Haiti Customs Support Project - Final Report

Haiti Customs Support Project - Final Report

USAID 2020 42 pages
Summary — This final report summarizes the activities and achievements of the USAID-funded Haiti Customs Support Project from 2016 to 2020. The project aimed to modernize customs procedures, enhance trade facilitation, and increase revenue and security for the Haitian government through support to the Administration Générale des Douanes (AGD). The report outlines key components including assessments, ICT procurement, capacity building, and recommendations for future improvements.
Key Findings
Full Description
The Haiti Customs Support Project, funded by USAID, operated from early 2016 to June 2020 with the goal of boosting Haiti's economic development through the modernization of customs procedures. The project focused on streamlining processes for clearing exported and imported goods by supporting the Administration Générale des Douanes (AGD) in implementing reforms related to organizational structure, human resources, capacity building, technology, and operational procedures. Key activities included assessments of AGD's organizational structure, ICT infrastructure, and training needs, as well as the procurement and installation of ICT equipment and the provision of ongoing capacity building through training programs. The project faced challenges including delays in port rehabilitation, security concerns, and the COVID-19 pandemic, but adapted by relocating activities and utilizing remote training methods. The final report outlines the project's achievements, challenges, and recommendations for the future development of Haiti's customs administration.
Topics
GovernanceEconomyTradeInfrastructure
Geography
NationalOuest DepartmentNord Department
Time Coverage
2016 — 2020
Keywords
customs, trade facilitation, Haiti, USAID, AGD, risk management, ICT, capacity building, border security, modernization, revenue collection, strategic planning
Entities
USAID, Administration Générale des Douanes, AGD, WCO, WTO, Nathan Associates, Steve Létourneau, Carla Tena, Bernard Touboul, UNOPS, APN
Full Document Text

Extracted text from the original document for search indexing.

1 FINAL REPORT HAITI CUSTOMS SUPPORT PROJECT JUNE 2020 This publication was produced for review by the United States Agency for International Development. It was prepared by the Haiti Customs Support Project team. USAID / Haiti Customs Support Project – Final Report 2 Haiti Customs Support Project FINAL REPORT Contracted under AID-521-C-16-00004 Haiti Customs Support Project DISCLAIMER The author’s views expressed in this publication do not necessarily reflect the views of the United States Agency for International Development or the United States Government. 1 CONTENT Acronyms and Abbreviations 2 Introduction 3 Background 4 Component I: Mobilization, Assessments, and Trade Facilitation Training 7 Component II: Analysis of Procedures 11 Component III: ICT Procurement and Installation 13 Component IV: On-Going Capacity building 17 Component V: Project Closure 26 Conclusion and Recommendations 27 Annex A: Organizational Structure and Human Resource Recommendations 37 Annex B: Capacity Building and Training Needs Recommendations 38 Annex C: ICT Infrastructure Recommendations 39 Annex D: Policy and Procedure Recommendations 40 USAID / Haiti Customs Support Project – Final Report 2 ACRONYMS AND ABBREVIATIONS AEO Authorized Economic Operator AGD Administration Générale des Douanes APN Autorité Portuaire Nationale CH Cap-Haïtien CHCSP Cap-Haïtien Customs Support Project CHP Cap-Haïtien Port COP Chief of Party COR Contracting Officer’s Representative DG Director General DGA Director Genaral Adjoint GOH Government of Haiti HQ Headquarters HR Human Resources ICT Information and Communications Technology RM Risk Management PAP Port-Au-Prince POE Port of Entry PPP Public-Private Partnership STTA Short-Term-Technical-Assistance TFA Trade Facilitation Agreement TBD To be determined USAID United States Agency for International Development USG United States Government USAID / Haiti Customs Support Project – Final Report 3 INTRODUCTION From early 2016 through June 2020, USAID supported the Government of Haiti in boosting economic development through modernization of customs procedures and clearances, incorporating international best practices, reducing financial waste, and increasing security and revenue. The project was to help streamline processes for clearing exported and imported goods. To do so, the project required the support of Haiti’s Administration Générale des Douanes (AGD) in implementing proposed reforms in the following areas: • Organizational structure • Human resources • Capacity building and training • Technology and infrastructure • Operational procedures • Cooperation and communication This report will outline the achievements by the project that were undertaken between March 2016 to June 2020. Below are the main activities completed by the project: 1. Components I: Mobilization, Assessments, and Trade Facilitation Training 2. Component II: Analysis of Procedures. 3. Component III: ICT Procurement and Installation 4. Component IV: On-Going Capacity Building 5. Component V: Project Closure USAID / Haiti Customs Support Project – Final Report 4 BACKGROUND The role of Customs has changed significantly in recent times as the global supply chain has become imperative and each country participating adds value. Globalization can be seen as an opportunity to aid the development of the world economy. It leads to improving the business and investment opportunity. Haiti is among the developing countries with some of the longest release times in the world. The Administration Générale des Douanes (AGD) physically inspects most of the cargo entering the country. In contrast, EU and North American countries inspect less than 3-4% of cargo that arrives at their borders. While some might expect that Haiti’s high level of inspection would yield exceptional results, it does not. A significant amount of revenue evasion continues to exist through misclassification and egregious trader misconduct. Historically, many organizations have used risk adverse approaches that required a full inspection of all shipments, conveyances, crews and passengers. It is a fundamental misconception that inspecting all consignments leads to higher revenue collection or better security. Equally inaccurate is that belief that inspecting only a few consignments will bolster trade facilitation. In fact, both approaches harm revenue collection, security, and enforcement. It is therefore critical for Haiti to accept that 100% or 0% inspections are not effective controls. The current inspection services performed prior to the good entering in the country are accomplished under a contract, which has proven detrimental internationally to building customs capacity and have impeded the achievement of expected benefits including the transfer of skills and knowledge through border organizations. It is important for the AGD to transfer back the power to its owns border organizations and establish the benefits for the government of Haiti, and the economy as a whole, to move toward a sustainable and efficient Risk Management (RM) Framework. From an international perspective, the Revised Kyoto Convention on the Simplification of Customs Procedures promotes a common methodology, for which trade facilitation and risk management are its main pillars. In this approach, the complex set of controls that have been developed over many years by border organizations are more easily managed. These controls, conceived so that border organizations could secure their borders, have unfortunately created bottlenecks that hinder the movement of trade in various regions of the globe. Simplifying border controls requires new approaches that combine the latest technology with advanced analytic. These tools will support border organizations as they make decisions at the border. Further, the WCO Safe Framework of Standards specifically endorses the use of risk management systems and targeting systems to identify high-risk trade for closer scrutiny and inspection. As top decision-makers are asking increasingly complex business questions, providing rapid and meaningful answers is becoming critical to any customs organization’s performance. To that end, the AGD already created a Risk Management (RM) framework. Having said that, the AGD has not been able to properly USAID / Haiti Customs Support Project – Final Report 5 establish a sound RM framework capable of providing a single and reliable source of information for top- level decision-makers, in order to shed light on previously unanswerable border questions. At the same time, the flow of low risk and pre-approved shipments across borders must continue, since it promotes economic growth and regional and global competiveness. The twin pillars of risk management and trade facilitation are the future of border management, and advanced analytical approaches are key to achieving this outcome. Based on multiple diagnostics conducted to date, subject matter experts recommend that border organizations: 1) Ensure the implementation and use of a Risk Management Framework based on intelligence; 2) Cultivate selectivity using sound automated risk analysis and targeting; 3) Conduct a post-clearance audit to monitor systemic processing, conduct intelligence and investigation analysis, and adjust risk profiles; and 4) Integrate new expert systems for anti-smuggling. It is important to include supporting components, like subject matter expertise, in any large project, as they will promote and support change management, deliver appropriate support and training, and assist in policy development and business transformation. Without a risk management system driving an organization’s decision-making and feeding information back into the system, customs will spend its time chasing trader misconduct rather than identifying and preventing the misconduct before it happens. Revenue evasion is only one of many threats occurring at the border. Other threats include security, narcotics, sanitary and phytosanitary safety, health, agricultural and environmental impact, commercial disruption, chemical weapons precursors, dual use goods, prohibited items, weapons and ammunition, intellectual property, endangered species, antidumping and more. Today, these pending threats are not systematically analyzed or managed by the AGD. When analyzing Haiti’s current state of selectivity, inspection, and overall risk management approach, it is clear there is very limited data at the disposal of customs officers, even though the data exists. The ASYCUDA system is only used in real time and functions as a repository of information; it does not provide officers with relevant field insights. When the current approach is looked at in closer detail, the only factor used to identify impeding threats is mostly a deductive approach that uses historical enforcement actions. Many experts agree that a risk management system that uses inductive logic and reasoning would allow the AGD to analyze the inherent risks presented by commodities, routing and geography, weights and volumes, equipment type, trading entity relationships, and more. At a national level, Haitian Policy stresses the need to protect its interests and augment revenue. It is an important first step for the government to proactively create opportunity for the country. For example, the Haitian government could lead the creation of a Border Plan between the Republic of Haiti and the Dominican Republic, which would promote a number of joint initiatives that would strengthen and USAID / Haiti Customs Support Project – Final Report 6 secure the Island of Hispaniola and the shared borders of both countries. These initiatives would also help secure the movement of goods and travelers across borders. USAID / Haiti Customs Support Project – Final Report 7 COMPONENT I: MOBILIZATION, ASSESSMENTS, AND TRADE FACILITATION TRAINING Mobilization Project startup activities began in February 2016 and were successfully completed, ensuring smooth project operations. Through meetings and discussions in the initial months, the project established a solid reputation and relationship with senior Executive of AGD and their employees, whose support and collaboration were vital to the project’s success. Chief of Party (COP) Steve Létourneau has maintained constant communication with the AGD and USAID and presented the project’s approach and timeframe to help reform four main areas: 1. Organizational Structure 2. Human Resources 3. Capacity Building and Training 4. Technology and Infrastructure Within the first few weeks, the project secured office space in Cap-Haïtien and procured furniture and computers to ensure the field staff and office were equipped with the required tools to support project work and maintain operations. In collaboration with its AGD, the project developed a detail project working plan to organize approach and timings for interventions proposed. The project team provided all the relevant background information to AGD and coordinated the activity schedule and project work plan to ensure success. During that period, the project team assembled a team of qualified experts to carry out short-term assessments, discussed below. Assessments One of the most important deliverables was to properly conduct four assessments of the AGD. These assessments are an important process of review and analysis which allows an organization to better understand its strengths, weaknesses, and threats, but also create opportunities that helps them to better understand where it presently stands in terms of its institutional development and the directions in which it should try to develop in the future. Experts have suggested various best practices and standards of excellence for their respective types of organization. Its important to note that all organizations are unique. That is why the approaches to evaluating them should be highly customized, as well. For this project, we will used the World Customs Organizations (WCO) standards. Benefits of Organizational Evaluation and Diagnosis n. Benefits of an evaluation include that it: • Mobilizes employees for organizational change as they feel their opinions are being heard and respected; USAID / Haiti Customs Support Project – Final Report 8 • Facilitates meaningful communication among participants – perhaps the most important benefit from the evaluation process; • Cultivates realistic expectations for change as participants continually think about the organization's situation and what can realistically be done about it; • Enhances learning for participants as they continue to collect and reflect on feedback about the organization's performance and their role in it; • Improves performance as participants continue to make adjustments to what they are doing based on the results of their learning; • Improves the organization's credibility among its stakeholders at a time when organizations are always competing for a positive image. During our assessment, we used the following guidelines: • Ensure the evaluation design matches the nature and needs of your organization; • Discuss evaluation with the AGD members in the early phases of the evaluation to ensure buy- in; • Focus on relevance, utility, and practicality as much as on technical priorities; • Integrate organizational evaluation with other ongoing evaluations in the organization; • Include a mix of methods to collect information; • Place high priority on capturing learning during evaluations; • Share findings from evaluations as soon as you have them. This assessment process enables an organization to map out a strategic plan that should allowed them to develop in the direction it desires and thereby meeting its mandate and objectives. As a government, you always want your organizations to be operating in an optimum level, whether or not the organization is the one collecting the most revenue in the country. The project team provided detailed assessments in the following areas: 1. Organizational structure and human resources of the AGD, and proposed sound recommendations for improving processes. Also served as a helpful reference resource during the design phase of the training curriculum in Component IV; 2. Gender Assessment (including a Gender Inclusiveness Plan) for the AGD on hiring practices, and made recommendations for ensuring equitable representation of women; 3. ICT infrastructure, a preliminary assessment of AGD building infrastructure and current ICT capabilities in both Cap-Haïtien and Port-au-Prince in order to identify issues concerning future port rehabilitation and potential challenges for implementing Component III, ICT Procurement and Installation. During this assessment, multiple issues occurred as the port rehabilitation project experienced multiple delays. Under the leadership of COP Steve Létourneau, a meeting was organized with APN, AGD, UNOPS and USAID in order to reach consensus on AGD building plans within the overall Cap-Haïtien Port rehabilitation project and implementation of Component III: ICT Procurement, Installation. Unfortunately, these plans were not successful, as more delays USAID / Haiti Customs Support Project – Final Report 9 occurred in the port project, initiating a sustainable mitigation strategy to install the equipment in Port-Au-Prince in order to sustain the AGD’s ICT infrastructure. 4. Capacity building & training needs assessment of the AGD with sound recommendations that served as a helpful reference resource during the design phase of the training curriculum in Component IV. 5. Designed a detailed Activity, Monitoring and Evaluation Plan (AMEP) to monitor key performance indicators and report on the project’s progress made toward target results. All of the assessments and the AMEP were shared with the AGD for comment and submitted to USAID. Included in annex A are all of the assessment recommendations by name. In regards to the advancement of the AGD on these assessments’ recommendations, minor advancements have been undertaken during the last few years. Having said that, the AGD recently developed a strategic plan incorporating all recommendations. The two principle issues the AGD will face for the development and the implementation of the strategic plan, are the absence of funding from the government and donors and the lack of internal and external knowledge and expertise. Trade Facilitation Agreement In 1952 the World Customs Organization (WCO) was formed to develop standards and provide technical assistance for the harmonization of procedures related to the movement of goods and people. Trade Facilitation (TF) has its origins in 1974 with the adoption of the WCO Kyoto Convention (KC), an instrument for the Simplification and Harmonization of Customs procedures. The Revised Kyoto Convention (RKC) entered into force in 2006 and evolved more comprehensive and complete tools that provide the bases to adopt the Trade Facilitation Agreement instrument to address new realities. For border organization around the world, like AGD, it’s important for employees to understand the ‘’WHAT’’ and the ‘’WHY” of the WCO instruments. Since the signature in 1947 of the General Agreement on Tariff and Trade (GATT), the establishment of the World Trade Organization (WTO) (1986-1993), the Doha Round (2001) and the July Package in 2004. During those multilateral meetings, member organizations agreed to launch negotiations on TF to foster three GATT articles – Freedom of Transit; Fees and Formalities connected with Importation and Exportation; and Publication and Administration of Trade Regulations. The TFA was materialized in 2013 to have better TF mechanisms that would benefit both developed and developing countries; focus on the explicit link between obligations made and donor assistance for implementation of new commitments; and enhance TA and support for capacity building and at fostering effective cooperation between border authorities. In that regard, the project team designed and developed a comprehensive training course that included modules on relevant convention and international best practices for a modern and performing XXIe customs organizations. The following are subjects (not all inclusive) that were discussed during technical and live trainings: • WCO SAFE Framework; • Revised Kyoto Convention; USAID / Haiti Customs Support Project – Final Report 10 • Trade Facilitation Agreement; • Legislation, Policy, Procedures and relevant authority and powers of Customs officers; • Health and Safety (H&S); • Leadership and Communication; • Changing operating environment and global challenges. It’s important to note that all project trainings integrated a gender perspective, based on USAID’s Gender Equality and Female Empowerment (GEFE) Policy (2012) and ADS 201. Finally, the project team designed and administered Kirkpatrick Level 1, 2 and 3 evaluations of AGD officials who participated in the Trade Facilitation Agreement Training and shared the reports with AGD and USAID. Gender and Organizational Structure Assessment visit to AGD in Port-au-Prince USAID / Haiti Customs Support Project – Final Report 11 COMPONENT II: ANALYSIS OF PROCEDURES Policy and Procedures As mentioned previously, one of the most important deliverables was to properly conduct assessments of the AGD. These assessments were an important process of review and analysis which allowed AGD to better understand its strengths, weaknesses, and threats, but also created opportunities that helped them to better understand where they presently stand in terms of its institutional development and the directions in which they should try to develop in the future. In June and December 2016, Trade Facilitation Specialists Ms. Carla Tena, Mr. Bernard Touboul and COP Letourneau conducted an analysis of the strengths and weaknesses of customs clearance procedures in Port-au-Prince and Cap-Haïtien. As this analysis was crucial for the AGD, we requested increased involvement of the AGD Senior Executive team in the development of this assessment. As the AGD was involved in drafting new business procedures at the time, the Nathan team encouraged the continuation of their participation by accompanying the assessment work and in-depth consultation meetings. The AGD involvement added value to the assessments and engendered more stakeholder ownership in their own evaluation process. The analysis undertaken in collaboration with the AGD took the following into consideration: • Inclusivity of all Government of Haiti (GOH) agencies responsible for regulated controls; • Exportation, importation, and transit operations; • Adherence to revised Kyoto Convention’s Annex E; • Adherence to GATT VIII: Fees and Formalities Adherence to TFA Articles 6: Disciplines on fees and charges imposed on or in connection with importation and exportation and penalties and Article 9: Movement of goods intended for import under customs control; • Licensing and permit requirements, and the time and cost to fulfill each requirement. After sharing the latest draft of new business procedures, the AGD further discussed the following points with the Nathan team: • Identifying capacity building and training needs; • Further developing ideas on a possible AGD pilot project in Cap-Haïtien to introduce new customs procedures such as in-transit shipments, export controls, and importing goods; • Strengthening AGD strategic partnerships and collaboration with private industry by creating a committee on policy and procedures that would promote open communication and clear understanding of new processes amongst all parties involved; • Capture of statistical indicators during the importation and exportation of goods. The AGD’s desire to enhance collaboration and increase involvement is beneficial for the overall project as stakeholder buy-in plays a key role in the success and sustainability of any development project. USAID / Haiti Customs Support Project – Final Report 12 This assessment was shared with the AGD for comments and submitted to USAID. Included in annex B are the assessment recommendations. There was some advancement made on the recommendations of this assessment during the last few years. Having said that, the AGD doesn’t have a full-time funded project with staff working on developing new policy and procedures for the entire AGD. Recently, the AGD developed a strategic plan incorporating all the recommendations from this assessment into the plan. As mentioned before, the two principal issues the AGD will be facing for the development and the implementation of the strategic plan, are the absence of funding from the government and the donors and the lack internal and external knowledge and expertise. Port-Au-Prince – AGD Port Inspection Facility USAID / Haiti Customs Support Project – Final Report 13 COMPONENT III: ICT PROCUREMENT AND INSTALLATION Defining the Approach Under the original Scope of Work of the contract, it was envisioned that the project would be able to assess ICT requirements and related training needs to modernize the operating systems for the AGD Port Customs office in the Cap-Haïtien. The Cap-Haïtien Port (CHP) Rehabilitation and Public-Private Partnership project was financing the transformation of the Port of Cap-Haïtien by improving its infrastructure and services and updating the customs operation to make it more competitive. The CHP PPP project proposed improvements to the port’s physical infrastructure, but the AGD office space requirements were not taken into consideration nor documented in the original plan. Moreover, the current office facility for AGD officers on the port terminal is in poor condition and was supposed to be demolished during the CHP PPP rehabilitation construction. Therefore, before ICT assessment work could begin, all parties involved – AGD, APN, UNOPS and USAID – needed to reach a consensus in order to finalize and execute new and/or interim AGD office construction. As these decisions are outside of the control of the HCS Project, this lack of common direction caused a delay for Component- 3 ICT Procurement and Installation. The project presented an approach to meet the initial scope of this component to procure and install ICT equipment for the AGD office in Cap-Haïtien. It is critical to note that the successful completion of this component was dependent on two major assumptions: 1. The concerned parties mentioned above are able to reach a conclusion on the final location of the Cap-Haïtien POE office on the port; and 2. Construction of the Cap-Haïtien POE office was completed and operational by November 2017. To facilitate the discussion amongst the involved parties, the COP met individually with USAID, UNOPS, APN and AGD to propose relocation scenarios. Based on the separate consultations with AGD, APN and USAID it became evident that the construction of the new AGD building in Cap-Haïtien would not be completed within the HCS project timeline and therefore discussions with the AGD shifted to redefine the desired outcomes of the Component III ICT activities. The COP proposed different mitigation strategies, which received approval by AGD and USAID to relocate Component III to Port- Au-Prince in order to enhance not only the Cap-Haïtien infrastructure, but the entire AGD – ICT infrastructure. The chosen locations were at the new AGD airport building and Port Office in Port-Au- Prince. Upon that decision, the project developed bid terms and specifications for ICT competition. The ICT firm that was chosen would be responsible for identifying, procuring, and installing the necessary hardware and software. The project estimated that the selection and installation, acquisition, and installation of equipment would take approximately seven months. USAID / Haiti Customs Support Project – Final Report 14 The following ICT equipment was selected and was to be procured and installed by the project after multiple meetings with AGD in order to determine their requirements: 1. Task Order 1 - Cabling at the AGD Port in Port-Au-Prince; 2. Task Order 2 – Satellites procurement and installation at 19 Port of Entry (POE); and 3. Task Order 3 – Procurement and installations of licenses on the AGD infrastructures. On March 12 th the HCSP published a Request for Proposal (RFP), “ Procurement & Installation of Information and Communication Technologies (cabling, satellite and licensing) for the Administration Generale des Douanes (AGD) .” Between September and December 2008, COP Letourneau communicated numerous times throughout October with the new AGD Deputy General Bell (DG) to ensure continuing project advancement as the Minister of Finance replaced the Director General (DG), and the two Deputy Director General (DDG) of Customs. In addition, the COP held meetings with Assistant Deputy General (DGA) Dubreus to discuss the ICT investment component and overall project objectives. Although the DGA was impressed with the proposal, he expressed concerns that the previous administration had only agreed to implement Task 1 – Cabling and had not agreed to Task 2 – Satellites and Task 3 – Licenses. DGA Dubreus requested to consult with DG Bell and the Minister of Finance in Decembre before committing to move forward. COP Letourneau managed to meet with Minister Decembre and present the original ICT proposal. Minister Decembre was very supportive of the original proposal. During subsequent meetings with DG Bell, the relevant DGAs and AGD IT personnel, it was agreed to proceed with the three Task Orders. Mr. David Roberge, the project’s STTA ICT Expert, visited the AGD HQ, where the cabling work was taking place and oversaw the mapping of the physical installation of the new cabling (Task 1). The project collaborated with the AGD HR and IT Departments to ensure a smooth transition. To this end, COP Letourneau worked with senior managers to help them plan alternative working space for the period when the vendor would be installing the cabling in the regular work space. Setting up ten computers in another room ensured that AGD operations did not experience any stoppage during installation of the new cabling. Further to the successful meetings held in December with the new AGD Administration, the project drafted and submitted a revised ICT Plan during Y3 Q2. The ICT Plan laid out in more detail the work plan for the following ICT Procurement tasks. Task Order 1: Cabling The project continued working with the selected vendor for the cabling installation work, who worked with the AGD to find mutually agreeable time slots to install the new cabling as per the finalized mapping plan. In May 2020, the new cabling was installed and certified by the IT vendor, the AGD, and the project’s STTA ICT Experts. Task Order 2 (Procurement and Installation of VSAT): USAID / Haiti Customs Support Project – Final Report 15 The AGD requested that we eliminate the satellite procurement and installation as multiple licenses within the new system needed to be renewed, and it wasn’t possible to physically install satellites throughout the country as originally planned, given the intense security situation. After discussion with USAID, it was determined that the project would change Task 2, in order to procure more licenses for the AGD. Task 3 (Licenses and Virtualization): Following the 2017 ICT evaluation, the decision was made by the COP, the AGD, and USAID to utilize Nathan consultants to help address the current problems with the AGD IT infrastructure, as opposed to outsourcing this work to a vendor for Task Order 3. This allowed for closer monitoring and oversight by Nathan of the work, faster acknowledgement of delays, and more direct control over the design and implementation of the full ICT procurement plan, ensuring that project delivery was on time and within the allocated budget. As the original ICT procurement RFP did not contain any information on the necessary virtualization of the new AGD servers, Nathan hired Virtualization Expert Pruszkowski with knowledge of AGD’s new servers to complete Task 3 in order to complete this task faster. During the implementation, this solution reduced the number of different people interacting with AGD staff and ensures the proper level of knowledge of virtualization. This solution also allowed for a fast, reliable, and cost-effective way to ensure the applications, database, and data are properly transferred onto the new virtual environment. Furthermore, the Virtualization Expert provided input and oversight on Tasks 1 and 3 to ensure consistency, synchronization, and network/data security between the servers and remote sites. The Virtualization Expert also took the lead in supporting the AGD in acquiring Oracle licenses, Firewall Licenses, SolarWinds licenses and a standard UCC SSL for Exchange for their new servers. In addition, the expert integrated the new hardware and software into the AGD infrastructure and provided support and guidance for the transfer of data from the old to the new servers. Having Nathan experts directly responsible for Task Order 3 mitigated the risk of using a vendor who may not have personnel with necessary and complete knowledge of virtual servers. This solution also avoided the risk of someone not familiar with the new AGD servers damaging or losing data during the transition from the old system to the new. As of June 2020, the all of the above licenses were installed and the infrastructure of the AGD has been upgraded. Note that the AGD now has production infrastructure and a Disaster Recovery system at the Airport commercial office. Training The project team met with the AGD IT Director and employees to discuss requirements for upcoming ICT training. The team also provided continuous onsite training to AGD staff during the virtualization process, installation of licenses, and operating systems. In addition, Nathan experts provided technical support until June 20, 2020 to ensure a smooth transition. USAID / Haiti Customs Support Project – Final Report 16 O n March 11, 2020, the World Health Organization (WHO) assessed COVID-19 as a global pandemic. It important to note that Nathan Associates and USAID agreed after a careful assessment, that the COP and Training Manager be evacuated from Haiti to ensure their health & safety. Despite these challenges, COP Letourneau has continued to communicate and engage the AGD Directors General, in order to advance project objectives. As part of this emergency request for travel, Nathan was granted an informal no cost extension through June, 2020, and approval for work to continue remotely for the COP and Operations and Training Manager. As it was impossible to deliver live training in Haiti during this period, Nathan contracted a company that to deliver online training. The following courses were delivered in March and May 2020 to twenty AGD IT employees: Training course # of peoples Course date(s) MCSA Windows Server 2016 4 20.04.2020, 04.27.2020, 05.25.2020 CISSP 8 05.04.2020 Windows GPO (MS50255) 4 05.11.2020 Cisco CCNA 4 06.08.2020 SECURITY T he prolonged political crisis and tense security environment continued to have an adverse impact on the country’s economy and hinder the Haitian government’s ability to meet the basic needs of its people, resolve long-standing governance issues and address humanitarian crises. As a result, increasing tensions at the highest levels of the executive branch prevented the development of a common understanding on a way out of the crisis and the holding of a comprehensive and inclusive political dialogue. Specific to the project, the technical scope of work required travel to Red or Orange level zones on a nearly daily basis by project staff, government of Haiti counterparts, and project vendors. The frequency with which the project team had to travel to these areas, coupled with the lack of sufficient security coverage, put the staff at a high risk of a major security incident. At the same time, the primary counterpart, the AGD, was not able to travel to their offices or other locations in the city to participate in training or to allow access to the AGD office, one of the primary work sites. As the project work on Component III was significantly delayed due to the security situation that began in July 2018, key activities under this component were behind schedule, and the schedule was pushed back further given the uncertainty of the security situation. Furthermore, as mentioned above on March 11, 2020, the World Health Organization (WHO) assessed COVID-19 as a global pandemic. As the COP and Training Manager were evacuated from Haiti to ensure their health & safety, Component III implementation continued virtually. 17 COMPONENT IV: ON-GOING CAPACITY BUILDING Introduction In fulfillment of Component 1V, Ongoing Capacity Building, the Nathan team organized and carried out multiple one-week training sessions and mentoring activities for Administration Générale des Douanes (AGD) participants over the course of the 4.5 year project. In preparing the training design, COP Steve Létourneau discussed the content and objectives with the AGD to ensure that the training material would be timely, relevant, and practical. Equally important was that the training encourage equal participation from male and female employees. Although equality of rights is conferred by law, women do not enjoy all the rights enshrined in the 1987 Constitution and the measure of equity provided for in the 2012 amendment under article 17.1 establishing a target quota of at least 30% women at all levels of national government bodies. It should be noted that during the length of the project, about 40% of female AGD officers, some of whom serve in management positions, participated in the training. Training Matrix COP Steve Létourneau increased the involvement of the AGD Senior Executive team in the development of On-Going Capacity Training. The AGD’s involvement was excellent in developing a list of proposed training during more in-depth consultation meetings with the Nathan project team. The team involved the AGD in the following areas: • Identify capacity building and training needs; • Develop a matrix to identify training needs by including elements such as: o Compliance of training with one of the AGD's priorities o The importance of training at the customs level o The existence of legislation and regulations for this training o The existence of policies and procedures for this training o The existence of a program in place within the AGD o The existence of similar training; • Develop and implement a training schedule for the AGD. Based on this information and what was gathered during the project activities, consultations and recommendations from the Capacity Building and Training Needs Assessment report, eight training topics were identified and prioritized to better align with AGD priorities as well as serve practical areas where the AGD might be able to apply and implement new procedures, thereby attaining the goal of streamlining and improving customs procedures in Haiti. USAID / Haiti Customs Support Project – Final Report 18 In December 2016, COP Steve Létourneau presented a proposed list of training topics and dates to the AGD HR Director which was later confirmed and agreed upon by the Deputy Director Generals and the Director General of Customs. COP Létourneau along with the team of qualified STTA customs experts designed a capacity building approach that aligned with the AGD’s mission, vision, and strategic objectives and allowed the team to develop targeted training, curricula, manuals, evaluations and reports. The training consisted of conducting eight trainings in the following areas: • Trade Facilitation Agreement; • Risk Management; • Leadership, Change Management and Communication; • Intelligence and Investigations; • Targeting of goods and passengers; • Vessel and Container Searches; • Authorized Economic Operator (AEO); and • Train-the-Trainer. The training curriculum included modules on relevant convention and international best practices for a modern and performing XXIe customs organization. The following are subjects (not all inclusive) that were discussed during technical and live trainings: • WCO SAFE Framework; • Revised Kyoto Convention; • Trade Facilitation Agreement; • Legislation, Policy, Procedures and relevant authority and powers of Customs officers; • Health and Safety (H&S); • Leadership and Communication; • Changing operating environment and world challenges. It’s important to note that all project training materials integrate the gender perspective whenever applicable, based on USAID’s Gender Equality and Female Empowerment (GEFE) Policy (2012) and ADS 201. Capacity Building Assessment During the first part of the project and specifically during the component one implementation period- Mobilization, Assessment, and Trade Facilitation Training, the project team analyzed, developed and provided a complete strategic assessment of current training capacity building within the organization. This assessment report outlined the current AGD training program and recommendations for the development of a modern and enhance training curriculum to ensure long-term sustainability for the AGD. It will require the AGD to focus on strategic development of an operational roadmap to forecast and plan present and future training requirements and needs. The diagram below illustrates that process. USAID / Haiti Customs Support Project – Final Report 19 It should be noted that the training needs analysis contained in this report is only one element of an overall Learning, Training and Development (LT&D) strategy. Summary of the Haitian Context The AGD is facing many challenges with accession to the WTO TFA and WCO RKC as well as other CARICOM initiatives and the devastating 2010 earthquakes. These together with the Minister of Economy and Finances (MEF) focus on revenue collection and compliance, the recent State Reform Framework Program, the overall Public Finances reform pilot by MEF and the strategic framework for the modernization of the AGD has added to the pressures on the organization to enhance its performance. Customs administration is a complex and highly technical area of public administration. Unlike many professional disciplines there are few opportunities available to gain professional qualifications relevant to customs administration. As such, most customs administrations throughout the world invest heavily in internal staff development and training. While the AGD staff attend minimal courses offered by the Customs Department and small numbers of staff can attend programs offered periodically by development partners there has not to date been a comprehensive human resource development strategy in place to address competency gaps that impact negatively on organizational performance. The AGD requires a strategy to manage their human resources and in particular develop the skill levels and competency of the employees to face the challenges lying before the organization and meet the operational priorities set by the government. The training courses designed and developed, were particularly appropriate, as the AGD is working toward becoming a self-sustaining organization with clear lines of communication and accountability. Many studies have demonstrated that strong communication is essential for attaining an organization’s objectives and maintaining strong relations at all levels, especially for those in a process of modernization. USAID / Haiti Customs Support Project – Final Report 20 Many training participants have extensive customs experience, with some serving in management or directorial positions. As organizational decision-makers, they are precisely the sort of employees this tutorial was designed for, and ideally positioned to implement its teachings. The course’s objective, then, was to engage the AGD’s leaders in discussion about how the training’s three strands coalesce to create and sustain strong organizations. Given the variety of training participants’ experiences, the training covered a wide range of border related topics in order to give participants a comprehensive overview of what is required in a border administration. The subject matter fostered spirited debate and many constructive conversations. Several exercises throughout the training helped participants put their learning to critical use. Overall, the trainings were well received, and the trainees participated enthusiastically throughout. Evaluation Methodology The project used the four-level Kirkpatrick Model of Evaluation to conduct training evaluations. The Kirkpatrick methodology ensures that the effectiveness and impact of the training are well measured, so that it can be improved in the future. Donald Kirkpatrick was Professor Emeritus at the University of Wisconsin and Past President of the American Society for Training and Development (ASTD). His four-level training evaluation methodology was first published in 1959 in the US Journal of Training and Development. The methodology was then updated in 1975, and again in 1994, when he published his best-known book, "Evaluation of Training Programs." The methodology is designed to determine the behavior of the one who received the training. It determines how much is transferred as knowledge, skills and attitudes to see if workplace behavior has changed as a result of the training. At this level, it is assessed to what extent employees have changed their behavior, based on the training they received, and more precisely, how they apply the information. It is important to realize that behavior cannot change if conditions are not favorable. For example, if the tools or mechanics needed to implement trade facilitation are not put in place, then it would be difficult to imagine a change in behavior among employees. Therefore, one could assume that the training was ineffective. On the other hand, it should be noted that if the behavior has not changed, it does not mean that the employees did not learn anything. As mentioned above, if there is a reform of tools and mechanisms to implement trade facilitation, then employees will have the opportunity to apply this new knowledge. At the end of each training, participants filled out a Level 1 evaluation, of the course and the trainers, and a Level 2 evaluation, of participants’ knowledge of the training subject matter. The results of these evaluations can be found in the appendixes. A Level 3 evaluation, of the extent to which trainees incorporate what they learned during training into their daily work, is carried USAID / Haiti Customs Support Project – Final Report 21 out three to six months after the training. A Level 4 evaluation to assess the training’s impact on organizational performance and the extent to which the training improves the processes and functioning of the organization, will be conducted at the end of the project. In order to collect the information, we used the Questionnaire Method, which is commonly used to ensure that the impact of learning is accurately measured and that evaluation data is easy to collect. Please note that our questionnaire was designed to maximize several aspects of the evaluation including: Opportunities to exploit • Obtain direct engagement with the operational side of the DGA to facilitate the development and maintenance of relationships and linkages between training and business requirements. • Identify potential improvements in training with respect to the skills and knowledge that learners need to integrate to better equip them with their roles and responsibilities. Risk mitigation • Lack of consistency in the methodology can create difficulties in comparing results. • Manage comments received to strengthen the collection of more scientific data. • Ensure active engagement of employees and management at the evaluation level. Evaluations of training content (Level 1) and subject matter acquisition (Level 2) were conducted at the end of trainings. As for the evaluation of the behavioral change (Level 3), with the exception of five courses that weren’t completed as the country had increased protest and security issues, this assessment was conducted six months from the completion of training to assess its impact on participants’ job performance. The Level 4 evaluation was a significant summary produced by the project of the overall affect of the courses on the AGD. That Level 4 Training Report was submitted as a deliverable to USAID. Security The prolonged security issues mentioned under Component III in this report also affected Component IV. The COP was not able to complete some of the Level 3 evaluations, as this required in=person meetings or enhanced online infrastructure for virtual evaluation, both of which were not possible given the situation with the AGD in Haiti. In this instance, the Nathan project team in consultation with the M&E project expert Erika Dunmire, determined that we had gathered enough data and information from previous Level 3 evaluations conducted over the last three years of training courses to make a general assumption about the behavioral change. This assumption will serve as an indication of the changes, since it isn’t possible at this time to obtain Level 3 evaluation data for certain courses. USAID / Haiti Customs Support Project – Final Report 22 Observation and Recommendations The events of January 12, 2010 have had a dramatic impact on the Administration Générale des Douanes program and the Administration has faced many challenges as it seeks to deter and detect non-compliance at the border. In our assessment report in 2016, we made several recommendations for managing the risks regarding capacity building within the Administration. We found that the Agency has made minimal progress in implementing our recommendations. We found that the Administration had developed a strategy for capacity building, but the government doesn’t invest in training, resulting in the AGD requesting funds from donors. We hope that by following the new strategic plan and implementing this action plan, the AGD will strengthen its capacity building and ensure that AGD meet its mandate and objectives. Until the strategy is fully implemented and a complete analysis is done, gaps will remain in the Administration’s risk assessments, border management and capacity building plans. Customs officers must administer customs legislation and parts of laws that govern other departments and agencies. They must know about passport and visa requirements, as well as laws that cover a broad range of products and services. Customs officers who work at the primary inspection line must quickly decide whether to let travellers and commercial shipments go on their way, or send them for a secondary inspection where they will be questioned more extensively and, in some cases, examined. Given the complexity of custo