cox, agreed to establish a monthly call with AIR’s project director. After the initial direct AIR to Lumos call in April
2017, for which a positive way forward on communications and engagement were agreed upon, the designated
Lumos point of contact declined further opportunities to communicate on a regular basis, including as a follow up
to an evaluation deliverable for which AIR wrote to USAID to request an extension on Lumos’ behalf. Lumos was not
able to complete this work in time (end of Year 1 research activities), nor within the timeframe of the requested
extension (end of 2017). IN DEED HAITIANS WORKING FOR FOREIGN NGOS ARE CHRONICALLY POWERLESS
Year 2 Activities
As in Year 1, the team’s overarching goal in Year 2 was to leverage Haitian voices, experiences and knowledge as
well as existing evidence to inform and achieve the reduction and prevention of violence against children in Haiti.
Upon USAID’s assessment of the project in September 2017, it was recommended by USAID Haiti that AIR: (1)
increase its local staff to expand its field footprint, (2) strengthen the relationship with central government
authorities (IBESR, CNLTP and BPM), and (3) ensure that Years 2 and 3 implementation activities were aligned with
and complemented efforts to support the National Strategy for Child Protection (SNPE) and the work of the National
Committee to Combat Human Trafficking (CNLTP).
Following up on the lessons learned from Year 1 and the recommendations provided by USAID, the AIR Home Office
proceeded with the recruitment of a Chief of Party (COP), Deputy Chief of Party (DCOP), and a Technical Lead (TL),
and two Community Development Officers (CDOs). The COP and Technical Lead were strategically recruited for their
long-standing relationship with IBESR and the CNLTP. With these additions, the project’s organizational chart was
modified, roles and responsibilities of the staff were revised, and a new Workplan was conceptualized and drafted,
taking into account the recommendations of USAID.
From October to December, with the support of USAID Haiti, AIR was able to better engage central level
representatives of the Government of Haiti in project activities. From October to December, AIR engaged in four
working group meetings with representatives of IBESR, BPM and CNLTP. In addition to the SNPE, the project team
2
Please see Appendix A for the list of attendees that were present at the Advisory Committee Meeting
July 18-19, 2017.
6
ZANMI ANSWERS TO BOSTON, ENPAK WORKS FOR USAID
referenced the Violence Against Children Survey Plan (PAN/VACS) and the CNLTP Action Plan3 in order to build a
project Workplan for Year 2 that would reflect government priorities under the project Scope of Work. In addition
to government counterparts, the NGO partners discussed with USAID as subaward partners for Years 2 and 3
activities were: Zanmi Lasante, Restavèk Freedom, Terre Des Hommes-Lausanne (TDH-L) and ENPAK. All of these
organizations participated in more than one working group meeting with government representatives and
contributed to the Workplan. There were additional working group meetings held with partners to enhance the
design of project intervention plans under the Year 2 Workplan. Lumos-Haiti was part of one of the brainstorming
meetings in October and contributed to the design of Intervention 3. AIR submitted the initial draft of the Workplan
in October 2017 for Lumos’ comment. The timeline for developing the Workplan was not convenient for Lumos to
contribute to at that time. As such, they declined to comment further on the Workplan. Despite this, a copy of the
final submitted Workplan was provided to Lumos on December 22, 2017 on the same day this was submitted to
USAID for approval.
In summary, the activities planned for Year 2 of the project which were validated by the Government of Haiti and
other stakeholders were as follows:
Intervention 1: Development of an inclusive behavior change communication (BCC) strategy at national level
and community level, was designed to support IBESR in addressing SNPE Objective 4, sub-objectives 4.2, 4.3 and
4.4. Each NGO engaged in child protection sector has a communication strategy but IBESR is not always informed
of what messages are being conveyed, by whom, and for whom (i.e. which group of vulnerable children). Part of
Year 2 envisioned support from AIR to foster collaboration between IBESR and CNLTP to develop a BCC strategy
with the Ministry of Communication, CONATEL and others to draft policy guidelines for coordinating messages and
content disseminated nationally through multiple channels across the sector. Community leaders, religious leaders
and other community-level associations were also part of the BCC through disseminating appropriate child
protection messages, helping communities learn about children’s rights/laws/policies and referral resources and
national emergency phone lines (IBESR: 133; BPM: 188).THE PLAN WAS AND IS TO TELL HAITIANS THAT THEY ARE THE REASON WHY
KIDS ARE VICTIMS - BEHAVIOR - RATHER THAN COLLATERAL DAMAGE
OF DESTABILIZATION OF SOVEREIGNTY AND NEOCOLONIAL POLICIES
Intervention 2: Develop community supports that provide protection for the most at-risk and vulnerable
children and that start to address the root causes continue to drive child neglect, abandonment, and
exploitation of children and youth of reproductive age, was designed to support SNPE Objective 3 and further
reinforce elements of Objectives 3 and 4 within the CNLTP Action Plan. Building the capacity of local community
leaders and members in leveraging a positive deviance model that assists with the identification and tracking of
children entering and leaving communities, this model was to serve as a cascade approach for training neighboring
communities to adopt the same processes. Strengthening the quality of protection offered to vulnerable children,
developing a system of reference between services, reinforcing psychosocial intervention models and engaging
community leaders in psychosocial support, health, education and justice was the primary objective of
Intervention 2.
Intervention 3: Provide support for deinstitutionalization efforts and increase the number of accredited foster
care families, was designed to provide support to deinstitutionalization efforts and increase the number of
accredited foster care families. This intervention in design, supported the work of IBESR, Terre des Hommes (TDH)
and Lumos to increase the number of accredited foster families and alternative care settings in select communities
and provided the opportunity to evaluate and measure impact. This intervention was developed in response to the
pressing need to increase the number of accredited foster families in preparation for the closing of the worst
residential care centers in the country (that received a red rating as part of the evaluation conducted by
IBESR/Lumos). The goal was to work with TDH to support the work in increasing the number of accredited foster
care families. OUTCOMES ? Accredited foster families??
3
AIR was requested in April to provide funding and staff labor to support the CNLTP National Conference
in June 2017. While AIR was not part of year-long discussions on this conference and was asked in the end to shift
its labor and other resources to this priority while the year one data collection was still underway, AIR did fund the
large portion of this event per USAID’s request.
7
The AIR project team developed a plan to work closely with IBESR to build capacity of local community members
and leaders, as well as strengthen coordination with partners in South, West, Central Plateau, and Southeast
departments. Partner meetings were designed to be held on a monthly basis in each department, and were to
include community leaders and other stakeholders. Quarterly updates and information sharing would also occur
with communities and partners through a ‘town hall model’ on a quarterly basis in each community. In addition,
IBESR requested AIR to sign a Memorandum of Understanding for a formal partnership together around the
proposed project activities. They collected $6M and the "community" has zero resources
In addition to these interventions, AIR consistently participated in the monthly GTPE meetings held by IBESR in
Year 1 and intended to continue this participation in Years 2 and 3 of the project. AIR also planned to take part in
the convening of a monthly foster family committee meeting.
AIR submitted a full Year 2 Workplan to USAID on December 22, 2017 per USAID’s request. In addition, USAID Haiti
requested a detailed plan from AIR to ensure that a lack of participation from Lumos in the project would not
affect project activities. This memo to USAID Haiti was submitted within one week of request on January 26, 2018.
AIR was verbally informed by USAID on February 1, 2018 and in formal, written letter on February 7, 2018 that due
to changes in USAID Haiti’s governance strategy and mission needs, the project award would end March 15, 2018.
1.2 Analysis of Progress to Date
In Year 1, the Alliance for the Protection of Children project enabled community members, researchers,
government partners, and NGOs to contribute to understanding the causes of violence against children in Haiti
from the household and community perspective, to recognizing any examples of positive deviance that existed in
Haiti, and to discussing intervention models that have seen success in countries with a similar human development
index to that of Haiti. Further, the project team worked with community structures to allow for their participation
in informing pilot interventions. One of the key pieces of evidence, for example, related to community members
being frustrated with central-level decision making that did not include their voices or perspectives. In the research
on positive deviance, a very strong example of identifying and tracking children in Anse-a-Pitre had led to a
decrease in violent incidents; an example of protection that could be leveraged and strengthened by reinforcing
local capacity and scaling this out and up other communities. where is the data?
Also in Year 1, AIR utilized the research methodology and data collection to gain the buy-in of community
stakeholders as well as understand household and community patterns of thinking around abuse, exploitation, and
violence. While much research has been implemented in Haiti prior to this project, the research design and Co-
InterpretationSM of findings allowed the AIR project team to bring child protection stakeholders and community
members/leaders together in an equitable and structured way to inform and validate data as well as implicate
both national and local entities in becoming more aware of the need for attitude and behavior changes. This work
was invaluable to identifying positive deviance in target communities and ensuring that both a top-down and
bottom-up approach to pilot interventions would be considered. In addition, the evaluation report submitted to
USAID at the end of the Year 1 project year showed significant capacity building and professional growth of project
partners in the learning and application of research tools related to the Rapid Qualitative Assessment, Cultural
Models study, Social and Broadcast Media scan, and Positive Deviance study and the process for conducting a Co-
InterpretationSM workshop which allows for more collaborative interpretation and analysis of research data.
2.0 Pipeline Analysis
APC started on July 26, 2016, with a total budget of $6,049,908.
Table 1 summarizes the Approved Budget, Total Expenses and Accruals through March 15, 2018; Projected
Expenses, Total Expended and Projected, and Balance by line item are also listed.
8
Table 1: Project Budget and Expenses
Total Projections
Approved Budget Cumulative Costs Total Estimated Costs Variance
January-March 2018
07/26/2016 to 07/25/2019 07/26/2016 - 12/31/2017 1/31/2018 to 3/15/2018 07/26/2016-3/15/2018
Dollars Dollars Dollars Dollars Dollars
1. Personnel 1,190,467 530,352 246,458 776,810 413,657
2. Fringe Benefits 608,662 123,203 100,295 223,498 385,164
- -
3. Consultant 71,467 147,026 2,854 149,880 - 78,412
- -
4. Travel 168,664 82,141 7,734 89,875 78,789
- -
5. Equipment 47,208 54,185 416 54,601 - 7,393
- -
6. Supplies 18,369 8,319 - 8,319 10,049
- -
7. Subcontractors / Subgrants 2,053,000 436,000 - 436,000 1,617,000
- -
8. Allowances 19,310 6,293 847 7,140 12,170
- -
9. Activities/Trainings 165,242 5,769 - 5,769 159,473
- -
10. Other Direct Costs 261,900 50,515 25,470 75,985 185,915
Total Direct Charges 4,604,288 1,443,803 384,074 1,827,877 2,776,411
11. Indirect Charges 1,445,620 562,359 237,350 799,709 645,911
TOTAL ESTIMATED COST (U.S. DOLLARS) 6,049,908 2,006,161 621,424 2,627,586 3,422,322
Out of an approved budget of $6,049,908, AIR had expended or accrued $2,006,161 as of December 31, 2017. AIR
is projecting to spend $621,424 between January and March 15, 2018 for a total of $2,627,586 by the end of the
project.
2.1 Leverage
There was no cost share under this project. Lumos UK pledged $1,352,955 to support the efforts of the APC
project. Based on Attachment B of the APC Cooperative Agreement, Lumos would contribute two interventions at
their own expense (expenses being associated with the estimated $1,352,955 leverage that would not be tracked
by USAID or AIR).
From Cooperative Agreement - Attachment B - page 20, 21:
As part of Lumos’ leveraging contribution to the program, the following will be in their
responsibility as resource partner. Assess residential institutions and PD models for alternate
care, including families. Possible evaluations in select residential institutions of children and
their changes in health, development and quality of life may be conducted. The tools for these
evaluations will be designed by Lumos in partnership with IBESR, reviewed by a local Haitian
evaluation firm to be determined, and implemented by trained social workers.
From Cooperative Agreement - Attachment B - page 22:
As part Lumos’ leveraging contribution to the program, the following intervention and any
reporting will be Lumos’ responsibility. Designing a child protection systems strengthening
intervention with a cohort of at least 500 children living outside families (in institutions, on the
9
OUTCOMES 500 kids?
streets, or in the restavèk system). Based on the outcomes of the Year 1 research and evaluation
of existing child protection approaches, and leveraging relevant PD outcomes, a range of
interventions will be developed and implemented for this cohort of children. These will be
implemented by joint teams of social workers from partner organizations and IBESR, in order to
ensure government ownership of both process and outcomes when looking at testing new models of
family support and alternative care for Haitian children. Furthermore, we also aim to improve the capacity
of IBESR social workers to mitigate and prevent violence against children outside families.
3.0 PROGRAM REPORTS
3.1 Quarterly Financial Reports (SF425)
AIR will submit quarterly financial reports for all expenses through March 15, 2018.
3.2 Technical/Program Reporting
AIR has no additional technical reports or deliverables to submit. Quarterly reports through Year 2, QR 1;
the Activity MEL Plan; the Branding and Marking Plan; Workplans for Years 1 and 2; TORs for the Advisory
Committee (February 2017 original submission); five research studies-Rapid Qualitative Assessment,
Cultural Models study, Social and Broadcast Media scan, Positive Deviance Study, Systematic Review; Co-
InterpretationSM Workshop report; Evaluation Report for Year 1 Activities: all these were submitted on
time with no exceptions.
All relevant reports were submitted to DevResults.
4.0 SUBCONTRACTS/SUB-AWARDS
There are no current active sub-awards. All sub-awardees from Year 1 were paid in full for work in Year 1. No sub-
awards were signed for Year 2 as the Workplan and budget realignment were still pending.
5.0 INVENTORY AND PROPERTY DISPOSITION PLAN
AIR maintains a detailed inventory of all expendable and non-expendable property acquired or received from other
USAID funded projects and used under the project.
In this Closeout Plan, AIR is submitting a disposition request for non-expendable property and restricted items. We
respectfully request USAID approval for the disposition of these non-expendable items and vehicles as detailed in
the accompanying inventory and property disposition plan. For informational purposes, we also include a detailed
list of AIR’s expendable project property and its planned disposition.
5.1 Non-Expendable Property with a purchase price over $5,000 transferred to or acquired
under the Cooperative Agreement
All non-expendable property are vehicle used for transport during the life of the project. This list also has
motorcycles, which are valued less than $5,000, but are included in this list since they are restricted commodities.
5.2 Expendable Property with a purchase price under $5,000 acquired under the Cooperative
Agreement or transferred from another Federally-Funded Project
The expendable property primarily consists of computers, office furniture, office materials, and supplies.
10
6.0 PERSONNEL PHASE-OUT
6.1 Cooperating Country National Staff
AIR consulted with the retained labor law firm of Hudicourt Woolley in Haiti prior to staff terminations to ensure
that AIR followed the language of the existing employee contract and also all local labor laws. As such, the grid
below indicates the phased out termination of all national staff.
Staff Member Contract Start Date Notice of End Date Severance
Termination Indemnity
Caroline Durena October 3, 2016 Feb 6, 2018 Feb 7, 2018 1 month
Nixon Mondesir October 3, 2016 Feb 6, 2018 Feb 28, 2018 1 month
Elmire Petit De Brice September 9, 2016 Feb 6, 2018 Feb 28, 2018 1 month
Rolinx Augustin October 2, 2017 Feb 6, 2018 Feb 7, 2018 15 days
Evy Toussaint October 2, 2017 Feb 6, 2018 Feb 7, 2018 15 days
Myriame Elvariste December 4, 2017 Feb 5, 2018 Feb 28, 2018 None
Melodie Cerin December 4, 2017 Feb 5, 2018 Feb 28, 2018 None
Patrick Camille December 4, 2017 Feb 5, 2018 Feb 28, 2018 None
Article 7 of the employee contract reflects that when the client requests immediate shut down of the project, the
notice to employees can be immediate provided that severance is paid. Severance and pro-rated 13 month bonus
pay for employees who had served beyond the probationary period was provided. The following was taken into
account for severance:
The Previous Notice (Préavis) or Severance Indemnity has been calculated as follows:
0 to 3 months No indemnity
3 to 12 months 15 days
1 to 3 years 1 month
3 to 6 years 2 months
6 to 10 years 3 months
Over 10 years 4 months
AIR terminated non-essential technical staff on February 7, 2018. Exception was requested of USAID related to the
three staff hired in early December 2017 in order to allow them to serve the probationary period so that they
could reference their work with AIR on future USAID 1420 forms and or other professional opportunities. The
Finance Manager and Driver will be retained until February 28, 2018 in order to ensure an orderly close of the
project finances, disposition plan, and to be available for meetings with partners that the AIR Project Director from
the Home Office will be attending throughout the week of February 19, 2018. All field staff and field operations will
terminate on February 28, 2018. Notices for each employee have been deposited with the Ministry of Social Affairs
and Labor (MAST, Labor Board).
7.0 OTHER GENERAL DEMOBILIZATION PROCESSES
AIR has organized closeout actions by categories to plan an orderly closeout. AIR Home Office staff will travel to
Port-au-Prince to assist in the field office closeout.
7.1 AIR Field Office – Port-au-Prince
Meetings
11
The Chief of Party, Technical Lead, and Driver will go on one final field mission to Anse-a-Pitre to speak with
community leaders about the end of the project from February 15-17, 2018. Given the extraordinary work done to
win the buy-in of local leaders in Southeast department and to build the relationship with leaders and community
leaders among the stateless population on the border, AIR believes it is important to speak to these community
leaders face-to-face (notably, telephone communication is often difficult with certain community leaders). In
addition, this same team will speak with community leaders and members within the West department and
Artibonite as needed by phone or in person during the week of February 12, 2018. The community leaders of
Northeast department were less engaged with the project team after the research efforts of Year 1. They did not
participate, for example, in the Co-InterpretationSM workshop held in July 2017.
The AIR Project Director, Amy West, will travel to Haiti from February 19 – 28, 2018. In that week, she will
participate in meetings to formally inform stakeholders and partners of the project close out. AIR is attempting to
schedule meetings with the following entities: IBESR, BPM, CNLTP, Zanmi Lasante, Restavèk Freedom, ENPAK,
Terre des Hommes. As key members of the Advisory Committee, AIR has informed UNHCR and UNICEF in writing of
the project close-out.
Office Space & Disposition
To accommodate the increase of staff, AIR expanded its office space within the same building on February 1, 2018.
The office had signed a new lease valid through February 2019. AIR has provided notice to the landlord as of
February 7, 2018 and will pay the penalties per the lease agreement.
A final walk through and release by the owner will be held on February 27, 2018. Upon approval of the disposition
plan, expendable and non-expendable property and vehicles will be delivered to the approved recipient by
February 26 or 27, 2018, or to USAID if further instructions have not been provided. Transfer and receipt of
property will be documented.
Other
Melodie Ngo Tonye, AIR’s Field Finance Associate, will travel to Haiti from February 19 – 28, 2018. She will assist
the DCOP and Finance Manager in financial close out and provide quality assurance to all accounting. Accounting
and financial files will be inventoried and shipped to AIR’s Washington, DC headquarters for safekeeping. Project
suppliers and vendors are being are notified in writing and by personal visit in advance that the project is closing
and are requested to send final invoices.
The project bank account will be closed on February 28, 2018.
12